LOR-U.S. 20 / S.R. 113 Center Ridge Rd. Widening Center Ridge Rd. at Avon Belden Rd. (S.R. 83)

Similar presentations


Presentation on theme: "LOR-U.S. 20 / S.R. 113 Center Ridge Rd. Widening Center Ridge Rd. at Avon Belden Rd. (S.R. 83)"— Presentation transcript:

1 LOR-U.S. 20 / S.R. 113 Center Ridge Rd. Widening Center Ridge Rd. at Avon Belden Rd. (S.R. 83)

2 LOR-U.S. 20 / S.R. 113 Center Ridge Rd. at Jaycox Rd. Center Ridge Rd. is the main east-west route and commercial area in the city.

3 LOR-U.S. 20 / S.R. 113 The project includes widening Center Ridge Rd. from 3 to 5 lanes, upgrading of traffic signals, addition of turn lanes, a 10’ wide multi-use path on the south side, and a 6’ wide sidewalk on the north side.

4 LOR-U.S. 20 / S.R. 113 The approximate length of the project is 2.3 miles from Stoney Ridge Rd. to Lear Nagle Rd. Ohio Turnpike Exits 151 and 152 are located approximately 1.5 miles from the intersection of Center Ridge Rd. and Lear Nagle Rd.

5 LOR-U.S. 20 / S.R. 113 The existing roadway is currently exceeding its capacity with an average daily traffic of over 16,900 vehicles per day.

6 LOR-U.S. 20 / S.R. 113 The project will address safety concerns and reduce the number of accidents.

7 LOR-U.S. 20 / S.R. 113 Project will relieve traffic congestion.

8 LOR-U.S. 20 / S.R. 113 T he project will correct geometric deficiencies such as the offset intersection at Root Rd. and Ridgeview Blvd.

9 LOR US 20/SR 113 Project Status Preliminary Engineering Completed Detail DesignCompleted Environmental Clearance Completed Right of WayIn Progress ConstructionOn Schedule and Budget for 2017

10 LOR US 20 / SR 113 Right of Way Summary Property Impacts 270 Parcels:Includes Temporary, Permanent, Easements, Relocations 43 Relocations:17 Owners;26 Tenants = Total 43 Acquisition Status 27 parcels have signed agreements 186 in negotiations 57 parcels in appraisal status Right of Way Phase completed by May 2015

11 LOR-U.S. 20 / S.R. 113 Right of Way Cost Estimate 2013 Application2014 Application Acquisition$9,500,000 (155)$12,753,200 (227) Relocation Costs$2,000,000 (23)$2,438,000 (43) Contingencies (20%)$3,020,240 Real Estate Services$2,198,500 Total R/W Costs$11,500,000$20,409,940

12 LOR US 20 / SR 113 Thank You! Questions?


Download ppt "LOR-U.S. 20 / S.R. 113 Center Ridge Rd. Widening Center Ridge Rd. at Avon Belden Rd. (S.R. 83)"