1 Annual Attachment O Stakeholder Meeting
August 30, 2018

2 About Wabash Valley Power (WVPA)
WVPA is a not-for-profit electric generation & transmission company Supplies its 23 rural electric distribution members with 100% of their wholesale power and transmission requirements Members located in Indiana, Illinois and Missouri Governed by members

3 Joint Transmission System (JTS)
Joint Ownership in the JTS WVPA Indiana Municipal Power Agency (IMPA) Duke Energy Indiana Agreement strives for each party to maintain an investment level equal to their load ratio share of system usage WVPA’s interest includes all rights to the use, output and capacity of the transmission and local facilities constituting the JTS MISO schedules, manages and oversees use of the JTS Duke primarily responsible for system operations, maintenance and administration

4 Protocol Timeline Action Date (Historical) June 1
Posting of annual update Information exchange period begins Review period begins September 1 Deadline for annual meeting November 1 Deadline for joint meeting on regional cost-shared projects December 1 Deadline for Interested Parties to submit information requests January 10 Deadline for Transmission Owners to respond to information requests January 31 Deadline for Interested Parties to submit Informal Challenges February 28 Deadline for Transmission Owners to respond to Informal Challenges Any rate changes agreed to by the Transmission Owner will be included in the Information Filing and will be reflected in the Annual Update for the following Rate Year March 15 Transmission Owners submit informational filing March 31 Deadline for Interested Parties to file Formal Challenge

5 2018 Attachment O Summary based on 12/31/17 ($ in 000’s)
Item 2016 2017 Transmission Rate Base $97,046 $136,180 Transmission Revenue Requirements: Operation & Maintenance $ 6,486 $ 9,481 Depreciation & Amortization 2,973 3,891 Other Taxes 74 120 Return 6,157 8,938 Gross Revenue Requirement $15,690 $22,430

6 Contact Information All requests for information must be submitted no later than December 1, 2018 Requests must be submitted in writing to: Questions and answers will be sent via to the requesting party and posted on the MISO website