1 Financial Status (FS):UK £7.5M commitment OST+PPARC+CCLRC +£750k working margin (wm:10% attributed to UK tasks) +£1.5M contingency (OST control) =£9.7M.

Similar presentations


Presentation on theme: "1 Financial Status (FS):UK £7.5M commitment OST+PPARC+CCLRC +£750k working margin (wm:10% attributed to UK tasks) +£1.5M contingency (OST control) =£9.7M."— Presentation transcript:

1 1 Financial Status (FS):UK £7.5M commitment OST+PPARC+CCLRC +£750k working margin (wm:10% attributed to UK tasks) +£1.5M contingency (OST control) =£9.7M –Spend to date is light (<£1.5M) –Rapidly changing Move from design to manufacture

2 2 FS:UK Task budget break down: Control of scope: –PSAG/CMPB/PPARC-OsC

3 3 FS:UK Calls on UK contingency: Oct’05: £720k for solenoid cryogenics – £287k over budget (despite guide price) – re-evaluated cooling budget; » freed £200k (but kept original c&wm : risk  ) – £90k call on contingency (plus £43k from wm) –Accepted by PPARC: funds drawn from OST Done under change control (interim CMPB) –painful process »needed effort and caused delay! Lesson learnt: danger of single response tenders

4 4 FS:UK Potential calls on UK contingency: –Shielding Cause: escalation of requirement over plan (negotiating) Remedy: Shielding available on site at DL –(RAL’s sister laboratory) – negotiations in progress Unbudgeted items: Steering magnets, Q35 refurb. (~£50k within wm on BL) Note: Achieved £50k saving on import of decay solenoid from PSI – kept within beam line budget. Staff: –Additional local DAQ effort needed Potential extra because of stretch of phase 1.

5 5 Additional Contributions:UK Risk Reduction: £92k additional funds to help tracker solenoid: End-of-year (WFL) funds –Mechanism: UK paid for items in US & Jp budget: need to realise benefit »US: released existing MRI funds ; »Jp: Bid £30k risk borne by ISIS for phase 2 –Procure tube bases for RF power source

6 6 Current Procurement:UK –Cryogenics for decay solenoid (on order) –Hydride bed (on order) –RF test stand HV system (parts in build) –RF test stand solid state amplifier (on order) –Tubes for the test stand driver (300kW) amplifier –Beam line power supplies (tender posted) –Cryo-coolers for 4 tracker VLPC cryostats –Parts for VLPC cryostats - commit through FNAL –Fibre (clear and scintillating) –Tube bases for RF TH116 (about to order) - Phase 2

7 7 FS:UK Phase 2: unfunded –Baseline plan has been seen by the PPARC-Science committee Infrastructure (RF power, hydrogen systems) Focus Coil module, completed tracker – “£3.3M” –Additional aspirations/synergies Contribution to cavity: – Engineering, surface treatments 'Official' G/W 2/3, SC, and Council statement: "Phase 2: To be completed in financial years 2007/08 to 2008/09: ― Construction of UK contributions (infrastructure, focus-coil modules and the full tracker) to the subsequent stages of the full experiment (£3.3M)."

8 8 FS:US US: –DoE NFMCC programme –MICE, MERIT, Cooling, ISS –NSF Tracker electronics Spectrometer solenoid superconductor Tracker solenoid contributions CKOV-I est. $32k to $42k depending on design

9 9 FS:US NFMCC: Current FY –Programme: Annual budget ~ $0.7M for MICE –Baseline plan: RF cavity & coupling coil modules (“RFCC”, 2 ea.) Absorber windows Tracker collaboration –D0 contribution of AFE-IIt boards (in return for a MICE effort & test stand) –Spectrometer solenoid Immediacy of need Current funds marginal for two units; okay if spread over two years –Cavity: initially concentrating on MTA work (MUCOOL) –Coupling coil: additional bid to NSF (MRI): CC needed for MUCOOL Bid to DOE for CC not funded this year

10 10 FS:US NFMCC for MICE: Future years –Programme: budget bids for MICE ~$1.0M would allow continuation at current level ~$1.4M additional bid to support CC design & build… –5 year funding plan Dependent on response to MuTAC/MRI Bids etc Aspirational budget to bring MICE to stage V NSF –MRI funds award: 2006 $750k Tracker electronics Spectrometer Solenoid Magnets –NSF support for MICE ~$100k/yr (2005-2007) Bid for UC-Riverside grant just submitted

11 11 FS:US Current procurement –1 st Cryostat for VLPC –2 nd – 4 th in manufacture at FNAL –Superconductor for spectrometer magnets (on order) Delivery expected in April –Spectrometer magnets (about to place tender) –AFE-IIt boards (D0)

12 12 FS:Jp Absorber bodies & R&D for MICE (est. value ¥58M) –Work at KEK on absorbers and –In collaboration with MuCool & MICE Tracker collaboration (est. cap. value ¥48M) –KEK beam time –People –Future funding dependent on bids to agencies Contributions to tracker – mainly fibre* & cryogenics* Contribution to tracker solenoid *UK swap

13 13 FS:Eu Ch: – Decay solenoid from PSI – Contribution to detectors (TOF) – People – DAQ for TOF, muCal – Bids for Coupling coil unsuccessful Nl: –Contribution to magnetic sensors

14 14 FS:Eu Italy: –INFN: funding TOF0 & MuCal Prototypes –TOF1, 2 dependent on TOF0 delivery –TOF2 further dependence on instrumentation case Be: CKOV2: design, no construction funds –Est. ~250kEuro –Remove from baseline configuration based on additional simulation studies ? Unclear: –Front end electronics for above –DAQ CERN –RF Power Phase 2 potential CERN contribution (est. 140kCHF)