1 Drakenstein Municipality
Bulk Infrastructure Contribution Levy (BICL’s)

2 Background information
Pre Year 2000: Wellington Municipality had development contributions for Water & Sewer as part of their tariffs. Paarl Municipality negotiated with developers for upgrading of infrastructure. Post Year 2000: Paarl and Wellington amalgamated in late 2000 and adopted the contributions into it’s tariffs. The new Drakenstein Municipality applied the BICL’s for subdivisions, group housing, private residential flats and any development that may place an additional burden on the system. The services on which contributions were charged increased to: Water, Sewer, Stormwater, Roads, Electricity. The criteria for charging the BICL’s were: Market value of property = R (minimum fee/service). Market value of property = R (maximum fee/service). Pro rata levy is payable for units between R – R Market value of the property is defined as: Residential erven: Market value of the erf Flats/Group housing: Market value of the unit Year 2010 GAP Housing received 40% discount on there BICL’s payable. Year 2011 Drakenstein Municipality appointed Vela VKE to re –evaluate our policy inline with other municipalities

3 Current Policy(Subdivision)
Current vs New Current Policy(Subdivision) For the subdivision of a residential property of ±1020m² into portion A ( 315m²), portion B (270m²), portion C (225m²) and Remainder (208m²). Property value of the site is R Property value of the portion is R Tariff as per 2013/2014 financial year is R vat incl. per service. Cost per erf is R x 5(services) = R vat incl. Total BICL’s is calculated as R 8089 x 5(services) x 3 units= R vat incl.

4 Current Policy(Group Housing)
Current vs New Current Policy(Group Housing) For a new development from agricultural with 1 homestead (4.67ha) to 193 residential units (3.22ha). A GAP housing project which receives 40% discount on BICL’s. Property value of each portion is R BICL tariff as per 2013/2014 financial year is R vat incl. GAP discount is 40%. Cost per unit is R x 5 x 0.4 = R vat incl. BICL’s is calculated as (R 8089 x 5(services) x 40%) x 193 units = R vat incl

5 Current vs New Proposed New Policy
For the subdivision of a residential property of ±1020m² into portion A ( 315m²), portion B (270m²), portion C (225m²) and Remainder (208m²). Water Module Existing CALCULATION OF DEMAND CALCULATION OF CONTRIBUTION UserType Unit Number of Units in Development Land Area to be developed with proposed Land Use m2 GLA (m2) (where applicable) Average area per unit (m2) Unit Demand (kl/day) Total DEMAND (kl/day) Socio-Economic Factor Sustainability Factor Municipal Area Bulk Service Contribution Payable ( R) Single Residential stand area > 500m2(Med/ High Income) erf 1 1020 - 1.9 Paarl, Mbekwini, Wellington R TOTAL R

6 Current vs New Water Module New UserType Unit
CALCULATION OF DEMAND CALCULATION OF CONTRIBUTION UserType Unit Number of Units in Development Land Area to be developed with proposed Land Use m2 GLA (m2) (where applicable) Average area per unit (m2) Unit Demand (kl/day) Total DEMAND (kl/day) Socio-Economic Factor Sustainability Factor Municipal Area Bulk Service Contribution Payable ( R) Single Residential stand area < 500m2(Med/ High Income) erf 1 317 1.2 Paarl, Mbekwini, Wellington R 270 - 0.6 R Single Residential (Low Income) 225 R TOTAL 3.0 R

7 Current vs New Summary for subdivision for 3 additional units Service
Bulk Services Contribution New Land Use (R) Excl VAT Bulk Services Contribution Existing Land Use (R) Excl VAT Nett BSC PAYABLE (R) Excl VAT Current BICL'S No of units Water R R R 4 967 R 3 Sanitation R R R Storm water R 4 213 R 8 821 R 0 Roads R R 7 726 R 6 181 Solid Waste R 6 035 R 3 353 R 2 682 R 0.00 Electricity R R R TOTAL BULK SERVICE CONTRIBUTION PAYABLE R R

8 Current vs New For a new development from agricultural with 1 homestead (4.67ha) to 193 residential units (3.22ha). A GAP housing project which receives 40% discount on BICL’s. Sewer Module Existing CALCULATION OF DEMAND CALCULATION OF CONTRIBUTION User Type Unit Number of Units in Development Land Area to be developed with proposed Land Use m2 GLA (m2) (where applicable) Unit Discharge (kl/day) Total DISCHARGE (kl/day) Socio-Economic Factor Sustainability Factor Municipal Area Bulk Service Contribution Payable ( R) Agricultural small holdings ha 4.67 46700 0.8 3.7 1 Paarl, Mbekwini, Wellington R - TOTAL R

9 Current vs New Sewer Module New UserType Unit
CALCULATION OF DEMAND CALCULATION OF CONTRIBUTION UserType Unit Number of Units in Development Land Area to be developed with proposed Land Use m2 GLA (m2) (where applicable) Unit Discharge (kl/day) Total DISCHARGE (kl/day) Socio-Economic Factor Sustainability Factor Municipal Area Bulk Service Contribution Payable ( R) Single Residential (GAP Housing) erf 193 31000 0.5 96.5 0.6 1 Paarl, Mbekwini, Wellington R Road Reserves ha 1.45 14500 - 0.0 R Sports, Recreation & Parks 0.12 1200 1.0 0.1 R TOTAL 96.6 R

10 Current vs New Summary for new Group Housing Service
Bulk Services Contribution New Land Use (R) Excl VAT Bulk Services Contribution Existing Land Use (R) Excl VAT Nett BSC PAYABLE (R) Excl VAT Current BICL'S No of units Water R R R R 193 Sanitation R R R Storm water R R R Roads R R 7 726 R Solid Waste R R R R 0.00 Electricity R R R TOTAL BULK SERVICE CONTRIBUTION PAYABLE R R