1 Muon Installation Status
Geoff Tappern 7/22/2019 Muon Plenary Meeting

2 Muon Installation Phases
Phased installation:- Phase 1 all 12 BMF, 6 BOG, and 4 BOF - completed. Phase 2a BMS chambers in sector 10 – completed. Phase 2b BMS chambers in sector 16 – completed. Phase 3a 6 BML (completed), and 3 BOL (1 installed) in sector 13. Phase 3b will be installation of EIL4 at end A. Phase 4 is muon installation after the release of the jacks of the BT coil. Also muon rails and brackets will be checked at this stage, and adjusted to position. 7/22/2019 September 2005 Muon Week

3 Sector 13 7/22/2019 September 2005 Muon Week

4 BML & BOL Installation sector 13
7/22/2019 September 2005 Muon Week

5 Preparations for BML 7/22/2019 September 2005 Muon Week

6 BML Installation 7/22/2019 September 2005 Muon Week

7 Survey rails BOL sector 13 end A
7/22/2019 September 2005 Muon Week

8 BOL Installation through truck
7/22/2019 September 2005 Muon Week

9 BML Installation 7/22/2019 September 2005 Muon Week

10 BOL Installation through truck
7/22/2019 September 2005 Muon Week

11 Barrel Muon Layout 7/22/2019 September 2005 Muon Week

12 Muon rail & Bracket Positions
7/22/2019 September 2005 Muon Week

13 Bracket and rail manufacture
7/22/2019 September 2005 Muon Week

14 Phase 4:-Now Brackets and rails
7/22/2019 September 2005 Muon Week

15 BOS & BOL Bracket Installation
7/22/2019 September 2005 Muon Week

16 BOS & BOL 7/22/2019 September 2005 Muon Week

17 Monday Sept 5th 7/22/2019 September 2005 Muon Week

18 BMS Installed chambers sector 16
7/22/2019 September 2005 Muon Week

19 BMS Sector 2 & 8 7/22/2019 September 2005 Muon Week

20 BMS Sector 2 & 8 7/22/2019 September 2005 Muon Week

21 BMS Sectors 2 & 8 7/22/2019 September 2005 Muon Week

22 BMS Sectors 4 & 6 7/22/2019 September 2005 Muon Week

23 BMS Sector 4 7/22/2019 September 2005 Muon Week

24 Mast climbing platform and frame
7/22/2019 September 2005 Muon Week

25 Phase 4 – Part of rails & access installation
7/22/2019 September 2005 Muon Week

26 Muon layout 7/22/2019 September 2005 Muon Week

27 Muon Summary In all cases of installation to date there have been problems in achieving the positional accuracy required. Typically play in brackets and bow of rails. Rail alignment, survey and adjusting is very time consuming. Rail & bracket delivery just in time!!!!! Services installation concerns. Connection to installation frame – watch pitch and “Z”. Lifting beams inc TIS approval will be dealt with at Work-package and PPSPS meeting in future. Also to include procedure. BML & BOL rail installation hit by many small clashes with bolt heads, feet, brackets. All relatively trivial items but each takes many hours to fix. “Z” survey target required on all rails. 7/22/2019 September 2005 Muon Week