Network exercise (P2) Consider the PERT/CPM network shown below. D A 2

Similar presentations


Presentation on theme: "Network exercise (P2) Consider the PERT/CPM network shown below. D A 2"— Presentation transcript:

1 Network exercise (P2) Consider the PERT/CPM network shown below. D A 2
3 E F B G J 1 4 6 7 H C I 5 a. Add the dummy activities that will eliminate the problem of activities having the same starting and ending nodes.

2 Network exercise (P2) b. Add dummy activities that will satisfy the following immediate predecessor requirements: Immediate Activity Predecessor H B, C I B, C G D, E

3 Network exercise with time (P4)
Construct a PERT/CPM network for a project with the following activities and times: Activity Immediate Time Predecessor (months) A B C A D A E C, B F C, B G D, E a) Find the critical path for this project network. b) This project must be complete in 1 1/2 years; do you anticipate difficulty in meeting the deadline? Explain.

4 Consider the following network (P6) (times are in weeks)
7 2 5 A 5 F 3 D 6 H 8 1 G 10 4 6 B 3 E 7 3 a. Identify the critical path. b. How long will it take to complete this project? c. Can activity D be delayed without delaying the entire project? How about activity C? If so, how many weeks? d. What is the schedule for activity E?

5 Network exercise with time (P7)
A project involving the installation of a computer system consists of eight activities. The immediate predecessor and activity time in weeks are shown below: Activity Immediate Time Predecessor (weeks) A B C A 2 D B,C 5 E D 4 F E 3 G B,C 9 H F,G 3 a. Draw the PERT/CPM network for this project. b. What are the critical path activities? c. What is the expected project completion time?