Presentation is loading. Please wait.

Presentation is loading. Please wait.

System tests at CEA O. Piquet 19/03/2019

Similar presentations


Presentation on theme: "System tests at CEA O. Piquet 19/03/2019"— Presentation transcript:

1 System tests at CEA O. Piquet 19/03/2019

2 System tests at CEA 5 RFQ sections Pick-ups (x28) Tuners x60
Power couplersx2 RFQ support

3 Typical flow chart for the RFQ section fabrication
ESS RFQ section Typical flow chart for the RFQ section fabrication

4 Check report about tridimensional measurements sent by mecachrome
RFQ section machining RFQ machining done at Mecachrome Vane assembly with 30µm tolerance Check report about tridimensional measurements sent by mecachrome Vane machining with 20µm tolerance The manufacturing of the RFQ is very closely followed with weekly meetings and visit to Mécachrome

5 Mechanical error study
Beadpull measurement Why beadpull measurements? Check the machining and the assembly of the 4 vanes according to RF design at different step of section fabrication 2D RF simulations of the cross-section vs. abcsissa Electrical parameters of RFQ vs. abscissa in order that Transmission Line model (TLM) mimics physical RFQ Mechanical error study Definition of CQQ, CSQ and CTQ parameters Vane machining with 20µm tolerance Geometry errors ~ Capacitance perturbations of the TLM Tolerances given by tuner range Vane assembly with 30µm tolerance

6 Magnetic field measurement for the 4 RFQ quadrants
Beadpull measurement Beadpull principle: Measure the magnetic field inside each RFQ quadrant Define TLM parameters according these measurements Compare these measured capacitances with theoretical values defined in the RF design study Principle of beadpull measurement: resonance frequency is shifted proportionally to the square of field at bead location; frequency shift is too small to be directly measured, phase shift is measured instead using a VNA. 4 assembled vanes Magnetic field measurement for the 4 RFQ quadrants

7 Beadpull measurement │CQQ │ /C≤1.85.10-2 │CSQ │ /C≤2.35.10-2
First beadpull measurement at Mecachrome Mathematical processing of the magnetic field measurement with the same process used for the RF design of the RFQ Beadpull results │CQQ │ /C≤ │CSQ │ /C≤ │CTQ │ /C≤ Beadpull testbench

8 Comparison with first assembly beadpull
Brazing at bodycote Beadpull of the RFQ section with all these definitive ports and flanges Comparison with first assembly beadpull Differences could be explain by the use of ‘’test’’ ports for the first beadpull Beadpull results │CQQ │ /C≤ │CSQ │ /C≤ │CTQ │ /C≤

9 Brazing At bodycote Brazing at 850°C

10 Leak test at bodycote Defined by the CEA (and ESS) RFQ Helium Leak Testing Procedure : First check by helium spraying of the different interfaces (welding and brazing part, seals, …) Leaks on seals are fixed (changing the gasket, sealing surface preparation, …) Global (or Partial) leak testing using a bag The leak should be less than mbar.l.s-1 Done by Mecachrome subcontractor with CEA team

11 FINAL machining At Mecachrome
Tridimensional measurements of the section after brazing Final machining of the section (end faces and locating) Definition of the beam axis and interfaces with the next section Hydraulic tests of the cooling channels and cooling plates Final tridimensional measurements before transportation to Saclay

12 Final leak test at Saclay Final beadpull at Saclay
Reception tests at CEA Final leak test at Saclay Done by Mecachrome subcontractor with attendance CEA # Value Method S1 mbar.l.s-1 Final global test at Saclay Beadpull results Final beadpull at Saclay │CQQ │ /C≤ │CSQ │ /C≤ │CTQ │ /C≤

13 Installation of the first section on the RFQ support
ESS RFQ section Installation of the first section on the RFQ support Documentation to manage Check of the installation procedure

14 RFQ couplers - 2 power coupling loops (in Section 3) for 1.6MW maximum power - Similar RF window designed for cryomodule couplers (only frequency adaptation) - Produced by PMB (same company for 120 cryomodule couplers) - A third coupler built in order to mitigate risk

15 RFQ couplers Coupler description: Electron current measurement +
Vacuum gauge Cooling for RF loop Cooling for ceramic window Coupling performed by rotating the coupler around its rotation axis Air side arc-detector Vacuum side arc-detector

16 Tests of sub-assemblies
Tridimensional measurements for each element Vacuum test of the different parts of the couplers hydraulic test of the cooling circuits SAT report For welding and brazing parts Different bags to isolate EPDM (temporary) gasket from nominal interface Visual inspection (Grooves, surface…) # Value Method Brazing/CF parts < mbar.l.s-1 Partial test before assembly

17 Coupler assembly Vacuum test of the coupler: (2 EPDM gaskets)
Assembly of 3 power couplers Assembly procedure # Value Method EPDM seals < mbar.l.s-1 * Partial test after assembly * no instant leak, only permeation after several minutes

18 Coupler qualification tests
Couplers are assembled on the cavity test: - Installation of EPDM seals - Installation of RF seals - Rotation of the coupler to get the optimal coupling - Leak test of the coupler-cavity interface - Coupler (and cavity) instrumentation installation

19 Coupler qualification tests
Instrumentation: Protection of systems (RF source, coupler, cavity…) Stop the RF in less than 20µs in case of interlock Acquisition of data (RF, arc, electron current, temperatures, vacuum…) Fast interlocks: - Electron current (*2) - Arc detection (*4) - Reflected power (*2) - Vacuum: coupler (*2) and coupling cavity Automatic procedure: Start at low power (from Pmin=1kW to Pmax=1000kW) Start with short pulses (from 100µs to 3.6ms) Start at low repetition rate (from1Hz to nominal repetition rate: 14Hz) Increase the RF power according the level of vacuum inside couplers and coupling cavity

20 Coupler qualification tests
Typical conditioning process Coupler qualification report 3 days long run test at maximum power (1MW), maximum width (3.6ms) and maximum repetition rate (14Hz) Power Temperatures Vacuum

21 And ready for transportation at ESS
RFQ couplers 3 conditioned couplers Requirements 2 power couplers Maximum power per coupler: 1MW Voltage pulse length: 3.5ms Voltage pulse rate: 14Hz Achievement 3 power couplers Maximum power per coupler: 1MW Voltage pulse length: 3.6ms Voltage pulse rate: 14Hz And ready for transportation at ESS Threshold used during coupler test at Saclay Fast interlocks Threshold for ligth émission 1.3 Lux Threshold for current electron 9mA Vacuum Hardware upper threshold 6*10-6mbar Hardware lower threshold 4*10-6mbar Software threshlod 2.5*10-6mbar Temperatures window part 40°C RF loop Water flows 4.5l/min 3l/min All the interlocks (Thresholds) defined by the coupler test done at Saclay will be used as a baseline for the RFQ conditioning

22 Visual inspection (Grooves, surface, hydraulic connections…)
Tuners (60) Used for the final tuning of the RFQ: Setting of the RFQ frequency and the voltage law = correction of mechanical defaults of the RFQ (fabrication…) Control the allowable range Position range on the RFQ = 60mm Visual inspection (Grooves, surface, hydraulic connections…)

23 Tuners (60) Helium leak test for each Tuners:
Performed by the company, with a CEA procedure (global leak test), before and after hydraulic tests. At Saclay, leak test on 2 tuners per transport box have been performed (in the max and min position) -> 8 Tuners FAT (with attendance of CEA ) and SAT reports Tuner assembled on RFQ section 1

24 Conclusion Status of Tuners, Couplers and RFQ sections
Vacuum RF conditioning Dimensions Beadpull Tuner Passed (10-9mbar l s-1) N.A. OK Couplers Done in March 2018 1MW RFQ sections S1: mbar l s-1 At ESS in Nov 2019 S1: Ok S1: OK S2: < 10-10mbar l s-1 after brazing S2: OK S2: OK before brazing S3: mbar l s-1 after brazing S3: OK before brazing S4: May 19 S4: First in April S5: May 19 S5: First in April : SAT of Section1 at Saclay Requirement for RFQ installation/conditioning at ESS Before the conditioning of RFQ, some ESS systems must be characterized and qualified: - RF power sources - Local protection System of RFQ (interlocks, speed…) - LLRF - Acquisition of the voltage Law - Control/command for RFQ (automatic software for conditioning…) - Vacuum system fully operational with downstream/upstream beam valves - Beam before RFQ entrance


Download ppt "System tests at CEA O. Piquet 19/03/2019"

Similar presentations


Ads by Google