MANGAUNG METROPOLITAN MUNICIPALITY

Similar presentations


Presentation on theme: "MANGAUNG METROPOLITAN MUNICIPALITY"— Presentation transcript:

1 MANGAUNG METROPOLITAN MUNICIPALITY
PRESENTATION TO THE PORTFOLIO COMMITTEE ON HUMAN SETTLEMENTS 2018/19 URBAN SETTLEMENTS DEVELOPMENT GRANT (USDG) RECOVERY PLAN Advocate Tankiso Mea City Manager 12 March 2019

2 Content USDG Financial performance Risks and mitigation
1 USDG Financial performance 2 USDG Adjusted Financial Performance 3 Risks and mitigation 4 USDG Projects and progress after revision 5 Key interventions and acceleration plan

3 2018/19 USDG EXPENDITURE – END JANUARY
USDG PER DIRECTORATE Original Budget YTD Movement % Spent Balance SOCIAL SERVICES R 27,000,000 R 11,387,337 42% R 15,612,663 PLANNING R 38,396,654 R 2,384,080 6% R 36,012,574 HUMAN SETTLEMENT AND HOUSING R 228,700,000 R 41,758,601 18% R 186,941,399 ROADS AND STORMWATER R 148,729,565 R 33,850,095 23% R 114,879,470 SANITATION R 222,598,729 R 107,823,987 48% R 114,774,742 WATER R 60,057,052 R 30,766,122 51% R 29,290,930 WASTE AND FLEET MANAGEMENT R 17,344,000 R 589,113 3% R 16,754,887 3% OPSCAP R 13,390,000 R 2,133,405 16% R 11,256,595 TOTAL R 756,216,000 R 230,692,740 31% R 525,523,260

4 Actual Expenditure ( R )
2018/19 USDG EXPENDITURE – END JANUARY Month Budget Target ( R ) Actual Expenditure ( R ) Budget Target % Actual Expenditure % Jul-18 R R 0 8,33% 0% Aug-18 R 16,67% Sep-18 R R   25,00%  3% Oct-18 R R 68,216,808 33,33% 9%  Nov-18 R R 93,544,406 41,67% 12%  Dec-18 R R 178,100,602   50,00% 23%  Jan-19 R R 230,692,740 58,33% 31% Feb-19 R 66,67% Mar-19 R 75,00% Apr-19 R 83,33% May-19 R 91,67% Jun-19 R 100%

5 2018/19 USDG EXPENDITURE – END FEBRUARY
DIRECTORATE Original Budget YTD Expenditure % HUMAN SETTLEMENT AND HOUSING R R 27% SANITATION R R 70% ROADS AND STORMWATER R R 32% WATER R R 41% PLANNING R R 14% SOCIAL SERVICES R R 49% WASTE AND FLEET MANAGEMENT R R 9% 3% USDG OPSCAP R R 18% TOTAL R R 40%

6 Actual Expenditure ( R )
2018/19 USDG EXPENDITURE – END FEBRUARY Month Budget Target ( R ) Actual Expenditure ( R ) Budget Target % Actual Expenditure % Jul-18 R R 0 8,33% 0% Aug-18 R 16,67% Sep-18 R R   25,00%  3% Oct-18 R R 68,216,808 33,33% 9%  Nov-18 R R 93,544,406 41,67% 12%  Dec-18 R R 178,100,602   50,00% 23%  Jan-19 R R 230,692,740 58,33% 31% Feb-19 R R 300,932,961 66,67% 40% Mar-19 R 75,00% Apr-19 R 83,33% May-19 R 91,67% Jun-19 R 100%

7 RISKS AND MITIGATION RISKS City not spending 100% of the allocation
Underperforming Directorates/Departments Business forums and community unrests MITIGATION Replaced non-performing projects with performing projects Reduced budget of poor performing Directorates and allocated more resources to performing Directorates Tracking and finalisation of all USDG BIDS at different SCM Committees Contractors requested to allocate more resources as part of acceleration plan Technical Team to monitor progress of all USDG funded projects and advice EMT

8 REVISED ALLOCATION AGAINST ORIGINAL PLAN
DIRECTORATE Original Budget Adjusted Budget % HUMAN SETTLEMENT AND HOUSING R 228,700,000 R 122,191,509 16% ELECTRICITY R0 R 78,000,000 10% SANITATION R 182,598,729 R 226,433,242 30% ROADS AND STORMWATER R148,729,565 R 138,112,865 18% WATER R 100,057,052 R 127,788,390 17% PLANNING R 38,396,654 R 16,955,994 2% SOCIAL SERVICES R 27,000,000 R 24,000,000 3% WASTE AND FLEET MANAGEMENT R 17,344,000 R 9,344,000 1% 3% USDG OPSCAP R 13,390,000 TOTAL R 756,216,000 100%

9 2018/19 USDG ADJUSTED EXPENDITURE
DIRECTORATE Adjusted Budget Adjusted Expenditure % After Adjustment HUMAN SETTLEMENT AND HOUSING R 122,191,509 R 44% ELECTRICITY R 78,000,000 R 56% SANITATION R 226,433,242 R 49% ROADS AND STORMWATER R 138,112,865 R 30% WATER R 127,788,390 R 28% PLANNING R 16,955,994 R 27% SOCIAL SERVICES R 24,000,000 R 47% WASTE AND FLEET MANAGEMENT R 9,344,000 R 15% 3% USDG OPSCAP R 13,390,000 R 16% TOTAL R 756,216,000 R 351,366,553 46%

10 Projected Cashflow for the remaining period (Mar – Jun)
Monthly Cash Flow Actual Exp February'19 Projected Exp March'19 Projected Exp April'19 Projected Exp May'19 Projected Exp June'19 Capital Expenditure R 70,240,221 R 101,500,874 R 120,000,000 R 144,875,574 R 88,906,591 Total Expenditure Cumulative R 300,932,961 R 402,433,835 R 522,433,835 R 667,309,409 R 756,216,000 Expenditure % 40% 53% 69% 88% 100%

11 USDG Projects and progress after revision

12 PRIORITY PROJECTS Service Description Budget Commitment YTD Movement
Exp % Balance SANITATION WATERBORN SANIT INTER BULK SERV IN THABA R R R 75% R ELECTRICITY MAPHIKELA DC 132/11KV R R R WATER REFURBISHMENT OF WATER SUPPLY SYSTEMS R R R 31% R WATERBORNE SANI INTER BULK SERV IN MMMM R R R 72% R WATERBORNE SANI INTER BULK SERV IN BOTSH R R R 86% R HUMAN SETTLEMENT AND HOUSING VISTAP 2&3 REALIG REROUT BULK WATER PIPE R R 56% R REFURBISHMENT OF SEWER SYSTEMS R R R 101% -R BOTSHABELO SEC L (HOUSEHOLDS ..) - INTER R R R 69% R ROADS AND STORMWATER ROUTE 22: TAXI ROUTES BLOEMSIDE PH46 R R R 5% R SOCIAL SERVICES NALLIES VIEW CEMETERIES PROJECT R R R 55% R REFURBISHMENT OF WATER SUPPLY SYSTEMS: A R R R 111% -R INSTALLATION OF PUBLIC LIGHTING R R 38% R KGOTSONG INT SEWER RETIC R R R 59% R MOROKA(EX 27 (290) -INST WATER SEWER RET R R R 2% R T1531:SEROKI RD SECTION M BOTSHABELO R R R 99% R T1533: HILLSIDE VIEW BULK ROADS AND STOR R R R 7% R BOTS WEST EXT WAT INTER SEW RET R R R 26% R T1432:MAN : BERMAN SQUARE R R R R T1430B:BOT RD 719&718 SECTION 0 R R R R R R R 61% R

13 No. of Households to be upgraded
UPGRADING OF INFORMAL SETTLEMENTS PROJECTS Description Adjusted Budget Scope of Work No. of Households to be upgraded KGOTSONG INT SEWER RETIC R 19,100,000 Internal Water and Sewer Reticulation 211 NAMIBIA INT SEWER RETIC R 5,000,000 53 INTERNAL WATER RETICULATION RATAU R 1,950,000 Internal Water Reticulation 78 MOROKA(EX 27 (390) -INST WATER SEWER RET R 17,912,293 390 BOTS WEST EXT WAT INTER SEW RET R 11,000,000 1000 BOTSHABELO SEC L (HOUSEHOLDS ..) - INTER R 24,942,915 500 INTERNAL RETICUL (TOILETS) SECTION L R 4,000,000 Internal Sewer Reticulation 100 BOTSHABELO E&M INTERNAL SEWER RETICULATI R 9,400,000 135 TOTAL R 93,305,208 100% 2467

14 UPGRADING OF INFORMAL SETTLEMENTS PROJECTS - PROGRESS

15 UPGRADING OF INFORMAL SETTLEMENTS PROJECTS - PROGRESS

16 CATALYTIC PROJECTS Description Adjusted Budget Expected Yield
Scope of Work Progress VISTA PARK 2 REALIG REROUT BULK WATER PIPE R 14,443,151 5110 Re-align bulk water and sewer pipelines for catalytic projects Bulk water pipeline 50% complete Sewer pipeline to commence after completion of water pipeline VISTA PARK 3 REALIG REROUT BULK WATER PIPE 5200 Bulk water pipeline 100% complete Sewer to commence before end March TOTAL R 28,886,301

17 CATALYTIC PROJECTS - PROGRESS

18 ROADS PROJECTS- PROGRESS

19

20 SOCIAL AMENITIES PROJECTS - PROGRESS

21 SOLID WASTE PROJECTS - PROGRESS

22 THANK YOU