1 MODAPS PIP Report June 25, 2013 1-866-738-1275 9454131#

2 Summary of MODAPS Production 6/25 Forward Processing (C5, C4.1 LST, 5.1 Atmosphere and Greenland IST) –Terra forward processing is at the leading edge. Aqua is 6 days behind due to maneuvers on days 170 and 171. –Collection 6 L1B Aqua and Terra processing is running in parallel with forward processing. –There are 41 files that the LPDAAC requires browse for. This data will be resent after all MOD07_L2 has been resent. –All of the MOD07_L2 data on the original list has been resent. LPDAAC has sent preliminary reconciliation for 2000-2011. We have resent 2000-2007 based on this. –We are waiting for 8 periods of MOD44C* data to begin reprocessing of C51 VCF (PGE61). –Sample C6 files have been sent to NSIDC and LPDAAC for ingest testing purposes. –We have received the inputs for the 2012 Land Cover products.

3 Summary of PGE Deliveries to SDST 6/25 Collections 5 and 5.1 Level 1: –None Land: –We baselined a new version of PGE11 (5.3.36) on 5/30. –We baselined a new version of PGE36 (5.5.0) on 6/4. Atmospheres: –None Collection 6 Level 1: –We baselined several new versions of PGE02 (6.1.21, 6.1.23, 6.1.25, 6.1.27) on 3/25. Atmospheres: –We baselined a new version of PGE04 (6.0.29) on 6/11. –We baselined a new version of PGE06 (6.0.60) on 5/30. –We baselined a new version of PGE69 (6.0.6) on 6/25. –We baselined a new version of PGE03 (6.0.24) on 5/30. –We baselined a new version of PGE70 (6.0.3) on 3/25. Land: –We baselined a new version of PGE23 (6.0.3) on 6/10. –We baselined a new version of PGE116 (6.0.16) on 6/17. –We baselined a new version of PGE25 (6.0.8) on 6/13. –We baselined a new version of PGE21 (6.0.4) on 6/10. –We baselined a new version of PGE07 (6.0.5) with new QIR on 5/23. –We baselined a new version of PGE34 (6.0.3) on 6/21. –We baselined a new version of PGE36/37/38 (6.0.1) on 6/19.

4 Summary of Science Testing 6/25 Atmospheres Science Testing: –An 8 month Terra PGE04 (6.0.27) test finished on 6/13. –An 8 month Terra PGE04 (6.0.28) test finished on 6/24. –A 4 month Terra and Aqua PGE06 (6.0.60) test finished 6/18. –A PGE04 (6.0.29) test finished on 6/23. –A PGE06 (6.0.61) test is planned. Land Science Testing: –A C6 Terra LSR test using C6 inputs has started; this covers the entire mission, and is running in parallel with forward processing as well. –The C6 Chain Test for Terra and Aqua is running. –A C6 LST PGE16 (6.3.2) test is running. –A PGE36/37 test using the new GEOS-5 subset (5.9.1) finished on 6/13. –An additional one tile test for PGE36/37 is being run. –A PGE116 (6.0.15) science test had multiple errors. This test was rerun with a new version (6.0.16) and again has a large number of errors. –A C6 PGE23 (6.0.3) 16 day test finished on 6/18. This test will need to be rerun. –A C5 PGE23 test is loaded. –A 5 year Terra and Aqua one tile test of PGE11/12/13 is running. L1 Science Testing: