Final Program Environmental Impact Report Gillespie Field Development Council January 17, 2012 Item #5.

Similar presentations


Presentation on theme: "Final Program Environmental Impact Report Gillespie Field Development Council January 17, 2012 Item #5."— Presentation transcript:

1 Final Program Environmental Impact Report Gillespie Field Development Council January 17, 2012 Item #5

2 Gillespie Field 70-acre Redevelopment Project: Vicinity Map 2

3  Redevelopment of the vacant 70-acre site  County – Infrastructure Improvements  Private Developers – Aviation Use Development 3

4  Meet existing unmet and forecast market demand  Comply with Federal grant assurances  Revenue-generating asset to the County and the surrounding communities 4

5 Biological Resources Hazardous Materials Traffic & Transportation 5

6  Public Review of Draft Program EIR  September 15 – November 7, 2011  Gillespie Field Development Council supported project on September 20, 2011  Draft Program EIR Public Review Open House on October 5, 2011 6

7  87 public comment letters received  70 in favor of Proposed Project  Expansion of aviation facilities  Economic growth  7 against Proposed Project  Noise and safety concerns under flight path  10 neutral ( responsible agencies and stakeholders )  Program EIR analysis 7

8  March 14, 2012 – CEQA Final Program EIR certification by Board of Supervisors  NEPA Draft EA  Public review tentatively anticipated February 2012  FAA EA completion tentatively anticipated May 2012 8

9 PhaseDescription Cost (millions)ACIP FAA Grants received to date$0.4Past AEF spent on Environmental and Preliminary Engineering$1.0Past IEnvironmental and Design$2.72012-2013 II Grading, Drainage and Street Improvements$15.02014 III Taxiways, Ramps and Utilities for first 4 Parcels$11.52015 Total$30.6 FAA contribution $27.9 mil AEF contribution $ 2.7 mil 9

10  4 parcels in initial private development phase - Total 19.82 Acres  Remaining 4 parcels developed in future  Timing dependant on funding and need 10

11  RFP to GFDCSep 2013  Publish RFPNov 2013  Select Semi-finalists Jul 2014  Select DevelopersJan 2015  BOS ApprovalAug 2015  Private Construction Start Jan 2016 11

12  Meets forecasted growth, regional goals, TAF  Increased facilities for General Aviation  Annual revenue - $285K initial/$792K project  Private investment - $27M initial/$67M project  Annual tax increment- $272K initial/$670K project  Cajon Air Center project jobs  Construction - 700 initial/1,200 project  Aviation - 200 initial/440 project 12

13  Economic Impact Study prepared by CIC Research  Annual Gillespie Field Economic Benefit  Direct $403M / 3,164 jobs  Total Economic Activity $919M / 6,250 jobs  Gov Revenue $9.9M local /$51.2M federal/state  2025 (After Development) Annual Projection  Direct $530M / 4,190 jobs  Total Economic Activity $1.2B / 8,250 jobs  Gov Revenue $13M local /$67.2M federal/state 13

14 The Gillespie Field Development Council recommends the County of San Diego Board of Supervisors approve the Gillespie Field 70-Acre Redevelopment Project, certify the Program Level Environmental Impact Report and authorize DPW to apply for and accept grant funds for construction of the project. 14


Download ppt "Final Program Environmental Impact Report Gillespie Field Development Council January 17, 2012 Item #5."