Presentation is loading. Please wait.

Presentation is loading. Please wait.

RF systems introduction

Similar presentations


Presentation on theme: "RF systems introduction"— Presentation transcript:

1 RF systems introduction
Anders Sunesson RF group leader June 7, 2016

2 An artists impression of ESS

3 A builder realisation: Gallery/tunnel today

4 Overview RF systems RF distribution systems Risk workshop summary

5 ESS RF system building blocks
Modulator LLRF Distribution System Phase ref Cavity Interlock

6 RF systems RF provides the power that accelerates
155 cavities shall be powered, each from one station RF systems are placed between the wall power plug and the cavity coupler Many and complex subsystems Cooling water 50 deg C or more for collectors, loads

7 RF Technical performances
Spokes Medium β High β DTL MEBT RFQ LEBT Source HEBT & Contingency Target 2.4 m 4.5 m 3.6 m 40 m 54 m 75 m 174 m 75 keV 3.6 MeV 90 MeV 220 MeV 570 MeV 2000 MeV MHz MHz Energy (MeV) Frequency /MHz No. of Cavities βg Temp / K RF power /kW Source 0.075 - ~300 LEBT RFQ 3.6 352.21 1 1600 MEBT 3 20 DTL 90 5 2200 Spoke 220 26 (2/CM) 0.5 βopt ~2 330 Medium β 570 704.42 36 (4/CM) 0.67 870 High β 2000 84 (4/CM) 0.86 1100 HEBT

8 ESS accelerator power profile
Average beam power: 5 MW > 130 MW peak Pulse repetition rate: 14 Hz Beam pulse length: 2.86 ms 36 Medium beta cavities: 704 MHz 1.5 MW Klystrons 26 spoke cavities: 352 MHz Tetrodes Normal-conducting Linac: One RFQ and 5 DTL tanks 6 off 352 MHz klystrons 3 MW 3 Solid state amplifiers for bunchers 352 MHz, 30 kW 84 High beta cavities: 704 MHz 1.2 MW MB IOTs (klystrons as backup)

9 RF distribution system
Modulator LLRF Distribution System Cavity Interlock

10 RF distribution Transports RF power from Amplifier output to cavity coupler There will be several km of waveguides Arc detectors Directional couplers Circulators Loads In-kind delivery Courtesy of Rutambhara Yogi

11 Schedule RF systems The RF systems shall be ready to power beam for the linac up to and including medium beta by June 2019 RF for the High Beta part shall be ready to power beam by 2022 Installation shall start autumn 2017

12 Risk workshop A risk workshop was held at ESS on May 10 2016
It turned out to be a good kick-off and project workshop Indico: The workshop also issued a list of decisions and actions, see next slides

13 Risk workshop decisions
The following CDRs are required: Tender 1: Waveguides, elbows, coaxial components Tender 2: Standard RF components (bellows, shutter switch, directional couplers) (June 7th 2016) Tender 3: Support structure Tender 4: Circulators and loads Tender 5: Arc detectors Agreement on remaining CDR dates needed Continue weekly Skype, Morten to paricipate in last meeting every month

14 Risk Workshop actions Share prototype development contracts with partners (Yogi) Finalise cooling design for waveguides in stubs (Morten) Update SoW: 4-loop DCs; waveguide cooling stubs (Yogi) Finalise PSS interface (Yogi, Morten) Arrange Gallery review prior to CDR (John) Share project plan incl resources with ESS (Paul) Update P6 plan to align with UK plan (Yogi) CE marking – consider wording on safety and share w ESS (Rob)

15 Actions II Summarise the CHESS documents (Yogi, Paul)
Ask for longer access to CHESS for partners (Yogi) Send risk register to ESS (Paul) ESS and UK to agree on PQP, share with ESS June 24 (Paul) Delivery insurance documents to ESS for review (Rob) Agree on SAT scope and procedure (Yogi, Morten) Optimisation of tender packages (Yogi, Rob) Monthly reporting (Paul) Decision on HB installation tentatively before June 7 (Morten) Share target spend profile with ESS (Rob)

16 Actions III Plan for Stub mockup of HB stub and Spoke or DTL stub to test installation sequence, cooling, and cabling Plan CDR before submitting tender circulator/load/arc detectors. Can be remote (John) Plan CDR for the design of support structure to be held at ESS (John)

17 Thank you


Download ppt "RF systems introduction"

Similar presentations


Ads by Google