Revised Tender Timescale for DN Interruption Arrangements

Similar presentations


Presentation on theme: "Revised Tender Timescale for DN Interruption Arrangements"— Presentation transcript:

1 Revised Tender Timescale for DN Interruption Arrangements
Distribution Workstream 23rd August 2007

2 Background Mod 0090 – Revised DN Interruption Arrangements
Ofgem decision 15 March 2007 Implementation Date 1 April 2008 New regime significantly different from existing regime DNs determine interruption requirements three years ahead (e.g. Feb 2008 for 2011 onwards) DNs publish interruption requirements (May 2008) Users value interruption - bid into DN tender process DNs select bids (offers) based on interruption requirements Successful Users receive payment for being interruptible Transition Arrangements in place to 2011 (based on existing arrangements)

3 Tender timescale – Mod 0090 Interruption Requirements published 1 May 08 Bid window opens (interruption offers) 2 June 08 Bid window closes June 08 Notification of successful bids 11 July 08 Apply for NTS Exit Capacity end July 08 Issue: Present timescales allow only short amount of time to conduct analysis on interruption bids and analyse and apply for NTS Exit Capacity

4 Proposal Bring forward tender timescales by one month:
Interruption Requirements published 1 April 08 Bid window opens (interruption offers) 1 May 08 Bid window closes May 08 Notification of successful bids 14 July 08 Apply for NTS Exit Capacity end July 08

5 Proposed Timescales Discuss at Workstreams Distribution 23 Aug 07
Transmission 6 Sept 07 Mod Panel Sept 07 DMR Issued Sept 07 Close-out 18 Oct 07 FMR Oct 07 Mod Panel Nov 07 Ofgem Decision 1 Dec 07


Download ppt "Revised Tender Timescale for DN Interruption Arrangements"