1 2018 Attachment O True-Up Stakeholder Meeting
Ameren Transmission Company of Illinois July 16, 2019

2 Purpose is to review ATXI 2018 Transmission Rate True-Up Calculations
Agenda Purpose is to review ATXI 2018 Transmission Rate True-Up Calculations Protocol Timeline Attachment O Template Changes ROE Complaint Cases and Impact on True-up calculations 2018 True-Up Calculation Total Revenue Requirement Comparison – Projected vs Actual Attachment O/Schedule 9 True-up Attachment MM/Schedule 26-A True-up 2018 MVP Spend 2018 Significant Projects Placed In Service An additional meeting will held to review the 2020 Projected Transmission Rate calculations.

3 (Forward-Looking Protocols)
Protocol timeline Date Schedule (Forward-Looking Protocols) June 1 Posting of annual true-up for prior year September 1 Deadline for annual true-up meeting Posting of net projected revenue requirement for following year October 15 Deadline for annual projected rate meeting November 1 Deadline for joint meeting on regional cost-shared projects March 15 Transmission Owners submit informational filing to the Commission

4 ATXI Attachment O tariff Changes
Docket ER FERC Order on November 5, 2018 Effective February 14, 2018 for ATXI The incentive return and income taxes was weighted for the number of days in effect for 2018 ~ 321 days. Approved 50 basis point adder for Mark Twain Component of the Grand Rivers Project Added a page 3 to Attachment MM to calculate the Incremental Return and Income Taxes for 100 basis point increase in ROE per dollar of Net Transmission Plant Added a column on Attachment MM page 2 Modified Attachment O page 3, to include the ROE incentive return and income taxes in the total revenue requirement Docket ER FERC Order on December 20, 2018 Effective January 1, 2019, but also applicable to the 2018 true-up Approved removing double averaging on the ADIT work paper The term double averaging or two-step averaging methodology refers to the application of the IRS proration methodology together with an additional averaging step

5 ROE complaints MISO ROE Complaints RTO Adder (ER15-358)
1st Complaint (EL14-12) Covers November 12, 2013 through February 11, 2015 FERC order received September 28, 2016; set the Base ROE at 10.32% Applicable going forward until 2nd complaint order 2nd Complaint (EL15-45) Covers February 12, 2015 through May 11, 2016 Initial decision issued June 30, 2016; recommended Base ROE at 9.70% Additional refunds may be required upon receipt of Final Order RTO Adder (ER15-358) FERC approved a 50 basis point adder for participation in an RTO Effective January 6, 2015, applicable to complaint case refunds after that date and going forward (i.e., total ROE is now 10.82%)

6 MISO ROEs for the 2018 True-Up
ROE complaints MISO ROEs for the 2018 True-Up 10.82% ROE for January 1 – December 31 Refunds already provided for EL14-12 Two phase process Phase 1 related to ROE impact on projected rates for forward looking TOs and annual updates for historical TOs. These were settled in February 2017. 2013, 2014 & 2015 projected rates from 11/12/13 to 2/11/15 Phase 2 related to the ROE impact on true-ups calculations for forward looking TOs. These were settled in June 2017. 2013, 2014 & 2015 True-ups included in 2015, 2016 and 2017 projected rates Refunds for Schedules 7, 8, 26, 37, 38, 26A were completed by MISO Refunds for Schedule 9 were processed by Ameren Schedule 9 Refund amounts and supporting documents are posted on Ameren’s OASIS

7 ATXI Revenue Requirement Comparison
Projected 2018 vs Actual 2018

8 Atxi 2018 Rate Base Page.Line 2018 Proj 2018 Act Change Percent 2.6
Total Gross Plant 1,287,715,104 1,337,399,221 49,684,117 4% 2.12 Total Accum Depreciation 43,663,636 40,469,645 (3,193,992) -7% 2.18 TOTAL NET PLANT 1,244,051,468 1,296,929,577 52,878,109 2.18a 100% CWIP RECOVERY 179,259,075 133,874,635 (45,384,439) -25% ADJUSTMENTS TO RATE BASE 2.20 Account No. 282 (210,933,057) (230,183,340) (19,250,283) 9% 2.21 Account No. 283 (3,795,167) (4,404,062) (608,896) 16% 2.22 Account No. 190 56,643,669 47,838,869 (8,804,800) -16% 2.25 Land Held for Future Use - N/A 2.26 CWC 1,841,296 1,668,284 (173,012) -9% 2.27 Materials & Supplies 2.28 Prepayments 386,923 352,448 (34,475) TOTAL ADJUSTMENTS (155,856,335) (184,727,801) (28,871,466) 19% 2.30 TOTAL RATE BASE 1,267,454,207 1,246,076,410 (21,377,797) -2%

9 ATXI 2018 Expenses Page.Line 2018 Proj 2018 Act Change Percent O&M 3.1
Transmission 3,022,265 3,770,448 748,183 25% 3.1a Less LSE Expenses - N/A 3.2 Less Account 565 3.3 A&G 11,708,106 9,575,824 (2,132,282) -18% 3.4 Less FERC Annual Fees 3.5 Less EPRI, etc. 26,233 143,754 117,521 448% 3.5a Plus Trans. Reg. Comm. Exp 3.8 TOTAL O&M 14,730,372 13,346,272 (1,384,100) -9% 3.12 TOTAL DEPRECIATION 28,881,967 26,496,929 (2,385,038) -8% TAXES 3.13 Payroll 3.16 Property 3,510,160 716,707 (2,793,453) -80% 3.18 Other 673,000 640,053 (32,947) -5% 3.27 Income Taxes 30,388,622 28,976,884 (1,411,738) TOTAL TAXES 34,571,782 30,333,644 (4,238,138) -12% TOTAL EXPENSES 78,184,121 70,176,845 (8,007,276) -10%

10 Atxi 2018 capital structure

11 ATXI 2018 total revenue requirement
Page.Line 2018 Proj 2018 Act Change Percent 2.30 TOTAL RATE BASE 1,267,454,207 1,246,076,410 (21,377,797) -2% 4.30 Rate of Return on ACS 7.58% 7.69% 0.11% 1% 3.28 Return from ACS 96,054,820 95,784,293 (270,527) 0% 2.30a 100% CWIP RECOVERY 179,259,075 133,874,635 (45,384,439) -25% 4.30e Incremental Rate of Return on HCS -0.02% -0.01% 0.01% -40% 3.28a Incremental Return from HCS (31,591) (14,061) 17,530 -55% 3.28b ROE incentive Mark Twain - 142,312 N/A Total Return 96,023,229 95,912,545 (110,684) Total Expenses 78,184,121 70,176,845 (8,007,276) -10% 3.29 TOTAL GROSS REV. REQ. 174,207,349 166,089,390 (8,117,960) -5% 3.30 Less ATT. GG Adjustment 3.30a Less ATT. MM Adjustment 166,512,669 158,942,692 (7,569,977) 3.31 GROSS REV. REQ. UNDER ATT. O 7,694,680 7,146,698 (547,983) -7%

12 Atxi 2018 Net Revenue Requirement For Schedule 9
Page.Line 2018 Proj 2018 Act Change Percent 1.1 Gross Revenue Requirement 7,694,680 7,146,698 (547,983) -7% 1.6 Total Revenue Credits 839,201 1,034,750 195,549 23% 1.6a Historic Year Actual ATRR 9,142,207 - 0% 1.6b Projected ATRR from Prior Year 8,608,134 1.6c Prior Year ATRR True-Up 534,073 1.6d Prior Year Divisor True-Up 148,506 1.6e Interest on Prior Year True-Up 11,746 1.7 NET REVENUE REQUIREMENT 7,549,805 6,806,273 (743,532) -10%

13 ATXI 2018 attachment o true-up for Schedule 9
Attachment O 2018 True-up Calculation (Schedule 9) Net Actual 2018 Rev Req (Actual Attach O, Pg 1, Line 7) $6,806,273 Net Projected 2018 Rev Req (Projected Attach O, Pg 1, Line 7) $7,549,805 Under/(Over) Collection of 2018 Net Rev Req ($743,532) Historic Year Actual Divisor for Transmission Owner (Attach O, Pg 1, Line 15) 7,199,027 Proj'd Yr Divisor for Transmission Owner (Projected Attach O, Pg 1, Line 15) 7,176,333 Difference between Historic & Projected Yr Divisor (22,694) Prior Year Projected Annual Cost ($ per kw per yr) $1.0520 Under/(Over) Collection of 2018 Divisor True-up ($23,874) Total Under/(Over) Recovery ($767,406) Monthly Interest Rate (Over collection = FERC rate, Under collection = company rate) 0.3900% Interest For 24 Months ($71,829) Total 2018 Attachment O True-up Under/(Over) Recovery (To be included in Projected 2020) ($839,235)

14 ATXI 2018 attachment MM true-up by project

15 ATXI 2018 attachment MM true-up for Schedule 26-A
Attachment MM 2018 True-up Calculation (Schedule 26-A) Actual 2018 Attachment MM Rev Req (Actual Attach MM, pg 2, col 14) 1 $158,942,692 Actual Attachment MM Revenues for 20181 $155,696,149 Under/(Over) Recovery of 2018 MM Rev Req $3,246,543 Monthly Interest Rate (Over collection = FERC rate, Under collection = company rate) 0.2030% Interest For 24 Months $158,172 Total 2018 Attachment MM True-up Under/(Over) Recovery (To be included in Projected 2020) $3,404,715 1 Amount excludes True-Up Adjustment, as reported in True-Up Year projected Attachment MM, page 2, column 15.

16 Atxi 2018 MVP SPEND Ameren MVPs Ameren Name 2018 CAPEX MTEP #s
MTEP Description Illinois Rivers $18 million 2237 Pana - Mt. Zion - Kansas - Sugar Creek 345 kV line 2239 Sidney to Rising 345 kV line 3017 Palmyra-Quincy-Meredosia - Ipava & Meredosia-Pawnee 345 kV Line 3169 Pawnee to Pana kV Line 3170 New Palmyra Substation (Maywood) Spoon River $4 million 3022 Fargo-Galesburg-Oak Grove 345 kV Line Mark Twain $81 million 2248 Zachary Ottumwa 345 Maywood - Zachary 345 kV Line

17 MVP Facilities status with In-service Dates
Illinois Rivers Substations Line Segments Kansas Oct-15 Sidney-Rising Sep-16 Sidney Nov-15 Faraday-Pana Oct-16 Rising Herleman-Maywood Pana Meredosia-Herleman Faraday Austin-Meredosia Sep-17 Herleman Pana-Austin Oct-17 Maywood Meredosia-Ipava Dec-17 Meredosia Faraday-Kansas Apr-18 Ipava May-17 Kansas-Sugar Creek 2020 Austin River Crossings Maywood-Herleman Herleman-Meredosia Spoon River Mark Twain Fargo Substation May-16 Zachary Substation Jun-19 Sandburg Substation Mar-17 Zachary-Ottumwa Sandburg-Fargo Feb-18 Maywood-Zachary Dec-19

18 Additional information