Presentation is loading. Please wait.

Presentation is loading. Please wait.

Field Emission and Mitigation in the CEBAF Linacs R Legg, R Geng Jlab SRF Ops Dept. TTC,

Similar presentations


Presentation on theme: "Field Emission and Mitigation in the CEBAF Linacs R Legg, R Geng Jlab SRF Ops Dept. TTC,"— Presentation transcript:

1 Field Emission and Mitigation in the CEBAF Linacs R Legg, R Geng Jlab SRF Ops Dept.
TTC,

2 Upgrade magnets and power supplies
new Hall 12 11 6 GeV CEBAF Upgrade is designed to build on existing facility: vast majority of accelerator and experimental equipment have continued use. Upgrade magnets and power supplies CHL-2 help me Two 0.6 GV linacs 1.1 Enhanced capabilities in existing Halls Maintain capability to deliver lower pass beam energies: 2.2, 4.4, 6.6….

3 Problem Description Field emission (FE) is generated and transported in CEBAF Reaches energies of 100’s of MeV FE strikes cavities and causes beam trips FE charges cavity windows which cause beam trips Pipe size step downs and magnets convert the field emission stopped to gamma radiation which damages organic molecules (cables, epoxy, etc.) on girders between modules

4 Other Issues Spurious trips correlated to CM Activation
Cavity Trips Gas load increase around cryomodules Spurious valve closures Frozen gas in cavities Electronic quenches

5 One Source of Problem C100 (12 Gev Upgrade) Cavities are seven cell “Low-loss” design Worked well in horizontal test bed Field emission threshold was not specified End groups larger diameter than cavity irises Cavity design transports FE from cavity to cavity Operated above known FE onset gradient Corollary: Don’t put machine energy in project name. Field emission has increased over time

6 Increase of Field Emission with time
How do we mitigate the problem?

7 Mitigation: Local Shielding
For C100s, we attempted to locally shield equipment with lead collars around beampipe adjacent to modules Pb Collar OSLs BL-1 BL-2 MAG-BL OPTICHROMIC EC-1 EC-2 Girder

8 Good and Bad News Good – Data fits closely with earlier dataset. Lead collars did attenuate radiation by 3x from one side to the other. Bad – 10 HVL of lead should attenuate 1000x. Core of radiation cone which passes through the shielding in the beam pipe gave a dose at the girder 3x higher than measured on the face of the cryomodule. Local shielding is not practical in this case. Normalized Dose Distance, in

9 Mitigation: Post Processing
Helium processing of cavities performed July 2015 Plot shows the distribution of changes in the gradient at which radiation becomes detectable by the DecaRad system * *Courtesy of Mike Drury

10 Mitigation: Reduce source of Field Emission
Cavities were field emission free when qualified. Rebuild C100 cryomodules using LCLS-II tools and procedures for clean assembly When module is replaced, clean the adjacent warm girder too. * * * Courtesy of C. Reece

11 Mitigation: Modeling of Problem
Use Fowler-Nordheim fit to cavities from commissioning data Also used on C20 modules in CEBAF (arXiv: ) For C100 cryomodules, an additional multiplier is added for energy gain in adjacent cavities Straight forward solver to maximize EACC vs Dose rate for a cryomodule. For C20s we maximize EACC vs trip rates Reality is a problem though; Field emitters pop-up and process away in cavities FE characteristics change over time; (gas load?) Users want the maximum EACC possible.

12 Mitigation: Reduce Radiation by Gradient Redistribution
CEBAF Injector Area Test w/ w CM’s in series 0L03(C20) total output voltage maintained at constant Lowering gradients in two FE source cavities Raising gradient in two FE free cavities 0L04(R100) at constant gradient Radiation reduced by 5 order of magnitude While preserving total accelerating voltage output 0L03-3 lowered by 3 MV/m 0L03-7 lowered by 3 MV/m 0L03-5 raised by 3 MV/m oL03-6 raised by 3 MV/m Requires knowledge on FE source cavity and FE onset May not always work due to other constraints In-situ FE instrumentation

13 Thank you for your attention.
Next Steps Field emission is a problem, but Can be modeled and optimized Mitigation can be realized He processing Run below the FE onset threshold Particle free, clean assembly of linac hardware Routine testing to stay within limits Jlab is in process of rebuilding the first C100 Cryomodule using LCLS-II clean room and techniques to mitigate field emission by raising onset thresholds. Thank you for your attention.


Download ppt "Field Emission and Mitigation in the CEBAF Linacs R Legg, R Geng Jlab SRF Ops Dept. TTC,"

Similar presentations


Ads by Google