Space Reallocation Update October, 2007. Summary “Almost” on time “Almost” on time Definitely under budget Definitely under budget Thanks to all for their.

Similar presentations


Presentation on theme: "Space Reallocation Update October, 2007. Summary “Almost” on time “Almost” on time Definitely under budget Definitely under budget Thanks to all for their."— Presentation transcript:

1 Space Reallocation Update October, 2007

2 Summary “Almost” on time “Almost” on time Definitely under budget Definitely under budget Thanks to all for their patience and good humour Thanks to all for their patience and good humour Lots of “small things” yet to do Lots of “small things” yet to do

3 Ferrier Building Everyone has moved in Everyone has moved in Still need signs Still need signs Some final details still to complete Some final details still to complete Access to Ferrier opposite James Building (to 1 st floor), from Dr. Penfield (to 3 rd floor), and from 3 rd floor of Arts (to 3 rd floor) Access to Ferrier opposite James Building (to 1 st floor), from Dr. Penfield (to 3 rd floor), and from 3 rd floor of Arts (to 3 rd floor)

4 Arts Computer Lab in May

5 Arts Computer Lab in September

6 The Art Computer Lab Help Desk

7 Department of History Workspace (May)

8 Department of History Workspace in September

9 The Beaverbrook Conference Room

10 The Arts Lounge (Ferrier 2 nd floor)

11 The Courtyard Construction should start very soon Construction should start very soon Noisy work to be done ONLY early in the morning Noisy work to be done ONLY early in the morning

12 Courtyard looking east

13 Courtyard looking west

14 Down the Slope

15 Arts West: DLLF

16 “Ready to Roll” The Computer Classroom: Leacock 212 New lighting is operational New lighting is operational Computers are now installed Computers are now installed Most software is installed Most software is installed The pedagogical options are unparalleled The pedagogical options are unparalleled To learn more and to be given a demonstration of our state-of-the-art classroom, contact Mary MacKinnon To learn more and to be given a demonstration of our state-of-the-art classroom, contact Mary MacKinnon

17 Leacock 212: The Computer Classroom (prior to the installation of the computers)

18 What’s Next ? How can we best integrate numerous projects in Peterson Hall? (washrooms, CFI projects, general repairs to offices, ventilation, and more) How can we best integrate numerous projects in Peterson Hall? (washrooms, CFI projects, general repairs to offices, ventilation, and more) How can we make the best use of our new assets? (especially the computer classroom and breakout rooms in Leacock) How can we make the best use of our new assets? (especially the computer classroom and breakout rooms in Leacock) Installation of the computers at the Stand-up computer stations in the Leacock corridor Installation of the computers at the Stand-up computer stations in the Leacock corridor Installation of the printers in Leacock by Snax Installation of the printers in Leacock by Snax