1 Contractors Networking & Teaming Forum January 17, 2012
FORT BLISS HOSPITAL REPLACEMENT PROJECT EL P ASO, TEXAS El Paso Community College Contractors Networking & Teaming Forum January 17, 2012 Jeffrey Allen, Senior Project Manager, USACE, Ft. Worth District Mitchell Alguadich, Senior Project Manager, HDR Architects Maurice Salata, Senior Architect, HDR Architects

2 Contractors Networking & Teaming Forum
Project Team Overview Project Award Packages Projected Schedule HDR Presentation 2

3 HA/TMA – Health Affairs/Tricare Management Activity
Project Team HA/TMA – Health Affairs/Tricare Management Activity ACSFAC (MEDCOM) – Assistant Chief of Staff, Facilities HFPA – Army Health Facilities Planning Agency WBAMC – William Beaumont Army Medical Center USACE Ft. Worth District / Ft. Bliss Program Office Ft. Bliss Garrison Contractors Infrastructure Project – Sundt Construction, Inc. Water Tower Project – Jamco Ventures, LLC

4 Overview Ft. Bliss Hospital Replacement project includes a M square foot World-Class Medical Facility Replaces William Beaumont Army Medical Center (WBAMC) Design-Bid-Build execution Campus buildings & features include - hospital, clinics, admin, research, central utility plant, access control points, therapeutic gardens, nature trails, and surface parking The Project Delivery Team have endeavored to incorporate state-of-art design ideas including the latest in Evidence-Based Design (EBD) and Sustainability as well as design innovations promoting family and patient-centered care

5 Project Award Packages
MAGNITUDE PLANNED SOLICITATION* PLANNED AWARD* INFRASTRUCTURE - JUL 2011 WATER TOWER JUN 2011 HOSPITAL >$500 M JUL 2012 DEC 2012 PARKING A $5 – 10 M APR 2012 HELIPAD $500 K - 1 M MAR 2013 JUN 2013 PARKING B $1 – 5 M OCT 2013 DEC 2013 ACCESS CONTROL POINTS $ M MAR 2014 LANDSCAPING $10 – 25 M *Dates subject to change 5

6 Projected Schedule (calendar year)
CONSTRUCTION PHASING* 2011 2012 2013 2014 2015 2016 2017 Q1 Q2 Q3 Q4 Water Tower MAY 11 - SEPT 12 Infrastructure AUG 11 - DEC 12 Parking A JUL12 – FEB 14 Hospital DEC 12 – JAN 16 Helipad JUN 13 – JUN 14 Parking B DEC 13 – MAR 15 ACPs MAR 14 – DEC 15 Landscaping Current Quarter Legend *Dates subject to change Construction Duration Construction in-Progress/Duration Construction Completion Initial Outfitting / Transition FOD – Facility Operations Date 6