Presentation is loading. Please wait.

Presentation is loading. Please wait.

Laser Deposited and Pre-Hardened Steel Rapid Tooling Case Western Reserve University / NADCA David Schwam.

Similar presentations


Presentation on theme: "Laser Deposited and Pre-Hardened Steel Rapid Tooling Case Western Reserve University / NADCA David Schwam."— Presentation transcript:

1 Laser Deposited and Pre-Hardened Steel Rapid Tooling Case Western Reserve University / NADCA David Schwam

2 Die Cast Aluminum Heat Sinks for Tank Tracks ABSORBS HEAT FROM THE RUBBER, EXTEND TRACK LIFE, PREVENT STRIP-OFF FAILURE Material: A380 Size:4.5”x2.5”x1.15” Weight: 1.1 pounds

3 Key Advantage: Short lead time. 49,000 parts (x4) were die cast with this pre-hardened tool. Industrial Partner: St. Clair Die Casting, St. Clair. MO Die Material: Pre-hardened 42 HRC Dievar Leadtime: Three weeks Die Cast Aluminum Heat Sinks for Tank Tracks

4 Shovel Nut DLA part. Industrial Partner: Empire Die Casting-Twinsburg, OH Die Material: Pre-hardened 42 HRC Dievar Leadtime: Three weeks (instead of 14 weeks) Key Advantage: Two hundred prototype parts were initially required. Production run is expected to exceed 100,000. So far at 49,000. The projects is running production with the prototyping tool, thus saving the entire cost of tooling.

5 DRS’s Driver’s Vision Enhancer (DVE) Display Control Module (DCM) is a 10.4" liquid-crystal display (LCD) providing a rugged display technology to the warfighter on today’s digital battlefield. Display Control Module

6 Warfighter Relevance

7 Objectives Problem Current tool building practices are costly and time consuming require sequential rough machining heat treating machining to final size use steel that does not allow fast heat removal and optimal control of the thermal profile Objective Demonstrate rapid tooling methods Use of pre-hardened steels to shorten lead times and extend die life Use of high thermal conductivity materials including Toolox 44, Anviloy and laser deposited rapid and bi- metallic tooling to improve rate of production

8 Benefits Accelerate fabrication of parts made by metal mold technologies Rapid tooling for die and permanent mold casting –More adaptive to frequent changes in design than traditional tool making methods –Can quickly provide small, prototype batches yet, if needed, make production quantities Demonstrate increased productivity and better mechanical properties of the castings by use of high thermal conductivity die materials

9 Technical Approach Use of high thermal conductivity materials (laser deposited H13 on copper, Toolox 44 and Anviloy cores) Utilization of pre-hardened advanced steels to shorten lead-time and lower tooling cost

10 Utilization of Pre-Hardened Superior Steels to Shorten Lead-Time and Lower Tooling Cost

11 Display Control Module

12 Implementation at Twin Cities Die Casting Anticipated production was 40,000 parts Using Pre-hardened tool steels of various types. Heat treat was 40 – 42 RC. Machining method was primarily High Speed but some Electro-Discharge Machining also.

13 Project Volume Increased Original plan was to cast no more than 40,000 parts. Tooling started to show some washout and heat checking around 20,000 shots. Notified by customer that there would be a second order coming after completing the first 40,000 parts.

14 Heat Check and Washout Inside after 24,000 shots

15 Heat Checking Outside after 24,000 Shots

16 Steel Repair Method Steel checked for hardness. Steel had softened through usage to 39–40 HRC down from 40-42 HRC. Cavity steel was ultrasonically cleaned, machined, welded and re-cut, polished and then nitrocarburized after 28,000 shots. Repair lasted balance of first order.

17 After Repair at 38,000 Shots

18

19 Tool Steel after First 40,000 Shots

20 Next Order is Being Processed for 20,000 Parts Steel has been polished and then Shot Peened. Nitride re-applied after last maintenance. Steel checks 39–40 HRC; no change from 20,000 shots. Estimated life to replacement is another 40,000 shots. Cost and time metrics needed

21 Use of High Thermal Conductivity Materials: Laser Deposited H13 on Copper, Toolox 44 and Anviloy cores

22 Rapid Tooling Method 1 *-Courtesy POM Direct Metal Deposition of H13 on Copper - the POM Method

23 Die Cast Part for Evaluation of Improved Cores The core is surrounded by molten aluminum therefore overheats and solders. Extracting heat more efficiently from the core can lower temperature, prevent soldering and allow shorter cycle times.

24 H13 Deposited on Cu – ready for machining

25 H13/ Copper Core after 250 cycles The core creeps due to insufficient stiffness and strength at high temperature.

26 Remedial Approaches Caves in Bulges out The distortion of the core seems to originate from insufficient strength and stiffness at the operating temperature. Anviloy and H13 cores do not suffer from this problem. Priority 1 - Increase strength: use core as deposited w/o tempering (downside-lower toughness). Priority 2 - Increase thickness of H13 layer(downside- slows down heat transfer). Use computer simulation

27 Technical Progress The life of the laser deposited core has been extended to 5,000+ shots. A computer modeling effort is underway to optimize the thickness of the laser deposited H13 layer. Other high thermal conductivity die materials (Toolox 44, Anviloy) are being tested. A current NADCA/NEMAK/GM project is leveraging this effort.

28 Finite Element Model Axi-symmetric analysis model Temperature variation along outer surface 300 o F constant 1 cycle cavity fill solidification Steel H13 Copper Alloy

29 Temperature and stress field at the end of cavity fill (deformation is enlarged by 100) Temperature ( o F) σ Von Mises (Psi)

30 Project Plans High cooling rates the mechanical properties. Shown is the improvement in Dendrite Arm Spacing (DAS) and respective tensile strength caused by a water cooled core.

31 Improving Mechanical Properties with High Thermal Conductivity Cores High thermal conductivity, cooled cores in die cast aluminum blocks

32 32 H13 Anviloy 3C CuBe Toolox 44

33 Continue Utilization of Pre-Hardened Superior Steels to Shorten Lead-Time and Lower Tooling Cost for Control Display Module A computer modeling effort is underway to optimize the thickness of the laser deposited H13 layer. Project Plans

34 Implementation

35 Conclusions Use of high conductivity alloys in die components can shorten cycle time significantly. In the present case, the cycle time dropped from 55 sec. for H13 to 40 sec.(13% ) The life of a tempered, 40HRC H13/ Copper laser deposited core was 250 cycles. By using the core in the as-deposited condition at 51HRC, life was extended to 5,000+ cycles and going. The balance between strength and toughness is critical to ensure durability of the core. High strength is required to prevent distortion while high toughness avoids cracking.

36 DescriptionBaselineGoalTarget Date (Month/Year) Progress% Accomp. Toughness Spray formed 6 ft-lb8 ft-lbDec 20087.75 ft-lb87.5% No. Shots Pre- Hardened 10,000 shots(P20) 30,000July 200920,000 in progress50% Enhanced cooling Spray formed – Die Temperature Die Surface 800 o F Die Surface 700 o F July 2010720 o F80% Improved Elongation Cooled core- 0.5%2%July 2010New task for 2009/2010 Project Metrics

37 JDMTP Criteria - Summary Jointness B – Benefit to more than one service, but not jointly funded Needs and Benefits Needs : Short lead times for rapid prototyping and legacy parts. Benefits: Up to 75% shorter lead time, depending on the part. Benefits: 20% shorter cycle time Transition Parts under evaluation at Empire Die Casting-2007 Parts under evaluation at St. Clair Die Casting-2007 Production of new part at Twin City Die Casting Composite cores in production at General Die Casters Results disseminated through NADCA committee meetings, NADCA publications for industry, and the Metalcasting Congress Leveraging Building on previous AMC and NADCA/DOE work Leveraged by current NADCA/NEMAK/GM project Relevance to Sustainment of Weapons Systems Strengthen supply chain by increasing number of metal mold suppliers able to meet DLA requirements. Shorten lead time for procurement of components for legacy systems. Improved mechanical properties of components. MRL 6 - Manufacturing capability to produce in a production representative environment

38 DLA - POC: Dean Hutchins (dean.hutchins@dla.mil, 804-279-5033) Problems: Standard tooling for metal mold processes requires long lead times High cycle times in the production of metal mold castings Objective: Evaluate advanced cooling techniques and rapid tooling techniques to reduce lead times Benefits: Demonstrate increased productivity by utilizing rapid tooling techniques and improve properties by incorporating high thermal conductivity die materials Milestones / Deliverables Evaluation of toughness and thermal fatigue of dies with deposited materials Optimization of laser deposited H13 layer Transition Plan The optimized laser deposited cores will be evaluated in production Partners: –Case Western Reserve, Twin City Die Casting, POM, DCD, NADCA, St. Clair Die Casting, Genral Die Casting, Empire Die Casting Laser Deposited and Pre-Hardened Steel Rapid Tooling


Download ppt "Laser Deposited and Pre-Hardened Steel Rapid Tooling Case Western Reserve University / NADCA David Schwam."

Similar presentations


Ads by Google