AC Mitigation Overview - TGA

Similar presentations


Presentation on theme: "AC Mitigation Overview - TGA"— Presentation transcript:

1 AC Mitigation Overview - TGA
High Voltage AC (HVAC) Power Lines Operating near Pipelines November 15, 2013 Ryan Dillender Draft Version - 05/11/2012

2 HVAC Power Lines and Pipelines
High voltage alternating current (HVAC) power lines operating near pipelines can be hazardous in two ways. Electric shock hazards to people and animals. Increased corrosion of metallic pipelines.

3 What is a HVAC Power Line?
High voltage alternating current (HVAC) power lines are grouped into transmission and distribution categories. Typically lines of 26kV and less do not significantly impact pipelines, however severe phase imbalances can create abnormal issues.

4 Influencing Factors Typical HVAC transmission power lines are 138 kV, 230 kV, and 345 kV. Typical HVAC transmission lines have historically had design limits in the A range. Conductor improvements now allow design limits of 5000 A. Increased emphasis on sharing a common corridor has increased collocation length and frequency. Increased HVAC power line construction activity. Increased awareness in the industry of the AC related hazards and pipeline integrity.

5 Electric Transmission in Texas

6 Discovery of AC Interference Issue
Observation of new HVAC power line construction or increased awareness of existing issue. Request of HVAC power line crossing. Observation of unacceptable AC potential readings. Must be taken at peak power line load. Must be taken at proper location. Observation of unacceptable AC density. Must be taken at peak power line load and proper location. Requires coupon test station. Draft Version - 05/11/2012

7 AC Mitigation Project Lifecycle
Survey site and collect data GPS data of location for pipelines and power lines Resistances between power line structures and pipeline Soil resistivity Pipe to soil measurements Pipeline parameters and alignment sheets Power line parameters and plan and profile drawings. Use computer model with collected data to predict impact of the HVAC power lines on the pipeline and design AC mitigation system. AC potential (step and touch hazard) AC density (corrosion hazard) Install coupon test stations and AC mitigation system. Draft Version - 05/11/2012

8 AC Mitigation – Criteria
AC Potential Used to assess risk of step and touch safety hazard 15 VAC or more is a shock hazard NACE SP AC Density Used to assess risk of corrosion hazard 20 A/m2 or more is at risk for accelerated corrosion NACE AC Corrosion State-of-the-Art, Publication 35110

9 AC Mitigation – Study Expectations
The AC interference study will typically identify the expected pipeline conditions under peak power line loading. Field measurements are likely to be less than the expected peak values, unless field measurement are taken at peak power line loading.

10 AC Mitigation– Study Expectations

11 AC Mitigation– Study Expectations

12 AC Mitigation– Study Expectations
TK TK1 Pipeline Power Line

13 AC Mitigation– Study Expectations

14 AC Mitigation – Data Collection
The power grid is managed in real time without the use of stored energy. There is no current limiting device on the power grid. Load is balanced with lines being switched in and out of service. HVAC transmission lines loads vary with time. This variation can be driven by supply and/or demand. Power lines often have an emergency rating. This rating can be used for a short duration. Conductor sag and melting is the limiting factor.

15 AC Interference – Mitigation Methods
AC interference is monitored using coupon test stations. To be effective, test station must be monitored continuously. Step and touch hazards can be mitigated with through the use of gradient mats and bonding. The typical implementation of this is only effective at piping and appurtenances that are normally above ground. Step and touch hazards as well as corrosion hazards can be mitigated through the use of grounding systems.

16 AC Mitigation – Grounding System
Grounding systems can mitigate AC interference along the entire length of the pipeline. Grounding systems reduce the AC interference on the pipeline to acceptable levels. Grounding systems are typically created by installing a grounded conductor that parallels the pipeline. This is often accomplished with zinc ribbon. In order to maintain adequate cathodic protection, a decoupling device is required.

17 AC Mitigation – Grounding System
Grounding systems are developed using survey and model data. Grounding systems will be designed using a target pipeline to ground resistance value. In general, the resistance of the pipe to ground circuit is lowered by increasing the surface area of the grounding material. Horizontal and vertical lengths Zinc and copper are both common grounding materials. The use of copper requires close monitoring to ensure that it does not become connected to the pipeline in a way that allows DC to flow.

18 AC Mitigation – Decoupling Devices
The decoupling device allows AC to pass but not DC. Types of devices Polarization Cell (Kirk Cell) Solid State Decoupler (SSD) Polarization Cell Replacement (PCR) Failure mode Wet cells such as the Kirk Cell fail open. Dry cells such as the SSD and PCR fail closed.

19 AC Mitigation – Operations Impact
Installation of grounding systems. Installation of coupon test stations. Increased remote monitoring. Increased personal protective equipment (PPE). Increased review of crossing agreements for potential AC interference issues. Increased awareness of new HVAC power line construction. If available, increased coordination with power companies to minimize expenditure and risks.

20 AC Interference – Code Requirements
Subpart G – General Construction Requirements for Transmission Lines and Mains § – Additional construction requirements for steel pipe using alternative maximum allowable operating pressure For a new or existing pipeline segment to be eligible for operation at the alternative maximum allowable operating pressure calculated under § , a segment must meet the following additional construction requirements… To address this construction issue: The pipeline segment must meet this additional construction requirement: (e) Interference currents (1) For a new pipeline segment, the construction must address the impacts of induced alternating current from parallel electric transmission lines and other known sources of potential interference with corrosion control.

21 AC Interference – Code Requirements
Subpart I – Requirements for Corrosion Control § – External corrosion control: Interference currents (a) Each operator whose pipeline system is subjected to stray currents shall have in effect a continuing program to minimize the detrimental effects of such currents … § – External corrosion control: Electrical isolation. (f) Where a pipeline is located in close proximity to electrical transmission tower footings, ground cables or counterpoise, or in other areas where fault currents or unusual risk of lightning may be anticipated, it must be provided with protection against damage due to fault currents or lightning, and protective measures must also be taken at insulating devices.

22 AC Interference – Code Requirements
Subpart L – Operations § – Alternative maximum allowable operating pressure for certain steel pipelines. … (d) What additional operation and maintenance requirements apply to operation at the alternative maximum allowable operating pressure? In addition to compliance with other applicable safety standards in this part, if an operator establishes a maximum allowable operating pressure for a pipeline segment under paragraph (a) of this section, an operator must comply with the additional operation and maintenance requirements as follows:

23 AC Interference – Code Requirements
Subpart L – Operations § – Alternative maximum allowable operating pressure for certain steel pipelines. To address increased risk of a maximum allowable operating pressure based on higher stress levels in the following areas: Take the following additional step: (6) Controlling interference that can impact external corrosion (i) Prior to operating an existing pipeline segment at an alternate maximum allowable operating pressure calculated under this section, or within six months after placing a new pipeline segment in service at an alternate maximum allowable operating pressure calculated under this section, address any interference currents on the pipeline segment. (ii) To address interference currents, perform the following: (A) Conduct an interference survey to detect the presence and level of any electrical current that could impact external corrosion where interference is suspected; (B) Analyze the results of the survey; and (C) Take any remedial action needed within 6 months after completing the survey to protect the pipeline segment from deleterious current.

24 EN 15280:2013 – Current Density Section 7 – Acceptable Interference Levels The design, installation and maintenance of the cathodic protection system shall ensure that the levels of a.c. voltage do not cause a.c. corrosion. Since the conditions vary for each situation, a single threshold value cannot be applied. This is achieved by reducing the a.c. voltage on the pipeline and current densities as below: As a first step, the a.c. voltage on the pipeline should be decreased to a target value, which should be 15 V rms or less. This value is measured as an average over a representative period of time (e.g. 24 h). and As a second step, effective a.c. corrosion mitigation can be achieved by complying with criteria defined in EN 12954:2001, Table 1, and maintaining the a.c. current density (rms) over a representative period of time (e.g. 24 h) to be lower than 30 A/m2 on a 1 cm2 coupon or probe; or maintaining the average cathodic current density over a representative period of time (e.g. 24 h) lower than 1 A/m2 on a 1 cm2 coupon or probe if a.c. current density (rms) is more than 30 A/m2; or maintaining the ratio between a.c. current density (Ja.c.) and d.c. current density (Jd.c.) less than 5 over a representative period of time (e.g. 24 h). NOTE Current density ratios between 3 and 5 indicate a small risk of a.c. corrosion. However, in order to reduce the corrosion risk to a minimum value, smaller ratios of current density than 3 would be preferable … Effective a.c. corrosion mitigation can be also demonstrated by measurement of corrosion rate. 

25 HVAC Collocation in Texas
Natural Gas Pipelines within 1 Mile of HVAC Power Lines

26 References Page 3 Image [ Page 4 Image [By Dave Bryant (Own work) [CC-BY-SA-3.0 ( via Wikimedia Commons] Page 18 Image [