1 The SMART People Mover – for Today
AUSTRANS The SMART People Mover – for Today Piers Brogan Commercialisation Manager Bishop Austrans Pty Ltd

2 PRESENTATION OVERVIEW
Introduction to Austrans Benefits of Austrans Case Study One – Brisbane Airport Case Study Two – Gold Coast CBD Case Study Three – Parramatta - Strathfield Call to Action The SMART People Mover

3 VALUE FOR MONEY Capital Costs Operating Costs Financial Outcomes
Gross Mass t t Capital Costs Light, small vehicles Narrow corridor Small stations Operating Costs No crew Minimal energy Financial Outcomes No operating subsidies Capital cost contribution Gross Mass/Axle 16t t Gross Mass t t Gross Mass/Axle 2t t The SMART People Mover

4 IMPROVED PASSENGER BENEFITS
Frequent Services No Timetables Comfortable, Fast, Convenient Simple and Transparent Operation Adaptable Feeder /Distributor Line haul Network The SMART People Mover

5 ENVIRONMENTALLY FRIENDLY
Environmentally Sustainable Emission Free Energy Miser Greenhouse friendly Minimal Visual Intrusion and Severence Fits Urban Fabric The SMART People Mover

6 COMPETITIVE ADVANTAGES
Less Passengers per Vehicle Greater Frequency of Vehicles Shorter Wait Times Lower Mass and Smaller Dimensions Lower Guideway Costs Lower Operating and Energy Costs Tighter Corners and Steeper Grades Expandability and Modularity The SMART People Mover

7 POSSIBLE SYDNEY APPLICATIONS
The SMART People Mover

8 To Cronulla & Sunderland
POSSIBLE EXTENSIONS To Mona Vale To Bringelly To Cronulla & Sunderland The SMART People Mover

9 ALIGNMENT Case Study 1 - BRISBANE AIRPORT The SMART People Mover
Domestic Terminal ALIGNMENT International Terminal Toombul Rail Station Shop Commercial The SMART People Mover 8.2 km

10 PEAK OPERATIONS Case Study 1 - BRISBANE AIRPORT 9 Seated (+9 standing)
31 Vehicles All Stop Operation, On Line Stations 30 secs Minimum Headway 2168/hr Passengers 8 mins Travel, 30 secs Wait Speed 56 kph av., 70 kph max. 21 secs av. Station Dwell PEAK OPERATIONS The SMART People Mover

11 FINANCIALS Case Study 1 - BRISBANE AIRPORT Capital Cost Operating Cost
Retrofit - 44% Heavy Rail Operating Cost $0.80 per trip - 67% of Heavy Rail NPV of Costs 35% of Heavy Rail Revenue $5.00 av. per trip Outcomes $4.20 per trip - Operating Profit Pays off Capital - 10 years Positive NPV FINANCIALS The SMART People Mover

12 ADVANTAGES Case Study 1 - BRISBANE AIRPORT Value for Money
More profitable than Heavy Rail Less risk to Government of project failure Passenger Benefits Higher Frequency No Waiting No Timetables Better Inter-terminal Link Environmentally friendly Enhance the Airport’s image ADVANTAGES The SMART People Mover

13 OPTIONS Case Study 1 - BRISBANE AIRPORT System Network
Increase Vehicles Intermediate Turnarounds Off Line Stations Reduce Headways Increase Max Speed Linked Vehicles All Passengers Seated/Belted Network Loop around Commercial Centre Link to CBD Connect Future Terminals Links to Airport Workforce Nodes OPTIONS The SMART People Mover

14 ALIGNMENT Case Study 2 – GOLD COAST CBD The SMART People Mover
Southport Paradise Waters Surfers N Surfers S Cascade Gardens Pacfic Fair Broadbeach 7.7 km ALIGNMENT The SMART People Mover

15 PEAK OPERATIONS Case Study 2 – GOLD COAST CBD 9 Seated (+9 standing)
32 Vehicles All Stop Operation 30 secs Minimum Headway 4650/hr Passengers 6 mins Travel, 1.1 mins av. Wait Speed 50 kph av., 70 kph max. 25 secs av. Station Dwell Time PEAK OPERATIONS The SMART People Mover

16 FINANCIALS Case Study 2 – GOLD COAST CBD Capital Cost Operating Cost
62% of Light Rail Operating Cost $0.35 per trip - 83% of Light Rail NPV of Costs 50% of Light Rail Revenue $1.85 av. per trip Outcomes $1.50 per trip - Operating Profit Pays off Capital - 10 years Positive NPV FINANCIALS The SMART People Mover

17 ADVANTAGES Case Study 2 – GOLD COAST CBD Value for Money
More profitable than Light Rail Private finance option Passenger Benefits Higher frequency No effective waiting No need for timetable Environmentally friendly Low greenhouse emmissions Reduced road congestion Reduced road accidents Enhance the City’s image ADVANTAGES The SMART People Mover

18 OPTIONS Case Study 2 – GOLD COAST CBD System Network
Increase Vehicle Numbers Intermediate Turnarounds Off Line Stations Reduce Headways Increase Speeds Linked Vehicles All Passengers Seated/Belted Network Links to Heavy Rail Robina (Sth), Nerang (Cntr), Helensvale (Nth) Feeder Loops to Suburbs OPTIONS The SMART People Mover

19 ALIGNMENT Case Study 3 – PARRAMATTA STRATHFIELD The SMART People Mover
Parramatta Rail Station Paramatta East Camellia Rail Station Silverwater Newington ALIGNMENT Olympic Plaza Aquatic Centre Tennis Centre Homebush Underwood Rd 11.3 km Strathfield The SMART People Mover

20 PEAK OPERATIONS Case Study 3 – PARRAMATTA STRATHFIELD
9 Seated (+9 standing) 55 Vehicles On Line Stations Conditional all Stop Operation 30 secs Minimum Headway 5000/hr Passengers 45 secs av. Wait 8 mins Travel 60 kph max. speed PEAK OPERATIONS The SMART People Mover

21 FINANCIALS Case Study 3 – PARRAMATTA STRATHFIELD Capital Cost
90% of Busway option Operating Cost $0.70 per passenger - 70% of Busway option NPV of Costs 55% of Busway option Revenue $2.05 av. per trip Outcomes $1.35 per trip - Operating Profit Break even - 40 years FINANCIALS The SMART People Mover

22 ADVANTAGES Case Study 3 – PARRAMATTA STRATHFIELD Value for Money
Less expensive than transitway Better return from the fare box Passenger Benefits Higher frequency No effective waiting No need for timetable Supplements bus/rail services to Olympic Park Environmentally friendly Reduced surface congestion Enhance image Parramatta & Olympic Park ADVANTAGES The SMART People Mover

23 SYSTEM OPTIONS Case Study 3 – PARRAMATTA STRATHFIELD
Increase vehicle numbers Intermediate turnarounds Reduce headways Off line stations Increase speeds Linked Vehicles All Passengers Seated/Belted SYSTEM OPTIONS The SMART People Mover

24 Carlingford Rail Station
Case Study 3 – PARRAMATTA STRATHFIELD Strathfield E Parramatta Carlingford Court Carlingford Rail Station Telopea Rail Station Dundas Rail Station Rydalmere Rail Station Westmead Hosptial Epping Macquarie Centre Epping Rail Station Parramatta Rail Station To Burwood Silverwater Newington Olympic Plaza Aquatic Centre Tennis Centre Homebush Underwood Camellia Rail Station To Concord West Rail Station NETWORK OPTIONS The SMART People Mover

25 The SMART People Mover - for Today
SUMMARY The SMART People Mover - for Today Transport Solutions Value for Money Passenger Attractive Environmentally Sustainable and Greenhouse Friendly First Commercial System in 2008

26 Call to Action Concept now proven
Future Developments Application Specific What we want from you: Champion an Application Claims Verified Commission Feasibility Study Application Specific Collaborators rrrrrrrrrrrrrrrrrrrrrrrrrr The SMART People Mover

27 6 min video attached over this page