1 NGWA 2004 Microbial GWQ Interest Group
Introduced Coliform Bacteria during Pump Replacement and Well Service: Diagnosis Prevention and Decontamination 2/22/2019 EGIS, Well Video & Geophysical Services:

2 EGIS, Well Video & Geophysical Services: 919-929-8363
By Michael L. Vaught EGIS 441 Northside Dr Chapel Hill, NC 27516 or 2/22/2019 EGIS, Well Video & Geophysical Services:

3 Two Wells that Became Coliform Positive after Pump Service
Calvary Baptist Daycare Piedmont granitic rock aquifer Salisbury, NC Orchard at Altapass Blue ridge gneiss rock aquifer Altapass, NC (Blue Ridge Parkway) 2/22/2019 EGIS, Well Video & Geophysical Services:

4 EGIS, Well Video & Geophysical Services: 919-929-8363
History of Clean Tests Calvary Baptist Daycare Owners memory Drilled in 1987 Daycare started in 1996 Tested clean until pump pulled Public Water records NCDENR Public Water Supply since 1996 Coliform positive = pump service in August, 20003 2/22/2019 EGIS, Well Video & Geophysical Services:

5 EGIS, Well Video & Geophysical Services: 919-929-8363
History of Clean Tests Orchard at Altapass Owner/ operators memory Drilled in 1976 Tested clean until pump pulled Coliform positive = pump service in October, 20003 Public Water records Available since Feb 2004 Owners records 2/22/2019 EGIS, Well Video & Geophysical Services:

6 Fractured Rock Aquifers
Partially Cased Open Rock Wells Unconfined Water Table Topography and elevation head Tectonic (Dikes, Faults, Emplacements) Borehole Stability Shallow Fractures = Less Filtration Time? Grout Seal Casing/Conduit 2/22/2019 EGIS, Well Video & Geophysical Services:

7 Downhole Video & Pumping
Observe All Three Stages Static rest. Pumping stress. Recharge. Characterize well. Construction (leaky casing?) Borehole stability (geology) Biofouling Water zones 2/22/2019 EGIS, Well Video & Geophysical Services:

8

9

10

11

12

13 Salisbury Field Project– Well Data
Calvary Baptist Daycare 21’ of 6.25” galvanized casing- tight 16’ to 170’ Slight biofouling No shallow exposed water zones 87’ slowly recharging water level 170’ downward walls clean 340’four inch standard submersible pump 415’ significant water producing fracture 455’ drillers well tag “Bottom of the Well”. (well yield 17 gpm) 2/22/2019 EGIS, Well Video & Geophysical Services:

14 Altapass Field Project– Well Data
Orchard at Altapass 30’ Water level. Walls are clean. 55.5’ Bottom of the 6.25’galv csg. – tight. 74’ Weathered fracture yielding 2 gpm 155’ Major water bearing rock fracture zone 273’ four inch standard submersible pump 304’ “Bottom of the Well” from video. (well yield about 10 gpm) 2/22/2019 EGIS, Well Video & Geophysical Services:

15 1st Failed attempt to disinfect
Salisbury First ever Pump replacement in August 8/14/03 coliform present in regular test Well Super chlorinated and recirculated 2/22/2019 EGIS, Well Video & Geophysical Services:

16 2nd Failed attempt to disinfect
Salisbury 8/27/04 coliform present in repeat tests Well Super chlorinated and recirculated 2/22/2019 EGIS, Well Video & Geophysical Services:

17 3rd Failed attempt to disinfect
Salisbury 10/06/04 coliform present in repeat tests Well Super chlorinated and recirculated 11/13/04 coliform present in repeat tests 2/22/2019 EGIS, Well Video & Geophysical Services:

18

19 Source of Introduced Coliform
Diagnosis by Downhole Video Survey Construction (Ridgewood – Leaky Csg?). Shallow water. Space below the pump. Grass and debris in the well Pump service work Salisbury is playground with wood chips Altapass surrounded by apple orchard (Oct.) 2/22/2019 EGIS, Well Video & Geophysical Services:

20

21 Eliminating Introduced Coliform
Salisbury well Extend pump to within four feet of the bottom Draw the well down and back flush; cycles Raise pH to 11 and recirculate overnight Draw the well down and back flush Create a 200 ppm chlorine solution in the well Maintain pH of 6 with the chlorine at 200 ppm Recirculate solution at least 4 hours Apply positive head by back flushing End of second day restore service, chlorinated water 2/22/2019 EGIS, Well Video & Geophysical Services:

22 Eliminating Introduced Coliform
Altapass well Extend pump to within four feet of the bottom Draw the well down and recirculate Pulled the pump assembly onto wooden deck Add chlorine tablets and gravel Reinstall pump with sleeve to the bottom Create a 200 ppm chlorine solution in the well Maintain pH of 6 with the chlorine at 200 ppm Recirculate solution overnight Cyclic Draw down and recirculation End of second day restore service, chlorinated water 2/22/2019 EGIS, Well Video & Geophysical Services:

23 EGIS, Well Video & Geophysical Services: 919-929-8363
Prevention Pump service work Ground cover or reel system Clean & disinfect drop-pipe and wire Replace twisted wire Remove and replace tape Rubber gloves Work clean “… Prevention is Worth a Pound of Cure” 2/22/2019 EGIS, Well Video & Geophysical Services:

24

25

26 EGIS, Well Video & Geophysical Services: 919-929-8363
Summary Avoid repeat chlorinations Verify Well construction and condition Flow sleeve for pumps. Disinfection depends on distribution. Efficient chlorination (pH & ppm) Wells remain clean 2/22/2019 EGIS, Well Video & Geophysical Services:

27 EGIS, Well Video & Geophysical Services: 919-929-8363
References Mansuy, N. (1999) Water Well Rehabilitation: a practical guide to understanding well problems and solutions, Lewis Publishers Smith, S. A., Borch, M. A., and Noble, L. N. (1993) Evaluation and Restoration of Water Supply Wells, AWWA Research Foundation Schnieders, J.H. (1999) Chemicals Used In Water Well Rehabilitation, U.S. Filter, Johnson Screens 2/22/2019 EGIS, Well Video & Geophysical Services: