Presentation is loading. Please wait.

Presentation is loading. Please wait.

Radiation To Electronics 2x A Brief Look

Similar presentations


Presentation on theme: "Radiation To Electronics 2x A Brief Look"— Presentation transcript:

1 Radiation To Electronics 2x1033 - A Brief Look
Very Quick M. Brugger on behalf of the R2E Project !!! Many Thanks To Everybody !!! (Specials to: Marco, Giovanni, Ketil!)

2 Questions SEE failures, status today?
Are higher peak luminosities more penalizing (for SEEs)? Efficiency of what has already been done ? What mitigation measures are planned within the R2E Project?

3 Very Preliminary! (many things were done during the last 24h!)

4 Risk of Low Statistics Appearance: Correlation: Likelihood: Impact:
Stochastic distribution of failures can lead to wrong conclusions. (e.g. collimation control racks being most critical for UJ14/16) Correlation: Radiation levels depend not only on luminosity (and intensity), also residual gas pressures can matter (e.g. some [more] events after the technical stop) Likelihood: Grouping of ‘events’ can occur within fluctuations (e.g. 3 or 4 SEE caused dumps in a row, then several fill no SEEs) Impact: Some failures lead to longer down-times (not because of the SEE nature, but due to the affected equipment) while failure xSection can be similar (e.g. Cryo PLC failures) Improvement: Mitigation measures are partly implemented in the shadow, focusing on most critical equipment (e.g. shielding & relocations)

5 Radiation Levels (we agree that SEE failures are caused by radiation?)

6 Measured & Expected Rad-Levels
2011 Operation up to Week 30 (2010 excluded): -> ~1,8 fb-1 (nominal: x30 for lumi scaling) Luminosity Dominant Intensity Dominant Luminosity Dominant Intensity Dominant Luminosity Dominant Intensity Dominant Luminosity Dominant Scaling might be non-linear for areas being dominated by direct losses (& distributions) and/or vacuum contributions!

7 Radiation Levels & Luminosity

8 Luminosity versus Time
Luminosity is main source of radiation in P1/5/8 Other Cases: Collimation (P7) Vacuum (All) Except… Very similar slope (so far)

9 Failures & Correlations
!!! Only Physics Fills !!! Shorter fills with higher luminosity -> ‘more’ likely to have SEEs ending the fill since some other failure modes depend rather on time? In terms of behavior with time the failures reflect the cumulative luminosity (see slide before)

10 SEE Failures Mini-Chamonix Status & Today

11 Observed SEE Failures (~1fb-1)
G. Spiezia LBOC (link) + Updates (not easy) Except QPS, only failures leading to dump? How to Scale to Nominal Operation? Luminosity: P1/5 (x50), P8: (x3-5) Energy: P1/5/7/8: (x1.5) Intensity: P7: Losses & Distribution (x ??? [10-50]) Beam-Gas: P1/5/7/8 + & Scrubbing (x ???) !!! STILL NOT AN EASY EXERCISE !!!

12 & Today !!! MANY EVENTS STILL TO BE DIGESTED !!! !!! All Fills !!!

13 & Tomorrow (Scaling) UJ14/16/56, RR13/17/53/57: US85: UJ76, RR73/77:
Failures scale with accumulated luminosity 2011: x2-3, 2012: x5-10 (theoretical with no actions!) (BUT: shielding + relocation) -> aim, not worse than now! US85: 2011: x2, 2012: x4? (BUT: some additional relocations) UJ76, RR73/77: Failures scale with collimation losses 2011: x2?, 2012: x5-10? (BUT: some additional relocations) BUT: TS and xMasBreak Actions improve situation (see later) Vacuum (25ns) & loss distribution to be kept in mind!

14 What’s to be done (prepared and partly already implemented)

15 Roadmap for 2011 Detailed radiation field analysis (Monitoring, TLDs, MD) Additional radiation tests (H4IRRAD, CNRAD) Provision/preparation of mitigation actions xMasBreak (shielding P1, some relocations, preparations) LS1 (shielding P1/5/8, relocations: P1/5/7/8) Development of RadTol Power Converters (also for patches!) TS & xMasBreak improvements Additional patch-solutions Evaluation of additional weak points (P4, REs) R2E Review in November

16 Mitigation Options What Can Be Done (in general) Solve & Gain Time
Improve & Gain Time RELOCATION SHIELDING Mitigation Options Solve & Remain Flexible No Major CE RAD-TOL DESIGN CIVIL ENGINEERING

17 Mitigation Strategy Immediate Relocation “Fast” & Global Improvement
1st Safety Critical Immediate Relocation 2nd Shielding “Fast” & Global Improvement Highest Impact on Operation: Relocation Shielding 3rd Most Sensitive Relocation Shielding New Design 4th Remaining

18 Performed R2E Mitigation Actions
Shielding: P6 (RA63/UA63 and RA67/UA67) (gain ~factor 5-10) UJ22/23/76/88/87 (gain ~factor 10) RR77/73 (gain ~factor 10) US85 Safe-Room (gain ~factor 10) Relocations: Fire-Control Racks UJ56/76, US85 (safe) RTU relocated from safe room in UJ56/76 (safe) Cryo-relocations/valve replacement in UX85 (safe) UPS from UJ76 (safe) Fire-Detectors: US85, other points prepared (safe) PLCs from US85 (safe) Replacements & Upgrades: QPS Firmware Upgrade (ISO150 failures) (transparent) US85 24V Power Supply -> replaced by old model (more robust)

19 xMasBreak - Shielding/Relocation
Point 8 US85: Cryogenics relocation (under study) US85: Relocation of 24VDC distribution All points Relocation/Shielding preparations Point 1 UJ14/16 shielding (gain factor 5-10) UJ/RRs: Fire detection relocation UJ14/16 Cabling Preparations Point 5 UJ56 Relocation Preparations UJ56 Civil engineering Phase I RRs Fire detection preparation

20 Equipment “Patches” QPS ISO150: Cryogenics control:
Firmware upgrade will be finished during xMasBreak Cryogenics control: Current lead temperature: hardware mod. (xMasBreak) Communication: reset possibility investigated Collimation control: Software update investigated Cryogenics PLCs: Redundant PLC system studied (to be tested in CNRAD) Cryogenics Power Supply: Old model (robust) in place, only part-time solution uFIP -> “brico-FIP”

21 LS1 Mitigation Actions Point 1 UJ14/16: relocation (+ some shielding?)
RR13/17: shielding Point 5 UJ56: relocation RR53/57: shielding Point 7 UJ76: Relocation RR73/77: tbd Point 8 US85: Relocation US85: Shielding Power-Converters: RRs P1/5/7 Radiation tolerant development Also important for patches

22 Conclusion SEE failures are a function of accumulated luminosity (and losses) [+vacuum!] Higher accumulated luminosity per fill makes a dump due to SEE more ‘likely’ to appear (coupled with origin of ‘failures’ other than SEEs) Number of SEE failures within R2E predictions but they will continue to appear until in 2011/2012! A clear R2E Mitigation plan is available xMasBreak actions will improve the situation LS1 is required for large scale Optimization is constantly applied (Input/Information is crucial)

23 Backup

24 Measured & Expected Rad-Levels
Weekly Report Detailed Analysis Comparison & Extrapolation x50 Link1 & Link2

25 Measured & Expected Rad-Levels
2011 Operation up to Week 25 (2010 excluded): -> 1fb-1 (nominal: x50 for lumi scaling) OLD ESTIMATE Luminosity Dominant Intensity Dominant Luminosity Dominant Intensity Dominant Luminosity Dominant Intensity Dominant Luminosity Dominant Scaling might be non-linear for areas being dominated by direct losses (& distributions)

26 Equipment Failures Sources of Information eLogBook 8:30h meetings
RadWG list (see link) Cryogenics List (see link) QPS analysis/list (see intermediate summary) TE/EPC List (updated log) s and discussions Your observations/input ! !!! NOT AN EASY EXERCISE !!!

27 Equipment Failures ??? Definition of Failure linked to SEE ???
One or several (ideally all) of the following conditions: Failure occurs during beam-on/ collisions/losses (source of radiation) Failure is not reproducible in the lab Failure signature was already observed during radiation tests (CNRAD and others) Failure frequency increases with higher radiation (hopefully we don’t get there)

28 Limitations in Analysis
Limitation-1: SEEs which are not SEEs? Limitation-2: Hidden failures ! (not related to SEEs, caused by 3rd party equipment with indirect impact, e.g. Ethernet Switches)? Limitation-3: High probability to miss those not causing a dump!

29 Power-Converters & Tolerance
Parts have been tested at CNRAD Expected sensitivity ~1x10-8 (= one failure every ~1x108cm2 per converter) LHC Observations so far four failures confirmed as SEE (sensitive module: AC/DC part) + few cases of 2nd failure ‘signature’ New Test-Area H4IRRAD: LHC-like conditions (spectra) About 1 year of nominal LHC within one week of test Final results after the summer! What will we learn: confirm LHC observations verify weak links and investigate patch-solutions (important for 2012 and 2014/15/16 operation) optimize global mitigation strategy North Area: Jura Side SPS Beam Saleve Side Power-Converter’s are the Key Point for the final R2E Mitigation Strategy

30 What it Means in Reality
TEST THIS: AND AFTER … BEFORE … HERE (W)HOW ??? DANGEROUS LIQUID:

31 Equipment Failures Low (weekly) statistics, but correlation visible

32 IR7 Performed Mitigation Actions
Shielding installed: [ECRs: and ] RR73/77 (we gained ~factor 10 in radiation levels) UJ76 (we gained ~factor 10 for safe-room, 3-4 for the 1st floor) Relocation of UPS from UJ76 (safe) [ECR: ] (safety critical at that time!) Relocation of fire control racks (safe) (possible impact on safety not excluded): UJ76 -> TZ76 [ECR ] Relocation of EN/EL control equipment (safe) RTU relocated from safe room in UJ76 -> TZ76 Relocation of fire detectors (possible impact on safety redundancy): Prepared for UJ76 and RR73/77 (see ECR ) Rack installation & cabling preparations: UJ76 -> TZ76

33 Mitigation Actions Already Done
Shielding installed: Ducts in P6 (RA63/UA63 and RA67/UA67) (gain ~factor 5-10) UJ22/23 and UJ88/87 (gain ~factor 10) US85 Safe-Room (gain ~factor 10) [ECR: ] Cryo-relocations/valve replacement in UX85 (safe) Relocation of fire control racks (possible impact on safety): US85, UJ56 [ECR: ] (safe) Relocation of fire detectors (possible impact on safety): US85 (other points prepared) [ECR: ] (safe) Relocation of EN/EL control equipment RTU safe room UJ56 (safe) Cabling preparations: P1, P7, P8

34 Possible SEE Failures Observed in 2010
CONFIRMED or very LIKELY WIC crate failure in TI8 Observed in 2009 Known problem with moderate x-section CRYO tunnel card SEE in 8L2 1 Fault in uFip (as observed in CNRAD 2010) SEE confirmed QPS Tunnel Card Failures (2x in 9L7 [ions], 2x in 8R8 [inj.], + others) ISO150 -> permanent PM trigger SEE confirmed (EMC has same effect) TE/EPC power supply burnout in UA87 Same effect observed in CNRAD SEE is very likely the cause (Streaming through Maze) QPS tunnel Card Failures in 9R7 & 9L7 uFip communication lost (2x) SEE confirmed (seen in CNRAD) NOT CONFIRMED (unlikely) VAC power supply burn out In UA23 between maze and duct (TDI losses + TCDI losses ) SEE rather unlikely PXI power supply burnout in UJ16 To be confirmed by producer (comparison with CNRAD burnouts) SEE unlikely (early 2010 operation)

35 Failures 2011 [Mitigation]
Collimation Control (3x, confirmed) [Soft + Relocation] Cryogenics UJ14/16/56/76 (several confirmed) [Relocation] Biometry UJ14/16 (2x, likely) [Operation + Rel.?] US85 PLCs (Cryo, 3x, confirmed) [Relocation] Power Converters (4x, TE/EPC) [New Develop.] UPS UJ56/US85?(unlikely, but possible) [Relocation] QPS Control UJ14/16 (few, corrector circuits) [Relocation] QPS ISO-150 (many, tunnel & shielded areas) [Soft + New Develop.] uFIP as used in QPS/Cryo (few times, tunnel + shielded areas) [Soft + New Develop.] Limitation-1: SEEs which are not SEEs? Limitation-2: hidden failures (not related to SEEs, caused by 3rd party equipment with indirect impact, e.g. Ethernet Switches)?

36 Power Converter Failures
© TE/EPC

37 LHC POWER CONVERTERs © V. Montabonnet, Y. Thurel
Minimize the number of converter types: Only the LHC60A-08V was specified for a radioactive environment ! 3 other converter types are part now of the radioactive sensitive areas! LHC120A-10V 4-Quadrant 300 Units LHC600A-10V 4-Quadrant 400 Units LHC4..6kA-08V 1-Quadrant 200 Units LHC60A-08V 4-Quadrant 752 Units Units : Quantity in all machine (UA, RR, UJ, tunnel)

38 IR7 Critical Areas & Equipment
Equipment Inventory (EDMS # ) Equipment UJ76 Fire/ODH control & detectors Cryogenics Instrumentation (Profibus) AUG control Vacuum UPS Beam Television Monitor Electrical Distribution & Control Ramses Remote-Reset & Timing GSM Diagnostics Access System Control Beam Loss Monitors Power Converter Beam Position Monitors (temporary) Ethernet Optical Fiber Cooling and Ventilation WorldFip Equipment RR73/77 Fire/ODH detectors Beam Position Monitors Power Converter Cryogenics Instrumentation (FIP) QPS WorldFip Cooling and Ventilation Current Lead Heaters Power Interlock Electrical Distribution Various critical equipments Several tested at CNGS and shown high radiation sensitivity Few cases allow for ‘patch’ solutions Less radiation critical equipment Fire/ODH detectos to be relocated Current Lead Heaters ok for the levels QPS known patch solution Power Converters – Big Unknown Global Solution Required

39 IR7 Radiation: Today? Combined Loss Analysis (BLMs & Injected/Dumped Intensities): IR3 lost in 2011: ~6E13 protons (per beam) IR7 lost in 2011: ~2E14 protons (per beam) We’re a factor of ~50x below nominal (~1x1016p/b/y) Can nominal operation lead to ‘relatively’ higher losses? © A. Nordt, A. Thornton Latest Weekly Report ( RR73/77: ~2-3x106cm-2 UJ76: ~1x106cm-2 Scaling: x75 (Energy!) Nominal Year: RR73/77: ~2x108cm-2 UJ76: ~8x107cm-2

40 Collimation Review Performed mitigation options very efficient
2011/12 Operation UJ76 relocation Power-converter tests & R&D for RadTol Dev. Betatron collimation in IR3 very efficient not limited by IR7 next step (safety) high-importance to judge for RRs Would provide additional flexibility

41 RRs: Power-Converter R&D
TE-EPC Planning for Rad Tolerant Converter Project © Y. Thurel Link: R2E Power Converter R&D

42 RRs Additional/Alternative Options
Betatron Collimation in IR3 No significant SEE impact for IR3 Low radiation levels in IR7 Additional flexibility Standard collimators to be added R&D for Superconducting Links © R. Assmann et al. © A. Ballarino et al.

43 IR7 FLUKA Application Benchmark
© K. Roeed Loss-Term (SixTrack [R. Assmann et al.]) TCP TCAP MBW TCS MQW TCLA Assumptions FLUKA Calculations Normalisation >500m 2010 Operation Summary (Protons) In 6.02E+15 Dumped 5.82E+15 96.70% Lost in Machine 1.99E+14 3.30% Of Lost protons Collisions 2.33E+13 11.73% Elsewhere 1.76E+14 88.27% RR73 RR77 UJ76 LM01 LM02 LM03 RM03 RM04 RM05 RM06 RadMon Dcum Rth SEU (3V) Measured Beam contribution SEU (FLUKA) Expected Error [%] Stat. only Exp./Mes. 6L7.7LM03S 19846 5 14401 B1 15015 3 1.04 5L7.7LM02S 19904 5253 9765 1.86 4L7.7LM01S 19991 2689 B1+B2 3116 6 1.16 4R7.7RM03S 20045 950 401 0.42 5R7.7RM04S 20133 18727 B2 13032 4 0.70 6R7.7RM05S 20208 31 303 962 8 3.17 RR77.7RM06S 20241 1 13 17 22 1.33 BLM ratio IR7 / IR3 Ratio % Loss in IR7 TCSG.A6L7.B1 / TCSG.5L3.B1 3.1 76 TCSG.A6R7.B2 / TCSG.5R3.B2 5.6 85

44 Tracking/BeamGas/etc. Operation Assumptions
Radiation Levels 2010 Source terms, operational conditions as well as monitor readings have to be carefully evaluated Tracking/BeamGas/etc. FLUKA Predictions Operation Assumptions Rad-Level Estimate Monitor Readings Calibration Assumptions Final Values Threshold of monitors is ~106! (lower values only by ‘trick’ [big uncertainties!]) VERY GOOD AGREEMENT (given the underlying uncertainties)

45 2010/2011/2012 Radiation Levels !!! Amazing !!! Close to ‘Threshold’
2011/2012/Nominal/+++ ??? !!! Amazing !!! Close to ‘Threshold’ Critical Dramatic?

46 IP8/TI8 Radiation Detectors
© V. Boccone 5RM07S PMIL8812 Current location not known in full detail of the Radmon and RAMSES positions PMIL8811 5RM05S Large Gradient: 4-5 orders of magnitude PATL8711 5RM06S 5RM08S

47 TED Loss: RadMon Downstream
© V. Boccone

48 UJ87: Loss on TCDIH.87904 © V. Boccone

49 Point-8 Application Benchmark
© M. Calviani FLUKA/RAMSES benchmark Detector Measured dose Ratio (meas/simu) PMI8501 (UX85) 24.0 1.1 PMI8511 (UX85) 120.0 0.8 PAT8511 (US85) 36.7 0.6 US85 UX85 UW85 FLUKA Simulations provide high energy hadron fluence, dose and 1 MeV Si equivalent in the LHCb cavern according to the Phase-2 shielding implementation proposed in the R2E Project FLUKA/RadMon benchmark Detector Ratio (FLUKA exp/measure) 8LE10S 1.6 8LE07S 2.0 8LE04S 8LE08S 2.2 Very good agreement with PMIs and PATs RAMSES detectors RadMons set at 3V more difficult (at low count rates) Significant uncertainties to be considered (thermal neutron contribution, detector geometry, etc…) Uncertainty at least a factor of 2


Download ppt "Radiation To Electronics 2x A Brief Look"

Similar presentations


Ads by Google