Presentation is loading. Please wait.

Presentation is loading. Please wait.

P. Paolucci - I.N.F.N. di Napoli 1 30-01-2006 / Joint RPC-Trigger meeting HV-LV-DCS Status DCS barrel:G. Polese and P. Paolucci DCS endcap:A. Cimmino and.

Similar presentations


Presentation on theme: "P. Paolucci - I.N.F.N. di Napoli 1 30-01-2006 / Joint RPC-Trigger meeting HV-LV-DCS Status DCS barrel:G. Polese and P. Paolucci DCS endcap:A. Cimmino and."— Presentation transcript:

1 P. Paolucci - I.N.F.N. di Napoli 1 30-01-2006 / Joint RPC-Trigger meeting HV-LV-DCS Status DCS barrel:G. Polese and P. Paolucci DCS endcap:A. Cimmino and P. Paolucci HV & LV:D. Lomidze and P. Paolucci NEWS DCS Endcap Integration DCS Barrel Integration see Giovanni talk 1 PC with barrel project working at 904 1 PC with endcap project at 904 asap HV-LV test setup is going on at BLG 904

2 P. Paolucci - I.N.F.N. di Napoli 2 30-01-2006 / Joint RPC-Trigger meeting EASY Crate board/cratechannel/crate (max power) power/crate# crate/rackpower/rack# A3486 LV336 (11 watt/ch) < 900*1< 9001ch/rack HV4-524-30 (10 watt/ch) < 600**3< 18002ch/rack A3486 AC/DC has 2 channels of 2 KW each * 3 boards with safety factor 2 ** 6 boards with safety factor 2

3 P. Paolucci - I.N.F.N. di Napoli 3 30-01-2006 / Joint RPC-Trigger meeting EASY crate back schema

4 P. Paolucci - I.N.F.N. di Napoli 4 30-01-2006 / Joint RPC-Trigger meeting EASY crate connection schema ConnectorCostCablecost 48V powerAPP - 75A red/black + pin (14-8 awg) (2.1-8.2 mm2) 2.46 + 1.51 KW2.5 (black) + 2.5 (red) + 3.0 (2 pins) = 8.0 48V serviceAPP - 30A red/black + pin (16- 12 awg) (1.5-4 mm2) 0.52 + 0.270.1 KW0.52(black) + 0.52(red) + 0.54 (2 pins) = 1.58 EASY bus50 pins flat cable8.39Flat 50 wires EarthFork 7mm0.10

5 P. Paolucci - I.N.F.N. di Napoli 5 30-01-2006 / Joint RPC-Trigger meeting NEW USC55 barrel HV system General Information max HV EASY board: 7 ch. max EASY crate: 42 ch. HV distributor: 32 input ch (2 sectors) 16 output ch. Rack height tot:56 U turbine4 U air defl.2 U Rack available height 50 U Total: 72/96 ch. We need (per wheel/rack) 72 ch  12 HV boards (reduced*) 96 ch  16 HV boards (final) 3 EASY crate (4-4-4) (6-6-4) 3 FAN crates + heat exchange 6 distributors + 1 RB4-sect4 join * RB3 and RB4 joint together (12 + 12) 8U EASY 1 2 3 4 5 6 - fan tary heat exchange EASY 1 2 3 4 5 6 - fan tary heat exchange 8U EASY 1 2 3 4 - - - fan tary heat exchange 8U 44 U 36 input ch. 24 input ch. 48 output ch. 36 ch. 24 ch. 12 ch. 24 ch. HV distributor sect 11-12 HV distributor sect 09-10 sect 08-07 48 output ch. HV distributor sect 05-06 HV distributor sect 03-04 sect 01-02 HV distributor spare turbine 4U air deflector 2U S1H02-06

6 P. Paolucci - I.N.F.N. di Napoli 6 30-01-2006 / Joint RPC-Trigger meeting 34U AC/DC 48V power 3U 2x2 KW S1H07 turbine air deflector 2U 4U NEW USC55 HV barrel racks composition SY1527 HV SY1527 LV 8U AC/DC 48V power 3U 2x2 KW AC/DC 48V service 3U 2x2 KW HW numbers 15 EASY crates 60-80 HV boards A3512 360-480 HV channel 30+4 HV distributors 2 SY1527 mainframes 3 or 4 AC/DC 48 V - A3486 (or A3485) CABLE numbers EASY power (direct)5 EASY power (daisy)10 EASY service (direct)2 EASY service (daisy)14 Branch Contr. (direct)2 Branch Contr. (daisy)14 Fan unit contr.15 EASY Ground -15 SY1527 ground -2 480 HV input + 240 HV out AC/DC 48V power 3U 2x2 KW (spare ?) 136 components 800 cables

7 P. Paolucci - I.N.F.N. di Napoli 7 30-01-2006 / Joint RPC-Trigger meeting HV-LV status Setup at 904 is finished. MTCC setup is almost ready Setup ready for Cosmic Challenge in March 06 Move from 904 to SX5 in April 06

8 P. Paolucci - I.N.F.N. di Napoli 8 30-01-2006 / Joint RPC-Trigger meeting LV MTCC setup 2 LV EASY crates OK 2 LV boards A3009 (2 sectors) 1 LV board A3009 (1 sector) Short cables and connections are OK Waiting for lengths for long cables. 2 Control cables

9 P. Paolucci - I.N.F.N. di Napoli 9 30-01-2006 / Joint RPC-Trigger meeting HV MTCC setup 1 HV EASY crates OK 4 HV boards A3512 (3 sectors) Short cables and connections are OK Waiting for lengths for long cables. 3 multi-conductors cables

10 P. Paolucci - I.N.F.N. di Napoli 10 30-01-2006 / Joint RPC-Trigger meeting RPC DCS status Barrel and Endcap projects are ready Two PCs running the projects are at 904 Integration with CMS DCS is almost ready, some common problems still to fix RPC DCS will be ready for May 2006

11 P. Paolucci - I.N.F.N. di Napoli 11 30-01-2006 / Joint RPC-Trigger meeting Next Steps Define the hardware of the endcap system Install the system at SX5 Build and install long cables Test it in April-May to be ready for CC

12 HW schema for CC BC LV BC LV BC HV RPC - SY1527 HV – EASY – 24 ch. HV AC/DC HV – MAO – 2 ch. Balcony Barack 48 V – service LV Control LV Detector PWR HV Control HV W+2 W+1 LV – EASY – 12 ch. LV LV – MAO – 1 ch. LV – EASY – 24 ch. LV LV – MAO – 1 ch. PWR HV AC/DC 380 3-phase HV multicond. 10 ch.

13 30-01-2006 / Joint RPC- Trigger meetingP. Paolucci - I.N.F.N. di Napoli13 RPC FSM Hierarchy Endcap RPC Endcap Supervisor Disc Ring Chamber Barrel RPC Barrel Supervisor Device level Wheel Sector Chamber Channel HV/LV Sys CMS_RPC Since the last meeting: The endcap is up to date with the barrel and the two systems are proceeding in parallel Tests on CPU and RAM usage have brought us to reduce the number of CUs. Limiting to the top two levels. Possibility of using only wheels or disks in standalone mode as lower nodes. Introduction of a new level in the hierarchy. This will allows a better partitioning of the system. The two systems are under a single top node as required by the CMS DCS Integration guidelines. The two systems can also work standalone. Device level Channel HV/LV Sys NEW LEVEL CU LU

14 30-01-2006 / Joint RPC- Trigger meetingP. Paolucci - I.N.F.N. di Napoli14 RPC DCS for MTCC Endcap RPC Disc Ring Chamber Barrel RPC Device level Wheel Sector Chamber Channel HV/LV Sys CMS_RPC Since the last meeting: Intensive (2 weeks) test with HW at 904 building induced us to perform Minor changes to the FSM schema Redesign Hierarchy and distribution on more PCs. We are investigating How distribute the HW component on more PCs and the resources needed. Device level Channel HV/LV Sys PC01 Supervisor PC02 PC03.. PC04.. DATABASE We are able to receive and upload the HW setup into the project from Oracle DB We are able to download different configuration setup from DB for ON and StandBy states Conf. DB

15 30-01-2006 / Joint RPC- Trigger meetingP. Paolucci - I.N.F.N. di Napoli15 RPC DCS Integration Status We were successful in creating a first version of the CMS RPC sub- detector SUPERVISOR component using the tool provided by the JCOP framework. The RPC component contains both Endcap and Barrel trees, but it has been designed has two components that can work on different PCs. We accessed the Configuration DB. We are able to read from and write in it (in a private Oracle DB) using custom scripts with Framework functions. We still need to - know the coordinates of the DB we are going to use for the CC and test the best way to access the DB (different solutions are possible) - finish to prepare the hardware component (march 06) - work on the condition DB - temperature monitoring (waiting for JCOP FW)

16 16 CMS RPC Gas Monitor Frascati Group A monitoring system of the RPC work point which is able to provide much faster and sensitive response than the CMS RPC system. A monitoring system of the RPC work point which is able to provide much faster and sensitive response than the CMS RPC system. Monitor efficiency and charge continuously Monitor efficiency and charge continuously If work point changes, alarm goes off and DSC systems (GC,probes, etc) verify what the change of work point is due to. If work point changes, alarm goes off and DSC systems (GC,probes, etc) verify what the change of work point is due to.

17 17 RPC Gas Monitor v.1 C 2 H 2 F 4 /SF 6 /i-C 4 H 10 /H 2 O Slow Ctrl GC, p/T/RH/Ph RPC PAD source MONITOR RPC PAD source CMS RPC PAD source REFERENCE

18 18 DAQ system for the CMS RPC Gas Monitor The system must be integrated in the Slow Control (SC) of CMS RPC. This implies to follow the CMS standards for DAQ: PVSS or xDAQ The system must be integrated in the Slow Control (SC) of CMS RPC. This implies to follow the CMS standards for DAQ: PVSS or xDAQ We are evaluating different solutions in order to minimize the effort in the integration with CMS Slow Controls We are evaluating different solutions in order to minimize the effort in the integration with CMS Slow Controls Our present option is to use a system fully based on PVSS both for P,T, RH and HV, and both for ADC, (+TDC...+ other VME module) readout based on VME standard Our present option is to use a system fully based on PVSS both for P,T, RH and HV, and both for ADC, (+TDC...+ other VME module) readout based on VME standard Standalone systems (PICO, ACQIRIS, etc) do not seem to offer the same versatility of a VME system and comparable performances Standalone systems (PICO, ACQIRIS, etc) do not seem to offer the same versatility of a VME system and comparable performances VME readout via PVSS ? VME readout via PVSS ?

19 19 Temptative DAQ architecture for the CMS RPC Gas Monitor Pressure, temperature & humidity sensors VME modules for RPC pads readout ● Controller VME CAEN ● ADC V1724A - 8CH 14BIT 100MHZ ● Scaler V830AC - 32 Channel 32 Bit ● Crate VME8002 MINI VME64 09 SLOT ● TDC V1290A - 32 Ch /25 psec CAEN HV system PVSS CMS SlowControl ?


Download ppt "P. Paolucci - I.N.F.N. di Napoli 1 30-01-2006 / Joint RPC-Trigger meeting HV-LV-DCS Status DCS barrel:G. Polese and P. Paolucci DCS endcap:A. Cimmino and."

Similar presentations


Ads by Google