Download presentation
Presentation is loading. Please wait.
Published byφώλος Βλαχόπουλος Modified over 6 years ago
1
ACEC/TxDOT joint education program Spring 2019
TxDOT PS&E Package & Improving Quality of Plans April 25, 2019
3
Presentation Overview
Pre-PS&E Elements to Consider Plans Plan Preparation & Reviews Specifications & Estimate Required Supporting Documents Pre-Letting Bidder’s Questions & Addendum
4
Table of Contents 1 Introduction - Laura 1 - 5 2
Elements to Consider at Pre - PS&E – Helen 6 - 8 3 Plan Preparation – Chad & Spenta 9 - 15 4 Plan Review – Laura
5
Table of Contents (cont.)
5 Supporting Documents: General Notes – Laura 1002 Form, Spec List, Significant Project Procedures – Duc TDLR Requirements, Final Certifications – Helen Environmental Clearance, AFA – Helen Temporary TCP – Etienne Contract Time Determination – Etienne Estimate Preparation – Etienne 6 Bidder’s Questions & Addendum – Sohrab
6
Elements to Consider at Pre-PS&E
Design Manuals: Various types of Design Manuals found in TxDOT website:
7
Elements to Consider at Pre-PS&E (cont.)
Type of Roadway: Interstate, Freeway, Principal Arterial, Minor Arterial, Collector, or Local Road Design Criteria: Roadway Design Manual covers the design criteria 2R = Non-Freeway Resurfacing or Restoration Projects - restore the pavement structure, riding quality, or other necessary components to their existing cross section configuration 3R = Non-Freeway Rehabilitation Projects - preserve and extend the service life of the existing roadway and enhance safety 4R = New Location and Reconstruction Projects - highest type design 5R = Mobility Corridor Projects - generate, or produce anew, very long term transportation opportunities Special Facility & Miscellaneous - includes off-system bridge projects, historical roadways or structures, park roads, and bicycle facilities, median barrier, MBGF, etc.
8
Elements to Consider at Pre-PS&E (cont.)
Fund Sources: FHWA, State, or Local Government Stakeholders: FHWA, TxDOT, Counties, Cities, Corp of Engineers, MPO, NCTCOG, Developers, Utility Companies, Railroad Companies, etc. Other Elements: SUE, Survey, Hydraulic Studies, ROW Mapping, Identify Utility Conflicts, Schematics, Environmental Studies, Public Meetings/Hearing, ROW Acquisitions, RR Coordination, USACE Permits, etc.
9
Roadway Design Criteria
Plan Preparation Roadway Design Criteria Design Summary Report (DSR) Initially set in schematic phase Form 1002 Design Criteria Sheet Easy reference for designers Update as criteria is updated Still need to refer to Design Manual and Standards Identify/verify Design Exceptions and Design Waivers Design Concept Conference / Kickoff Meeting Have decision makers in the room Action items for unresolved items – FOLLOW UP!
10
Plan Preparation (cont.)
Roadway Design Criteria TxDOT Manuals (Note: Always use latest manual – unless otherwise noted) PS&E Preparation Manual Roadway Design Manual Bridge Design Manual Bridge Detailing Guide Hydraulic Design manual Texas MUTCD Other applicable State or Local Design criteria manuals Check Preferences with Area Engineer and note in criteria Check schematic design criteria Environmental Commitments ROW needs/utility conflicts Incorporate VE study recommendations
11
Plan Preparation (cont.)
Plan Set Development Production Automation Global revisions Drives consistency in the plan set Reduce time to make non-design related revision Plan Sheet Appearance Standard scales Text sizes – existing vs proposed vs titles Use of screening (based on disciplines) OpenRoads Implementation Note that the 3D model has to be constantly updated as design progresses
12
Plan Preparation (cont.)
Drafting Guidelines File Naming Confirm and follow any client preferences Reference Files Master Reference File Master Text File Text Replacements – Utility automation processes Sheet numbering CSJ, Federal Aid No., District, Other? File name and location
13
Plan Preparation (cont.)
General Plan Set Title Sheet, Index of Sheets and Border – Follow TxDOT Standards Bridge Sheets – Use TxDOT Border and FDOT Font Index of Sheets Plan set order Titles must match Multiple Engineers seal this sheet Checklists General Notes PDF Portfolios Design base files (note: TxDOT should be able to replicate) OpenRoads files and 3D model
14
Plan Preparation (cont.)
Summary Sheet Preparation Bid Items Appropriate Bid Items (know your specifications – subsidiary items should not be paid separately – pay attention to one-time use items) Area and District Preferences Note that bid items will affect design. Need to know bid items/preferences prior to final design. Select commonly used bid items Quantities Values displayed add up to Total displayed Rounding per PS&E Preparation Manual (Don’t let Excel fool you!) Document quantity take-offs! Last minute changes Confirm that the complete spreadsheet gets reflected on your drawings Confirm earthwork – verify removal of existing pavement (Typical Sections)
15
Plan Preparation (cont.)
Summary Sheet Preparation TxDOT Quantity Summary Worksheet Single source for quantities Used to create Summary Sheet Used to Estimate Aids in unit price determination Summary Sheet should match estimate Make sure that all final summary sheets and E&Q Sheets match
16
Plan Review All plans must be reviewed for thoroughness, accuracy, and clarity. PS&E Preparation Manual, Chapter 2 provide details of Plan Set Development There are 30%, 60%, 90%/95%, and 100% reviews prior to advertising the construction project for letting. Each District has a checklist for each required submittal. Each PS&E package is reviewed by different District Departments such as Transportation Plans & Development (TP&D), Construction, Traffic Operations, Area Office, District Lab/Pavement Engineer, etc. Per District request, Design and Traffic Divisions can assist in reviewing PS&E in early phases (30% and 60% reviews).
17
Plan Review (cont.) In addition to PS&E reviews, the following items are also reviewed: Bridge Layouts Retaining Wall Layouts Railroad Layouts, Exhibit A Hydraulic Report/Analysis Pavement Design Report Sequence of Work/ Traffic Control Concepts
18
Plan Review (cont.) Reviews – 30%, 60%, & 90/95% Pre-PS&E Preparation
Final PS&E Pre-Letting Progress to next submittal Plan Review Conflict Resolution Meetings `` Address Comments
19
Project General Notes are included in the Proposal and Plan set
The purpose of the General Notes is to provide various supplemental data required by the specifications in one location General Notes vary by District There are required general notes and optional general notes. The General Notes should provide clear instructions. General Notes must be prepared by the Project Manager who is familiar with the Project.
20
General Notes (cont.) General Notes provide information such as base material requirements, gradation requirements, density requirements, and surface treatment data. General Notes show basis for estimating each of the pay quantities of the contract, which cannot be directly measured from the plans. These include such items as sprinkling, rolling, blading, lime, fertilizer, asphalt, aggregate, etc.
21
General Notes (cont.) General Notes should be updated to match the latest District General Notes. General Notes contain additional specifications that are specific to the project. Do not include notes that may create confusion or conflicts with the plans. When the project requires field office and laboratory, notes to Item specify the type and size of building with required equipment and appurtenances. Project Manager to work closely with the Area Engineer, who oversees the construction of the project, to add necessary notes to notify Contractor of specific event(s) that may impact the sequence of work.
22
General Notes (cont.) General Notes is part of the contract document; therefore, it must clearly indicate its content. General Notes shown in the Proposal and Plan Set must be identical in content. General Notes may clarify items that are considered as subsidiary to a specification item.
23
1002 Form Required at 100% PS&E This form should be completed and carefully checked when preparing the submission to avoid overlooking any of the supporting papers. Provides Austin with record of all supporting documents
24
1002 Form (cont.) Page 2: Financial Information, Environmental Status, Local Participation, Railroad Agreement, Contract Time Determination, District Contact Information, and TDLR Inspection Requirements. The above information can be found in TxDOT Connect.
25
1002 Form (cont.) Page 3: Project information should match information shown in TxDOT Connect Shows basic design criteria of a specific project Shows ADT & functional classification Provides a request/approval document for design exceptions/design waivers approved at the District level
26
List of Governing Specifications and Special Provisions
Spec List is included in the Proposal of all Construction Contracts let by TxDOT Spec List includes: Standard Specifications Special Specifications Special Provisions
27
List of Governing Specifications and Special Provisions (cont.)
Standard Specifications = Items 1 – 789 in the Standard Specifications for Construction & Maintenance of Highways, Streets, and Bridges Items 1-9, the General Requirements and Covenants are required for all contracts. Standard specifications includes description, materials, equipment, construction methods, method of measurement, and method of payment for items used in the project. Standard Specifications = Items 1– 789 in the Standard Specifications for Construction & Maintenance of Highways, Streets, and Bridges Items 1-9, the General Requirements and Covenants are required for all contracts. Standard specifications includes description, materials, equipment, construction methods, method of measurement, and method of payment for items used in the project.
28
List of Governing Specifications and Special Provisions (cont.)
Special Specifications (SS) = Items 1000 and above. SS are methods and/or items of work that are not covered by Standard Specifications. They may introduce a new description, materials, miscellaneous classification, construction methods, equipment, measurement, and/or payment articles. There are: Statewide Special Specifications Districtwide Special Specifications One-time use Special Specifications
29
List of Governing Specifications and Special Provisions (cont.)
Special Provisions (SP) = Special Provisions modify Standard Specifications or Special Specifications. There are: Statewide Special Provisions Districtwide Special Provisions One-time use Special Provisions Triple Zero Special Provisions describes conditions included in a contract which do not relate directly to a work item specification. For new SS and SP, the Project Manager submits the completed Form 1814 to the Roadway Specifications Section (CST_RDWY_SPECS) to receive a new Special Provision or Special Specification number.
30
List of Governing Specifications and Special Provisions (cont.)
TxDOT website: Required Checklists Federal Aided Construction Required Check List Non-Federal Aided Construction Required Check List Federal Aided Maintenance Required Check List Non-Federal Aided Maintenance Required Check List
31
Form 2229 - Significant Project Procedures
Form 2229 is required as part of PS&E Submittal package A Significant Project is: on an interstate or other controlled access facility; lies within a designated Transportation Management Area (urbanized area with a population of over 200,000 individuals); has intermediate-term or long-term stationary lane closures, or on any highway (IH, US, SH, FM, etc.) having an ADT of more than 20,000 and has long-term lane closures. This form has criteria to help define a significant project however a project can still be considered significant if the District elects to do so.
32
Form 2229 (cont.) Common Traffic Operations Strategies
Required Traffic Operations Strategies Common Traffic Operations Strategies
33
Form 2229 (cont.) Common Public Information Strategies
Required Public Information Strategies Common Public Information Strategies
34
Texas Department of Licensing & Regulation (TDLR) Requirements
If project has pedestrian elements like sidewalks, curb ramps, bike trails, etc. and the construction cost is >$50,000, TDLR inspection is required. The TDLR Registration Form must be submitted prior to final PS&E so the Texas Architectural Barriers online System (TABS) number can be obtained. This number is shown on the Title Sheet of construction plan.
35
Certifications include the status of:
Final Certifications Certifications include the status of: R.O.W. Relocation Utility Encroachment Railroad If any element above is not cleared by the time the project is advertised, an SP 000 is required to show the estimated date(s) of completion of outstanding element(s).
36
Environmental Clearance
The PM should provide plans and support document to the Environmental Team in advance so there is enough time to clear the project. Once the environmental is cleared, the information is shown in TxDOT Connect All PS&E projects must obtain the Environmental Clearance by the ePS&E date, which is the date the final PS&E is due in Austin.
37
Project with Agreement(s)
Agreements are important. Agreements should be executed prior to ePS&E date. Railroad Agreement. SP 000 is required if the RR Agreement is not executed by the ePS&E date. Signal/Illumination/Maintenance/Landscape Agreement. These agreements are handled by the District Operations. Advance Funding Agreement (AFA) When there is a commitment from the local government for the cost of construction, the District obtains the committed funds at least 30 days prior to bid opening in order to certify financial clearance.
38
Temporary Traffic Control Plan
Objectives of Temporary TCP Provide safe workplace to workers Guide and provide safety to road users Insure smooth traffic flow 2017: Texas had 27,148 work zone crashes 165 deaths 28 workers 30 pedestrians 107 motorists, bicyclists 813 serious injuries Leading causes Drivers not paying attention Reckless or impaired drivers intruding into work space
39
Temporary Traffic Control Plan (cont.)
Source: National Work Zone Safety
40
Temporary Traffic Control Plan (cont.)
Source: National Work Zone Safety
41
Temporary Traffic Control Plan (cont.)
IH 20 WB incident, TxDOT, Kaufman Area Office, Jan 30,2019
42
Temporary Traffic Control Plan (cont.)
Advance warning Temporary drainage Minimize lane closures Adequate signs, delineation, channelization Concrete Safety Barriers, Impact Attenuators, LPCB TCP General Notes Ensure constructability Night work, weekend work and detours Ensure the work sequence and narrative match and makes sense Temporary pavement details
43
Temporary Traffic Control Plan (cont.)
TCP plans & typical sections for each phase Overnight drop-offs not authorized Ensure proper roadway materials are used Use of Google street view Coordination with adjacent property owners Coordination with TxDOT Area Office & Local Government on Special Events Adequate SW3P devices ( silt fence, rock filter dam, erosion control logs…) Ensure correct BC, TCP, WZ, CSB, LPCB, SW3P, Crash Cushion standards are used Avoid reduced speed zoning as much as practical. Drivers will reduce their speeds only if they clearly perceive a need to do so
44
Temporary Traffic Control Plan (cont.)
Example Traffic Control Plan TRAFFIC AREA WORK AREA TRAFFIC AREA EXISTING
45
Temporary Traffic Control Plan (cont.)
TRAFFIC AREA WORK AREA WORK AREA Used Low Speed zones TRAFFIC AREA Example Traffic Control Plan Typical Sections
46
Temporary Traffic Control Plan (cont.)
Summary of TCP Quantities
47
Contract Time Determination
6 Steps for Contract Time Determination 1. Identify the scope of work 2. Establish production rates for each work item 3. Adapt production rates to the project Narrowed/ tight working conditions Non-standard construction 4. Understand potential constraints Major material acquisition and delivery Historic weather trends Utilities 5. Compute contract time 6. Review and Develop Narrative PS&E review Meeting
48
Contract Time Determination (cont.)
Construction Production Rates
49
Contract Time Determination (cont.)
Construction Production Rates Baselines provided by TxDOT Used for estimating project duration Lower rates typically used for small projects Medium rates for medium size projects High rates for big projects Adapt to your project Use engineering judgement Proper critical path method Weather delays are not accounted in the rates provided by TxDOT Utility construction not accounted in the rates provided by TxDOT Site specific conditions Complexity or technical difficulties, non standard projects
50
Average Low Bid Unit Prices
Estimate Preparation Average Low Bid Unit Prices Update Bid Prices at every PS&E Submittal: 3 month, 12 month, District and Statewide
51
Estimate Preparation (cont.)
Price Comparison Consider collaborating with subject matter experts, Area Office, Construction Office, etc. Do not reinvent the wheel. PERFECT the one you have Use similar projects to generate some of your bid items Use Bid Tabulation to compare price on recent & similar projects Incorporate Site Manager averages (TxDOT Intranet only) Print out your estimate and review it item by item Have your estimate reviewed by other Engineers If project has multiple CSJs, show quantities by CSJ For each item used, read TxDOT Standard Specs for that item.
52
Bidder’s Questions Designer/PM should be available to assist the Area Engineer during pre- letting/advertising period. Area Engineer and Assistant Area Engineer are point of contact for receiving bidder’s questions and responding questions on TxDOT FTP site. Area Engineer and Assistant Area Engineer will work with the Designer/TxDOT PM to address Bidder’s questions. If applicable, it is a good practice to post the following documents in TxDOT FTP site for Bidder’s information: Pavement Design Report, Hydraulic Report, Geotechnical Report, Cross Section files/.XSR files, ROW plans, Contract Time Determination, & SUE.
53
Bidder’s Questions (cont.)
Bidders can submit pre-letting questions, by , phone and in person. All communications to Bidders must be posted on TxDOT FTP site, Responses/ Communications include notes, minutes of all meetings, s, phone notes, letter, etc. All Bidder’s questions must be posted and responded in accordance with Memo from The Chief Engineer dated Feb 13, 2019.
54
Bidder’s Questions (cont.)
Post all responses within a reasonable time, keep in consideration that there is enough time for Bidders to ask additional questions based on the responses. Same day for simple, straightforward answers. Within 48 hours for complicated questions. Response posted to the FTP site trump any responses given verbally. For complicated questions, request Bidder to provide questions in writing. Do not make statements regarding the possibility or probability of a change in plans, specifications, or quantities—by addendum or by change order.
55
Addendum When there are errors found after the project is advertised, prepare addendum, if necessary, in a timely manner so Bidders will have enough time to update their bids. Addendum is required when: The competitiveness of the bid would be in jeopardy if the changes were not made. The quantities are in error to a degree that could place the department at a disadvantage in negotiating significant corrections after contract award. The bid documents would not be substantially representative of the project unless the change is made.
56
Addendum (cont.) Designer/PM prepares the addendum with concurrence of the Area Engineer. Addendum includes: a written summary of all changes that are made to the plans and proposal. revised plan sheets, specification list, general notes, bid items & quantities, etc. addendum number and date. Addendum must be approved by District & Construction Division, and must be processed by Design Division. The Area Office notifies all prospective bidders via the FTP site once an addendum has been posted.
57
ACEC/TXDOT JEP Spring 2019 Team
American Council of Engineering Companies of Texas ACEC of Dallas – Executive Director: Karen Khan ACEC of Tarrant County – Executive Director: Brinton Payne, P.E. TxDOT Liaison Committee – Chair: Robert Brown, WSP, P.E. TxDOT Liaison Committee – Chair: Mark Schluter, P.E. Consultant Team Spenta Irani, P.E. – Jacobs Chad Gartner, P.E. – TranSystems TxDOT Team Ram Dhakal, P.E – Fort Worth District, Consultant Project Management Sohrab Islam, P.E. – Fort Worth District, Central Design Etienne Etchouekang, P.E. – Dallas District, Construction Duc Lam, E.I.T. – Dallas District, Roadway Design Laura Rodriguez – Dallas District, Project Delivery – H&H Helen Tran, P.E. – Dallas District, District Design – Plan Review
58
Questions
Similar presentations
© 2025 SlidePlayer.com Inc.
All rights reserved.