Presentation is loading. Please wait.

Presentation is loading. Please wait.

Spectroscopy STAP Meeting ESS, 8th of April 2019

Similar presentations


Presentation on theme: "Spectroscopy STAP Meeting ESS, 8th of April 2019"— Presentation transcript:

1 Spectroscopy STAP Meeting ESS, 8th of April 2019
Introduction & Update Spectroscopy STAP Meeting ESS, 8th of April 2019 Ken Andersen, Neutron Instruments Division, European Spallation Source ERIC

2 Welcome! We are now on a regular schedule Format of this meeting:
2 STAP meetings per year, synchronised with SAC meetings Reporting to SAC meeting Spring: short video meeting Autumn: longer physical meeting Format of this meeting: Focused on status updates and current hot topics Last vidyo meeting was a test – improvements made

3 Purpose and Remit of Instrument STAPs
Scientific and Technical Advisory Panels one per instrument class STAP: instrument advisory body science case and functional requirements all aspects which impact on scientific output of instrument (not just instrument project) technical and project decisions early science Advice to both NSS management and instrument teams collaborative & non-adversarial setting NSS management & instrument teams take advice constructively allows NSS management & instrument teams to make good, informed decisions Each STAP meeting results in written recommendations followed up in subsequent meeting(s) presented at following SAC meeting SAC report includes highlights of STAP reports – presented to Council

4 December Annual Review
Recommendation A2.1 “The Committee believes that resources laboratory-wide should now be focussed on achieving at least the minimum criteria for a “day 1 of science” milestone. This will necessitate postponing activities which are not needed for the new focus, and reallocating resources between the key project areas (CF, Accelerator, Target, NSS). This focus will also provide a powerful driver toward cross-directorate cooperation and the effective centralisation of certain functions and capabilities, which inevitably must be done, but which will be of greatest benefit if it precedes installation. Scheduling and risk prioritisation/mitigations should be adapted to reflect the importance of this new milestone”

5 Rebaselined Schedule for Neutron Beam Instruments V4
Rebaselined Schedule for Neutron Beam Instruments V4.1, 29th November 2018 aligned with accelerator ramp up (ESS ) West sector North sector East and South sectors Current date First access to NSS bldg (E01) SOUP (3NBI*) BOT 8NBI* in User Program Preliminary Design Detailed Design Manufacturing & Procurement Installation & Integration Hot Commissioning/Early science Operation ES March 2023: Early Science with expert users (ES) Selection of first NBI for SOUP * NBI = Neutron Beam Instrument

6 Rebaselined schedule for NBI. Installation (TG4 –> TG5) (V4
Rebaselined schedule for NBI* Installation (TG4 –> TG5) (V4.1, 29th November 2018) from Installation workshops with teams building first 8 Instruments (May & Nov) NSS access to E01 Start User Program (3NBI*) Beam on Target NSS access to D01 NSS access to D03 8 NBI* in User Program Cave installation & fitout OOB Guides & shielding In bunker installation Cold commissioning NSS access to E02/2 ES Float for R-BOT: TBL ~ 21 weeks BEER ~ 7 weeks CSPEC & BIFROST ~ 4 weeks MAGIC & ESTIA ~ 1 week NSS has no float for R-SOUP, but does have 8 possible candidates Manufacturing on critical path for BEER, C-SPEC, BIFROST & MAGIC, not E01 access. West sector North sector East and South sectors Parallel installation in & out of bunker assumed for LOKI, ODIN, DREAM & ESTIA. * NBI = Neutron Beam Instrument

7 Highlights from October SAC meeting
Backup scenarios for first three instruments First three: DREAM, LOKI, ODIN Backup for DREAM is MAGIC Backup for LOKI is SKADI: decision point in mid-2019 No direct backup for ODIN: take any of the other first 8 Early Scientific Success = trusting your instrument Thorough hot commissioning, focused on benchmarking STAP reports highly appreciated Constructive and direct information given Instruments should make full use of V20 in 2019 Capability gap analysis is good starting point Be careful not to give impression of decisions already made Reinstate STAPs for spin-echo and particle physics Start annual proposal rounds Prioritise unique concepts Evaluate instrument completion together with new instruments Move ahead quickly

8 What else has happened since last time
All instruments have passed TG2 New “Early Science” milestone identified Expert users on first instruments in 2023 Initial Operations funding All countries working to fund the Initial Operations period Common shielding project moving ahead with 9 instruments PDR took place in January All 5 spectroscopy instruments included. CSPEC and BIFROST have accepted price offers Evolving boundary conditions for shielding Creation of ”blue” zones on cave roof Dose constraints in nearby offices TAs are finally progressing quickly Staffing situation is evolving CSPEC 2nd instrument scientist position advertised BIFROST lead engineer position soon to be advertised

9 Charge for this meeting
Instrument teams Prepare status reports and present them Identify hot topics and raise them Provide feedback on actions NSS management Organise the meeting Inform of main developments since last meeting STAP To what extent is the progress of the instrument projects consistent with the planned timeline? To what extent are the instrument projects on track for delivering early science?

10 Thank you! ESS site 2016 5th June 2015


Download ppt "Spectroscopy STAP Meeting ESS, 8th of April 2019"

Similar presentations


Ads by Google