Download presentation
Presentation is loading. Please wait.
Published byJustine Deary Modified over 9 years ago
1
Project Management OPER 576 Project Networks Greg Magnan, Ph.D. April 29, 2004
2
Project Life Cycle Stages
3
II. Project Planning 7.Sequence Deliverables To help schedule work efficiently Consider all WBS elements Estimate calendar duration for each List precedence for each task May construct network diagram CRITICAL PATH: longest path through the network showing minimum time needed Delays to elements on the critical path delay the entire project! Mascitelli: Critical Core
4
Activity Time Estimates PERT-based Assumptions: –“normal” operations –independent estimates for activities Optimistic / Most-likely / Pessimistic Formula (O + 4M + P)/6 Example (10 + 4*15 + 26)/6 = 16
5
Project Networks Developed from WBS –WBS must be deliverables-oriented! –Activity Labeling: use WBS outline as basis Used for Planning, scheduling, controlling Activities, sequences, precedence rel’ps Critical Path / “Crashing” network Basis for Resource Scheduling Communication to stakeholders Estimate of project duration
6
Network Terms Activity –An element in the project that consumes time, but doesn’t necessarily require resources (e.g., approvals, contract signing) “Events” do not consume time –Can include one or more Work Packages Verb/noun format Critical path –Path: a sequence of connected, dependent activities –CP: Longest path through the network Activity-on-Node (AON) vs. Activity-on-Arc (AOA) –AON is most commonly used (software packages) –Nodes reflect activities
7
AON Network Development Rules Arrows indicate precedence and flow –Flow from left to right –Precedence determined after WBS complete Predecessor and Successor activities –Preceding activities must be complete before beginning successor activities Activities need labels –Larger numbers than preceding activities No Looping! –No conditional (if/then) statements Single Start and End nodes
8
Project Scheduling: Node Elements
9
PERT Diagram (Activity on Node)
10
Sample Problem Activity Duration Predecessor A5none B10none C15A D10A E5B F20C G20E H5D, F, G I15H
11
Forward & Backward Pass Determine: –Early Start (ES) and Early Finish (EF) –Late Start (LS) and Late Finish (LF)…and then Slack Forward Pass (EF and ES) –For each path in the network, add activity times (duration) to each ES to get EF (ES + Dur = EF) –EF of preceding activity becomes ES of successor, unless Succeeding activity is a merge activity (>1 predecessor) Then select LARGEST EF time from all predecessor EF times to become ES for successor activity
12
Forward & Backward Pass Backward Pass (LF and LS) –Must have already completed Forward Pass –Start with the latest EF of last activity in the network –For each path in the network, subtract activity times (duration) from each LF to get LS (LF - Dur = LS) –LS of successor activity becomes LF of preceding, unless The next preceding activity is a burst activity (>1 successor) Then select SMALLEST LS time from all immediate successor activities to determine LF time
13
Conclusion… Projects are everywhere Can be actively managed Science AND art
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.