Association of Levee Boards of Louisiana USACE New Orleans District Update
Col. Stephen Murphy Commander, New Orleans District 4 December 2019
2
USACE, New Orleans District FY19-20 State of the District
$947M TOTAL OBLIGATIONS $404M in PBUD / Work Plan $209M HSDRSS Supplemental 1,491 contracts awarded Current & Future Funding Continuing Resolution thru Dec. 20 $326M PBUD / Carry-In $946M HSDRRS Supplemental $1.65B BBA-18 Supplemental TBD: FY19 Emergency Supplemental BUILDING STRONG® and Taking Care of People!
3
South Louisiana Flood Risk Management
Longest flood fight in New Orleans District history…with a hurricane 292 Days
4
Mississippi River and Tributaries
Repair & Restore, Construction & Supplemental Environmental Impact Statement 2019 Supplemental Funding Received Appropriation Total Items Cost O&M 4 $53.5M MR&T 10 $3.1M Totals 14 $56.6 MR&T Current and Upcoming Construction In Construction FY19 Award FY20 Award 6 4 Nine Mile Point Seepage Baton Rouge Front Phase IV Avondale Seepage Carrollton Phase III- District Floodwall MR Baton Rouge to the Gulf Dredging
5
Hurricane and Storm Damage Risk Reduction System 26 contracts
Armoring, Levee Lifts, and General Reevaluation Reports 26 contracts 8 in construction 42 of 76.6 total miles complete 29 miles in construction 76.6 miles total system Armoring 41.65 miles NCC’d 28.95 miles under construction 6.00 miles awarded, NTP pending NFS levee lift completion Two GRRs pending 45-day Public Review 26 total system Armoring Contracts 16 contracts NCC’d 8 contracts under construction 2 contracts to be awarded pending levee lift completion Completed Under Construction (armoring) Armoring Award pending levee lift completion Floodwall / Structure
6
Feasibility Study Areas
Flood Risk management: investigations Evaluating opportunities to further reduce flood risk Feasibility Study Areas Amite River & Tributaries Upper Barataria South Central Coastal
7
South Louisiana Flood Risk Management West Shore Lake Pontchartrain Hurricane and Storm Damage Risk Reduction
8
South Louisiana Flood Risk Management
Morganza to the Gulf
9
Hurricane and Storm Damage Risk Reduction
New Orleans to Venice/Non-Federal Levee NOV ($762M) 34 miles of back levees, pump stations and floodwalls 2 new pump stations 2 pump station fronting protection NFL ($671M) 37 miles of levees and floodwalls (west bank back levees and MRL) 4 pump station fronting protection 4 backflow prevention 2 floodgates
10
USACE Levee Safety Program
Engineering Circular, Silver Jackets and National Levee Inventory Draft Levee Safety EC Release in Jan 2020 Feedback sought Silver Jackets Funding Wax Lake I-Wall Stability Emergency Action Plan Levee Inventory & Review USACE-funded levee inspection and risk assessment Inclusion in National Levee Database BUILDING STRONG® and Taking Care of People!
11
Keep in Touch with the New Orleans District
Visit us at our website Follow us on @usacenola @westshorelakepontchartrain @comiteriverdiversion Participation In closing, please do not hesitate to contact my team if you have any questions or need additional information on any of the projects I mentioned and the countless others I did not. Follow us on our social channels You can also follow our social channels as we provide updates on our efforts and projects. Feel free to comment or direct message us and we will respond. Like us on Facebook Find us on
Similar presentations
© 2025 SlidePlayer.com Inc.
All rights reserved.