Presentation is loading. Please wait.

Presentation is loading. Please wait.

Background issues for the Super-B background simulation team

Similar presentations


Presentation on theme: "Background issues for the Super-B background simulation team"— Presentation transcript:

1 Background issues for the Super-B background simulation team
G.Calderini (LPNHE, Paris) for the Super-B background simulation team 5th Super B Workshop Paris, May 9-11, 2007

2 Status of the background simulations
for the CDR The different background processes The approximations used The implementation Post-CDR effort Adding what is missing The tools For the Beamline For the Detector The interaction with the final focusing and detector design

3 General approach Collection of background generators
primaries Transport inside a Geant4 beamline description (magnetic fields and material) shielding Propagation in a Geant4 detector description hit collections Background impact determination in the subsystems

4 Other sources of background
The machine design presented in the CDR gives reasonable but still important backgrounds Luminosity sources - beam-beam - radiative Bhabha Linear with currents lost particles synchrotron radiation Other sources of background Touschek background Thermal outgassing due to HOM losses; Not an issue with these currents Injection background

5 Pair production Studied with Guinea Pig and Diag-36 generators
After some debugging, the two results are no more incompatible Very high production rate but particles have low energy and they loop in the solenoid field 30MHz/cm2 Pt accept. @ 1.5 T , 1.2 cm ~Angular acceptance 1.2 1.5 R(cm)

6 Due to this feature, it is a source of background
only relevant for the tracker Expected average rate O(15MHz/cm2) at R=1.2cm, decreasing to 5MHz at R=1.5cm (Guinea Pig) Not fully simulated with Geant for the CDR. Background analysis in the tracker is based on kinematical distributions A more detailed simulation will be mandatory as a next step for the post-CDR effort

7 Radiative Bhabhas Bremsstrahlung process in the forward direction in
BhaBha scattering: e+e- -> e+e- g Simulated with the BBBrem generator and fully propagated in the Geant-4 description The outgoing particles are not the direct responsible for detector backgrounds but they generate very dangerous showers and backscattered particles in the downstream beamline elements Beamline and shielding design is very important

8 Radiative BhaBhas At small radii, with the present simulation, it is negligible wrt to pairs. Rate O(100KHz) at 1.2cm Present also at higher radii, (as in BaBar) due to backscattering from downstream machine elements (must be cured with suitable shielding)

9 Radiative Bhabhas Need serious amount of shielding to prevent the produced shower from reaching the detector.

10 IFR EMC Given the importance of this source for most of the Super-B subdetectors, it will be necessary to integrate the studies with other generators BHLUMI/BHWIDE for larger angles Neutrons ???

11 Touschek The study prepared for the CDR was based on the Boscolo code (LNF). This contains an approximate description of the ring and transport the off-energy particles due to intra-bunch scattering. The primaries hitting the beampipe are passed to Geant-4 Expected loss particle rate in a +/- 4m from the IP = 2.3 MHz/bunch, reduced to 90kHz after collimators deployment. Further effort necessary at this point to optimize mechanical aperture of chambers, position of collimators and masks

12 Lost particles Mainly Coulomb/Bremsstrahlung interactions with residual gas molecules in the beampipe For the CDR effort, the estimate was based on PEP-II rates and rescaled for beam currents. Found to be negligible with respect to other sources (1-2 MHz/cm2 in Layer_0, decreasing with R). Probably a pessimistic extrapolation, given the absence of permanent dipoles very close to the IP in SuperB final focusing. Further effort necessary for a more quantitative description As soon as an updated final focus design will be available, we should try to implement a Turtle description or something equivalent

13 Synchrotron radiation
The interaction region has been designed to reduce the bending of incoming beam trajectories, but some photons can still hit the beampipe. With the present final focusing, the expected rate on the IR mask tip is about 800 g/BX for energies above 20KeV, reducing to a few g/BX on the Be pipe, a rate similar to BaBar. Preliminary design of adequate mask system already available. Update necessary to the next final focus design, and additional studies for the residual backgrounds in the detector.

14 Some words on tools In the present version of the work, the C++ code
describing both the beamline (B fields/material) and the detector was written by hand in Geant-4. This made the iterations rather slow every time there was a change in the accelerator optics or in the detector. In the future it will be necessary to develop or import tools to help with this, similarly to what we did with the PEP-II beamline in the BaBar background simulation

15 Interfaces for the beamline optics
Some software, like the BDSIM interface, used for ILC studies, allows to import MAD configurations into a Geant-4 description. That could help! Interfaces for the geometry/detector As in the case of BaBar (for which we developed an interface to SolidEdgeTM ) it’s possible to use CAD oriented extensions to Geant-4: GDML ? Better organization of the software Presently the code is under CVS but organized as a single package. Difficult for different people to work on different parts at the same time

16 Organization In the CDR phase, the integration between background
simulations and final focusing design was rather limited, as well as the interaction with some subdetector. This needs absolutely to be improved in the next phase. Background studies are not intended to determine simply if a certain detector is feasible, but should be used to optimize the machine and the detector design Hopefully this will be easier after the use of the above tools which should reduce the response time in the interaction

17 Manpower and timescale
Many Institutions have already expressed their interest to participate to Super-B background studies. Some preliminary (but not necessarily unique) layout was even already suggested in the context of the Eurocrab project proposal. We hope that this Super-B workshop will be a chance to discuss the involvement of the new people/Institutions and to define the fields of interest The timescale is shorter than what it could look like: after the summer the new final focusing might be ready and by then all the bells and whistles ideally should be fixed and tested with the present configuration!

18 Conclusions A change from a individual homemade standard to
A very big effort has been made on background simulations by a small group of people for the CDR publication. In my opinion, the work has been much more detailed and elaborate with respect to what expected for a CDR standard, but it is definitely small with respect to what is needed next. A change from a individual homemade standard to a mass-production standard is necessary in the organization of the work. It is the right time for all the interested people to come onboard


Download ppt "Background issues for the Super-B background simulation team"

Similar presentations


Ads by Google