CITY OF SAN MARCOS/TEXAS STATE UNIVERSITY 2015 WORK PLAN BUDGETED CONSERVATION MEASURES
2
5.3.1/5.4.1Texas Wild-Rice Enhancement and Restoration Long-term Objective (Phase I): to establish 8000 m 2 of additional TWR (in addition to baseline of 4000 m 2 ) Target goal of 1100m 2 achieved for 2013 On track for 2014 Goal continued into 2015 Monitoring: 95% success rate in 2013 After USFWS survey, 2014 expansion can be determined
3
TWR Enhancement Budget Labor: $155,151 Travel (in-state): $1,000 Operations & Materials: $9,290 Equipment: $9,000 o Total: $174,441 Table 7.1 allocation for 2015: $175,000 Two percent increase: $3,500 Proposed Budget: $178,500
4
5.3.6/5.4.4 Sediment Removal Long-term Objective (Phase I) : Initial removal of targeted fine sediments from Spring Lake to IH-35 and then maintenance removal of sediment accumulations 2013 - Dropped bed elevation about two feet over an 86m 2 area at the two permitted locations 2014 – enlarging sites within the two permitted areas – expect to top out at 1000 m 2 (3000 m 2 was target) 2015 – will expand downstream with new permits to gain an additional 1000 m2
5
Sediment Removal Budget Labor: $185,151 Travel (in-state): $1,500 Operations & Materials: $14,000 Equipment: $20,000 o Total: $220,651 Table 7.1 allocation for 2015: $ 25,000 Remainder of initial funding: $500,000 (initial) - $151,800 (2013) & $150,000 (2014) = $198,200 remaining Proposed Budget: $223,200
6
It was initially assumed that sediment removal of entire reach from Spring Lake to Rio Vista dam would be accomplished in the first year. Thus the project was awarded full amount ($500K) in 2013, with maintenance funds ($25K) thereafter Not possible to spend the entire amount in the first year: TPWD permit allowed only the removal of 1750 CY in 2013 Physical and temporal limitations of this project Negative impacts on listed species $151,800 was requested for 2013, with the intent to spread the remainder over the next three years (2014-2016)
7
5.3.8/5.4.3/5.4.12Control of Non-Native Plant Species Long-term Objective (Phase I): Reduce density of invasive non-native aquatic & littoral plants Littoral: First sweep of elephant ears complete (2013 & 2014); maintenance and native plantings (2015) Aquatic: 1513 m2 (2013); pulled back sediment removal efforts to meet 2014 goal of removal & planting (Sewell, City and Bicentennial parks) 2015 – North Sewell and Rio Vista 2013 - $375,000 2014 - $175,000 2015 - $125,000
8
Control of Non-native Plants Budget Aquatic plant removal: $223,225.67 Plant propagation: $65,477 Littoral plant removal: $40,000 Equipment: $5,700.00 Expenses: $10,000.00 o Total: $344,402.67 Table 7.1 allocation for 2014: $125,000 Additional requested: $219,402.67 Proposed Budget: $344,402.67
9
5.7.1Native Riparian Habitat Restoration Long-term Objective: Establish a robust native riparian community that benefits Covered Species and the habitat quality adjacent to and within the San Marcos River down to IH-35 as well as prevents public access in undesirable locations which will decrease bank erosion. Two-thirds of the designated area has been planted with two sites remaining – Rio Vista (4050 sf) & Ramon Lucio (16,400 sf) Rio Vista - $29,497.50 Ramon Lucio - $190,554.00
10
Native Riparian Habitat Restoration Budget Table 7.1 allocation : $20,000 Amount required to complete both sites: $220,000 or $55,000 over 4 years Budget Plan: Transfer funds from Litter Removal (Measure 5.3.3) and Non-native Species Control (Measure 5.3.5) = $35,742.70 Proposed 2015 Budget: $55,000
11
The original Table 7.1 estimate was $100K in 2013 with maintenance funds ($20K) thereafter The Table 7.1 estimate was based on vegetative transects performed in 2011 by the USFWS Low bid estimates for restoration at $537,404 After the completion of the 2013 riparian restoration, the estimated amount required for project completion is $437,500 Requesting a move of $180,000 from HCP measure 5.7.6 – Impervious Cover/WQ Protection
12
5.3.3/5.4.3Management of Floating Vegetation Mats and Litter Long-term Objective: Minimize impacts of floating vegetation and litter on TWR stands and overall aquatic community within the San Marcos River Table 7.1 allocation for 2015: $80,000 Contract Amount: $48,798.10 Unused funds to be transferred to riparian effort: $28,701.90 Public Outreach Funds: $2,500.00 Proposed Budget: $80,000
13
5.3.5/5.3.9/5.4.11/5.4.13Non-Native Species Control Long-term Objective: Reduction of non-native, invasive species in the San Marcos River to levels that minimize their direct and indirect impacts on Covered Species and the aquatic ecosystem. Table 7.1 allocated funds: $35,000 Contract Amount: $24,960.00 Unused funds to be transferred to the riparian effort: $7,040.80 Public Outreach & 2% increase: $2,500 & $499.20 Proposed budget: $35,000
14
5.3.2/5.4.2Management of Recreation in Key Areas Target 2015/Performance Measure : Educate the public engaged in water-based recreation on sustainable river use that protects listed species and their habitats. Pick up litter in and along river Remove vegetation mats Monitor recreation behaviors and impacts on habitat Construct and clean TWR enclosures Monitor ongoing HCP projects Empty trash boats Survey TWR stands within enclosures Place signs and repair fence Educate river users Allocated funds for 2015: $ 56,000 Proposed Budget: $56,000
15
5.7.6Impervious Cover/Water Quality Protection Long-term Objective : Implement a program that minimizes the impacts associated with urbanization and changes in land use/cover in the Upper San Marcos watershed; manage stormwater as close to its source as possible, treat stormwater as a resource rather than a waste product; emphasize conservation and the use of on-site features to protect water quality; and increase infiltration to groundwater and aquifer recharge for the protection of riverine integrity. Table 7.1 allocation for 2015: $200,000 Proposed Budget: $200,000
16
5.7.5Management of Household Hazardous Waste Long-term Objective: Continue to provide a place for citizens of San Marcos and Hays County to safely dispose of HHW. Table 7.1 allocation for 2015: $30,000 Proposed Budget: $30,000
17
Sessom Creek Sand Bar Removal Budget o Table 7.1 allocation for 2014: $ 75,000 o As recommended by Dr. Hardy and agreed to by the Science Committee, this measure will be undertaken in a systematic manner over time while monitoring downstream impacts on existing Texas Wild Rice stands in Sewell Park. There is the possibility that this measure may continue into the winter of 2015 before the targeted removal is completed.