NMBM INTEGRATED PUBLIC TRANSPORT SYSTEM OVERVIEW

Similar presentations


Presentation on theme: "NMBM INTEGRATED PUBLIC TRANSPORT SYSTEM OVERVIEW"— Presentation transcript:

1 NMBM INTEGRATED PUBLIC TRANSPORT SYSTEM OVERVIEW
ACTING PROJECT MANAGER : MR LUTHANDO MABHOZA Date: SEPTEMBER 2017

2 NMBM INTEGRATED PUBLIC TRANSPORT SYSTEM
PROJECT OVERVIEW AND FINANCIAL STATUS MASTER PROGRAMME & PROGRESS STATUS UPDATE RISK MANAGEMENT IMPROVEMENTS ON IMPLEMENTATIONS CHALLENGES UNIVERSAL ACCESS AND INTEGRATED TICKETING SYSTEM FUTURE OF IPTS

3 1. PROJECT OVERVIEW AND FINANCIAL STATUS
In 2004, the Public Transport Plan (PTP) was compiled as a part of a CITP as required by the National Land Transport Transition Act (NLTTA, 2000) In 2010, limited IPTS launched to provide for the public transport needs of the 2010 FIFA World Cup , the proposals of the PTP were further developed into draft Operational Plans. The Operational Plan proposed 5 contract areas as listed below: Cleary Park Njoli Motherwell Uitenhage Western Suburbs

4 1. PROJECT OVERVIEW AND FINANCIAL STATUS
April 2012, planning and construction of additional infrastructure to operate a pilot service was initiated. January 2013, pilot services were launched on seven routes (5 in Port Elizabeth and 2 in Uitenhage). January 2013, construction of the roadway civil works started in the Cleary Park Contract Area (trunk & main routes), portions of the Njoli Contract Area (trunk route) and Western Suburbs (Termini). January 2014, project steering committee was re-established followed by the establishment of the relevant project workstreams. February 2014, operational planning for the starter services for Cleary Park , Njoli and Western Suburbs Contract Areas commenced and were completed in June 2015 December 2015 a scaled-down approach (Starter Service) was adopted with operations anticipated in July 2016, which has since moved to October 2017.

5 1. PROJECT OVERVIEW AND FINANCIAL STATUS
Contract Area’s 1 Motherwell 2 Njoli 3 Cleary Park 4 Western Suburbs 5 Uitenhage CBD

6 1. PROJECT OVERVIEW AND FINANCIAL STATUS

7 1. PROJECT OVERVIEW AND FINANCIAL STATUS
Area Route 347: Route Length: km Fleet: 15 Mini-bus Passenger Trips: 2 000/ day Area Route 341: Route Length: km Fleet: 22 Mini-bus Passenger Trips: 3 000/ day Area Route 340: Route Length: km Fleet: 24 Mini-bus Passenger Trips: 2 000/ day Trunk Route 30: Route Length: km Fleet: 18 Artic. Buses Passenger Trips: / day Future Extension to University (2017/2018) Bus Lanes and Platforms Constructed (11.97 km)

8 1. PROJECT OVERVIEW AND FINANCIAL STATUS
Area Route 244: Route Length: 3.95 km Fleet: 8 Mini-bus Passenger Trips: 3 000/ day Area Route 257: Route Length: 3.56 km Fleet: 8 Mini-bus Passenger Trips: 3 000/ day Bus Lanes and Platforms Constructed (5.8 km) Future Extension to University (2017/2018)

9 1. PROJECT OVERVIEW AND FINANCIAL STATUS
WESTERN SUBURBS

10 1. PROJECT OVERVIEW AND FINANCIAL STATUS
UITENHAGE-KWANOBUHLE

11 1. PROJECT OVERVIEW AND FINANCIAL STATUS
LINK WITH BUILT ENVIRONMENT PERFORMANCE PLAN (BEPP)

12 LINK WITH BUILT ENVIRONMENT PERFORMANCE PLAN (BEPP)
UNS: Major Movement Directions R335 R334 MW CDC U JVT MM UD D R368 Legend R102 Metro Boundary R334 R75 IB R367 Urban Edge Existing Rail Future Rail National Road (N2) Primary Roads DP SD Metropolitan CBD Sub-Metropolitan Nodes R102 GB Township/ Urban Clusters N2 NE Development Areas R102 Directional Flow on N2 PE CBD Directional Flow to and from Suburban areas M12 M9 M7 WM M9 12

13 1. PROJECT OVERVIEW AND FINANCIAL STATUS
Urban Network Strategy Framework LINK WITH BUILT ENVIRONMENT PERFORMANCE PLAN (BEPP)

14 1. PROJECT OVERVIEW AND FINANCIAL STATUS
ALLOCATIONS TO DATE Year PTIS Grant PTI Grant PTNO Grant PTN Grant Cumulative Amount 2005/06 R53,650,000 2006/07 R68,600,000 R122,250,000 2007/08 R131,200,000 R253,450,000 2008/09 R305,484,000 R558,934,000 2009/10 R147,079,000 R706,013,000 2010/11 R408,333,000 R1,114,346,000 2011/12 R340,000,000 R1,454,346,000 2012/13 R289,702,000 R1,744,048,000 2013/14 R357,021,962 R100,000,000 R2,201,069,962 2014/15 R130,000,000 R2,431,069,962 2015/16 R186,128,000 R2,617,197,962 2016/17 R0 Total R457,021,962 R230,000,000 R116,755,311

15 1. PROJECT OVERVIEW AND FINANCIAL STATUS
EXPENDITURE TO DATE Year Expenditure Cumulative Expenditure 2005/06 R 766,079 2006/07 R 33,156, 765 R 33,922,844 2007/08 R 66,228,928 R 100,151,772 2008/09 R 178,943,521 R 279,095,293 2009/10 R 427,719,916 R 706,815,209 2010/11 R 260,063,223 R 966,878,432 2011/12 R118,289,226 R 1,085,167,658 2012/13 R 360,725,806 R 1,445,893,464 2003/14 R 447,553,740 R 1,892,447,204 2014/15 R 237,283,000 R 2,130,730,204 2015/16 R 36,677,707 R 2,167,407,911 2016/17 R93,100,000 R 2,260,507,911 Surplus (Returned to National Treasury) R 356,690,051

16 PROJECT OVERVIEW AND FINANCIAL STATUS
DORA gazetted MTEF ALLOCATIONS 2017/18 – R 2018/19 – R 2019/20 – R

17 IPTS Financial Summary
2017/18 2018/19 2019/20 2020/21 R ‘000 Budgeted rates income 1,882,347 2,091,299 2,294,414 2,512,383 Estimated IPTS Fare Revenue 13,814 19,524 50,212 53,726 Estimated direct operating costs 35,725 50,491 93,576 99,191 Estimated indirect operating cost 43,929 51,400 81,663 86,563 Deficit/Surplus -21,911 -30,967 -43,365 -45,464 City contribution to direct operating costs 21,911 30,967 43,365 45,464 City contribution to indirect operating costs (30% - 50%) 11,319 13,448 32,000 33,920 Estimated total city contribution 33,229 44,415 75,365 79,385 Estimated Percentage contribution from rates bill 1.8% 2.1% 3.3% 3.2% PTNG contribution to indirect operating costs (70% - 50%) 32,610 37,951 49,663 52,643 PTNG contribution business development costs (100%) 14,000 16,520 22,191 23,523 PTNG contribution to capex 220,437 336,794 254,083 153,359 Total PTNG envelope 273,297 234,360 246,874 329,457

18 2. MASTER PROGRAMME & PROGRESS STATUS UPDATE
Starter Service Description Launch Date Phase 1A Cleary Park to PE CBD Trunk Route 2017/18 October 2017 Phase 1B Njoli to PE CBD 2018/19 Phase 1C PE CBD to NMMU Phase 1D KwaNobuhle to Uitenhage CBD 2019/20

19 2. MASTER PROGRAMME & PROGRESS STATUS UPDATE
Item Cleary Park Njoli Western Suburbs Uitenhage 2017/18 2018/19 2019/20 2020/21 2021/22 Distance to be covered by all starter service Phases 42.24 km 19.31 km 19.26 km 36.69 km Max passengers per day 6 918 7056 7 380 6 000 12 000 Estimated travel time(one way) 40 min 39 min 33.5 min 27 min Ticketing method Interim Paper ticket to be changed to EMV in 2019/20 AFC: EMV compliant Universal Design The plan is prepared and will be updated in 2017/18/19 financial years Operating Licence to be surrendered 100 16 38 79

20 2. MASTER PROGRAMME & PROGRESS STATUS UPDATE
4 stations planned for construction in 2018/19, these will be phased depending on demand Anticipated jobs to be created by transforming the PT operators: Permanent and shift drivers Ambassadors Cleaning and maintenance workers at depots etc. A call for proposal for a socio economic impact including environmental impact study will be developed this financial year

21 RISK MANAGEMENT Item Risk Mitigation Measure 1
Financial management of OPEX NMBM is setting up systems and tools to do away with mismanagement of funds and also improve on accountability. 2 Financial management of CAPEX Procurement policy adhered to, limit deviations 3 Revenue Increase Alternative sources of revenue will be investigated once system is operational 4 Delays in negotiation process The NMBM is continuously engaging with the operators and specialist capacity has been brought into the team to assist with negotiations, however, it may be necessary to consider mediation processes for effective negotiation when / if required. 5 Operator Business Model The NMBM is continuously engaging with the operators and specialist capacity has been brought in to assist with negotiations, continuous negotiations with VOC

22 3. RISK MANAGEMENT Item Risk Mitigation Measure 6
Delays in procuring trunk vehicles Funding insufficient to procure in the 2017/18/19. Projections done for 2019/20 for procurement of vehicles. Vehicle specifications will be developed in 2nd half of 2018/19 7 Institutional capacity An interim “TO BE” organisational structure for the Sub Directorate was submitted and approved by Council. Recruitment process commenced and anticipated to be completed by end Sept 2017 8 Signage Improvements Undertaken as part of the infrastructure development or upgrade process 9 Customer feedback Transport Operational Centre will be operational prior to start of operations in Oct 2017 10 Accident rates and law enforcement Safety and Security Plan currently under review 11 Reporting to NT Monthly, quarterly and annual evaluation report. (bilateral meetings, Cities Forum)

23 4. IMPROVEMENTS ON IMPLEMENTATIONS
Lessons learnt from pilot are currently implemented Negotiations with affected operators and not secondary co-ops Recommissioning of Integrated Transport Operational Centre i.e monitoring Improve on Marketing and communications plan Reduced operations and respond to demand Resource requirements for the implementation of the project Improved negotiation strategies with operators

24 5. CHALLENGES Procurement Issues The delays in the procurement of services for the planning and implementation of the IPTS have impacted negatively on the overall progress of the project. Institutional Capacity (External technical support / Consultants) Professional support services for the IPTS is a great challenge linked to procurement. Negative perception of the project Land Use-Transport Integration Limiting peripheral development to reduce longer travel distance Intensified integrated planning PRASA, ECDoT etc Funding requirements to complete critical projects

25 6. UNIVERSAL ACCESS AND INTEGRATED TICKETING SYSTEM
Universal Access Strategy developed during 2013/14 and will be revised for the starter service once consultants are appointed The initial fare system to be used is paper based Tender for the EMV compliant system is being revised Interoperability will be tested with PRASA Motherwell -PE CBD rail operation initiative in 2018/19/20

26 COORDINATION WITH PRASA
PHASE 1

27 RECENT ACHIEVEMENTS

28 END! THANK YOU