Presentation is loading. Please wait.

Presentation is loading. Please wait.

PLANNING FOR WIND AND QUEUE MANAGEMENT

Similar presentations


Presentation on theme: "PLANNING FOR WIND AND QUEUE MANAGEMENT"— Presentation transcript:

1 PLANNING FOR WIND AND QUEUE MANAGEMENT
Turkish Electricity Transmission Corporation(TEIAS) prepared by Gül Okan & Nurhan Ozan

2 400 kV Network KARADENİZ AKDENİZ GÜRCİSTAN ERMENİSTAN İRAN IRAK
BULGARİSTAN DIMODICHEV KARADENİZ HABİPLER BATUM GÜRCİSTAN BABAESKİ HAMİTABAT ALİBEYKÖY AHALTSIKHE İKİTELLİ A.ALANI AMASRA BOYABAT SAMSUN DGKÇ BORASCO YUNANİSTAN D.PAŞA Y.TEPE HOPA FILIPPI KAPTAN BEYKOZ PAŞAKÖY Z.KÖY EREĞLİ BORÇKA UNIMAR AMBARLI OSMANCA ÇARŞAMBA ÜMRANİYE ÇANKIRI DERİNER GUMRI İÇDAŞ TEPEÖREN ADA-GEBZE ARKUN ERMENİSTAN KARABİGA ADAPAZARI BAĞLUM TİREBOLU KALKANDERE YUSUFELİ KARS ÇAYIRHAN KAYABAŞI H.UĞURLU GÖKÇEKAYA SİNCAN ORDU-2 İSPİR İÇDAŞ BURSA K.KALE DGKÇ IĞDIR ÇAN BALIKESİR TEMELLİ GÖLBAŞI AKINCI TUNÇBİLEK İÇANADOLU DGKÇ SİVAS DEÇEKO AĞRI BABEK KANGAL ÖZLÜCE HORASAN SOMA SEYİTÖMER KAYSERİ ERZURUM D.BEYAZIT KEBAN VAN BAZARGAN KOCATEPE ELBİSTAN KHOY ALİAĞA MANİSA KARAKAYA İRAN YEŞİLHİSAR DİYARBAKIR ÇETİN IŞIKLAR KONYA HİLVAN BATMAN SİİRT UZUNDERE DENİZLİ AYDIN YEDİGÖZE ANDIRIN ATATÜRK ILISU SEYDİŞEHİR KAVŞAK SİLOPİ TES V.ŞEHİR YENİKÖY PS3 YATAĞAN OYMAPINAR ADANA G.ANTEP Ş.URFA ERZİN BİRECİK CİZRE KEMERKÖY KIZILTEPE ZAKHO ERMENEK KAYRAKTEPE AKSA VARSAK MERSİN IRAK İSKENDERUN İSDEMİR MUSUL TEİAŞ-APK 2010 HATAY TS (PLANLANAN) HALEP TS (MEVCUT) HES (PLANLANAN) AKDENİZ SURİYE HES (MEVCUT) TL (MEVCUT) TL (PLANLANAN) 220 kV EİH 154 kV EİH

3 Profile of System (end of 2010)
NUMBER OF SUBSTATIONS: 400 kV (35020 MVA) 154 kV (58015 MVA) 66 kV (637 MVA) TOTAL INSTALLED CAPACITY (93672 MVA) LENGTH OF TRANSMISSION LINES (km): 400 kV ,623 154 kV ,932 220 kV ,5 66 kV ,5 154 kV Cable ,9 380 kV Cable ,3 TOTAL ,148

4 Generation & Demand (for the year of 2010)
Installed Capacity MW Hydro+Renewable % Hydro % & Renewables 2.7 % Thermal % Annual Consumption 208 TWh Peak Demand MW (13 August 2010)

5 Topics Brief history of interconnection queue
Challenges while planning Tariff Policy Queue Management Future Efforts

6 Brief History of Queues
First WPP commissioned in: 1998 Number of the wind pp’s in operation are: 39 and total capacity: 1320 MW Current Licensed wind generation: 3483 MW Date: 1th November 2007 Number of the wind pp’s: 722 Total capacity: MW According to the system available capacity for connecting wind generation which is equal to 8474 MW a bidding code was prepared by TEIAS which includes the requirements for the applications. According to the bidding document the wind owner which will get the right to use the open capacity has to pay an amount to TEIAS for 20 years since connecting to the system which is equal the amount which will be calculated for per kwh generation of the wind power plant.

7 Wind power plant application areas

8 Recent Situation for Wind Generation in Turkey
3483 MW of wind applications has been licensed by EMRA 1320 MW is in Operation 2283 MW is Underconstruction 8488 MW is under evaluation The amount of the available wind generation capacity can be connected to the system until 2013 is MW In the strategy document it is foreseen that the total wind generation capacity will reach to MW until 2023.

9 The available wind generation capacity around 8488 MW is under evaluation

10 Marmara & Thrace Region available wind generation capacity ~ 2745 MW is under evaluation

11 Aegean Region available wind generation capacity around 2499 MW is under evaluation

12 Hatay Region available wind generation capacity around 190 MW is under evaluation

13 Challenges while planning
Available system reserve The required reinforcements for connecting WPP’s into power system. The difficulty to guess their production time of wind power plants. Who pays the investments and how it will be recovered Beside load flow, voltage profile, short-circuit and contingency studies; the %5 of the short circuit power of the substation which WPP will be connected is applied as a restriction criteria in order to keep the overall system security by now. Detailed dynamic studies for determining the connection capacities are going on.

14 INCENTIVES FOR RENEWABLE POWER PLANTS
The Turkey’s Parliament approved a new law 29 December 2010 on regulating the renewable energy resources market in Turkey. The incentives which are applied for Renewable Power Plants with the new law guarantees a price of: Hydro PPs and WPPs are paid at system marginal price, but minimum 7.3 US$ /MWh is guaranteed Geothermal PPs are paid at system marginal price, but minimum 10.5 US$ /MWh is guaranteed Biogas PPs and Solar PPs are paid at system marginal price, but minimum 13.3 US$ /MWh is guaranteed Those tariffs shall be valid for the PPs which came into service between 18 May 2005 to 31 December 2015 and will be applied for 10 years. After 31 December 2015, new tariff shall be given by the Government but the new tariff shall not exceed the tariff above.

15 Queue Management Process:
The available capacity for connecting wind generations are published by TEİAS. WPP applications are forwarded to EMRA (Turkish Regulatory Agency) for these capacities. These applications are forwarded to TEIAS for studying connection opportunities. TEIAS gives its comment concerning the availability.If the application is alone in the substation, EMRA gives license to those applications. If there are multiple applications, bidding process is done by TEIAS to determine the owner of the capacity. After taking license the investor sign a connection agreement with TEIAS. Project will be approved by MENR after the realization of the project System Usage Agreement will be done with TEIAS.

16 Queue Management Principle of connection cost sharing in between TSO and investor: If the investor pays for the connection line then the TSO will pay back to the investor this amount in 10 years from the investment budget. Otherwise, TSO will put the required investment for the connection of the power plant in it’s yearly investment plan and these procedures takes approximately 3-5 years for bidding (plus constructing period)

17 Planning Process by TEIAS
Turkish Electricity Transmission Corporation responsible from the WPP integration studies and to define the available capacity for connecting wind generation According to the results of load flow, contingency analyses and short circuit power calculations, the estimation for capacity for each substation and each region which will be available for connecting wind generation are defined by TEIAS Concentrated small wind generations in one region are collected in one substation (example: Çeşme Region) We have a specific grid code which defines the connection criteria for wind generation but it will be revised for future power system conditions.

18 ÇEŞME REGION WIND PROJECTS: 460 MW
21 km 380 kV 3 Cardinal 55 km 380 kV 3 Cardinal 380/OG kV Karaburun SS 380/OG Çeşme HAVZA SS 380/154 kV Uzundere SS 380/OG 125 MVA 380/OG 150 MVA 16,2 km 380 kV 2 Cardinal 31 km 154 kV 2x1272 MCM 154/OG URLA HAVZA SS OG OG Zeytineli-2 RES ,5 MW 10 km 7 km ~ ~ Karaburun RES MW 154/OG 50 MVA 154/OG 50 MVA 154/OG 50 MVA 12 km ~ Karadağ RES ,25MW 14 km ~ Mordoğan RES ,8 MW OG OG OG 17 km 10 km ~ Ovacık RES 18 MW Urla RES 15 MW ~ 5 km ~ Mordoğan RES ,75 MW Çeşme RES 16 MW 26 km 11 km ~ 10 km Seferihisar RES 14 MW ~ ~ Alaçatı RES 16 MW 9 km ~ Yaylaköy RES 15 MW 9 km ~ Seferihisar RES 16 MW Germiyan RES 10,8 MW 4 km ~ 11 km Korkmaz RES MW ~ ~ 13 km Urla RES 13 MW Sarpıncık RES 32 MW ~ 6 km Demircili RES 40 MW ~ SS TOTAL CAP: 211,55 MW SS TOTAL CAP: 139,55 MW SS TOTAL CAP: 109 MW

19 Future Efforts The wind forecast system has been developed by Turkish State Meteorological Service which is available to provide information about the wind forecasts for different heights and for 48 hours with 4 km. solubility all around Turkey. The trial tests are going on in order to improve the system. Specific monitoring system for wind generation will be installed and the procedures are going on with consultant company

20 Thank You for Your Attention !


Download ppt "PLANNING FOR WIND AND QUEUE MANAGEMENT"

Similar presentations


Ads by Google