1 Small Scale Projects – Learning from the CDM Paul Soffe

2 Small-scale Facility Concept
A dedicated facility providing buyers with CERs from small-scale projects Facility participants structure their requirements, specifying: Project type / Countries / Fixed price Current buy orders from Government of Austria and Japan Carbon Finance EcoSecurities sources all projects Direct sourcing + global network eg. E+Co joint venture (2E Carbon Access) EcoSecurities prepares all project documentation PDD, M&V plan etc. Arranges validation with a DOE Coordinates and oversees monitoring, verification and issuance All project developer costs are covered by the facility PDD, Validation, Registration Only cost to developer is verification and annual Share of Proceeds after CERs are produced Track-record – Small-scale Facility has registered 5 projects under CDM. One has issued CERs. Sunday, February 17, 2019

3 Buyer – Govt of Austria and JCF
Facility Structure Project #1 Master ERPA Buyer – Govt of Austria and JCF EcoSecurities Project #2 Project #3 Project #4 Individual ERPAs Project #5 Sunday, February 17, 2019

4 Key issues for SSc Project Success under carbon mechanisms
Minimise costs – all costs related with CDM project development, including third party costs for validation and registration have to be minimised Simplicity - all documentation standardized Speed – entire process process cannot be too long, SSc developers have limited budgets (time and cost) Expertise – SSc need access to assistance with process Financial value-added – prices for ERUs (CERs) for smallest project may need to be higher Track-record – Demonstrating that JI SSc can work with the rapid approval and development of the first projects is very important Sunday, February 17, 2019

5 Advantages for Buyers Small-scale projects with high sustainable development benefits; High-quality projects that have received business development services, thorough due diligence and assistance reaching financial closure – more likely to reach CER delivery targets; Projects that have advanced through the CDM Development Process – PDD completed, validated, or registered; Low transaction costs and high efficiency; and Optimum equilibrium between high quality project assessment and low transaction costs. Track-record: Small-scale Facility has registered 5 projects and 2 pending. One has received CERs. Sunday, February 17, 2019

6 Case Study: La Esperanza Hydroelectric Project
Location: Western Honduras Project type: Hydroelectric Installed Capacity: MW CO2e per year: 37,031 tons CER buyer: World Bank Current Status: Issued CERs Lessons learned: Partnerships Engage with DNA early in the process Additionality: include early Start Early Sunday, February 17, 2019

7 Case Study: Pig projects in the Philippines
Case Study: Small-scale pig projects Location: Philippines Project type: Anaerobic Digestion Installed Capacity: kW each CO2e per year: 1,500 to 10,000 tons CER buyer: Austria, JCF, and EcoSecurities Current Status: Final validation Lessons learned: Difficult to keep transaction costs low Economies of scale possible over time Methodologies + data availability Validation costs high Sunday, February 17, 2019

8 Case Study: Hydro in Honduras
Case Study: Cuyamapa Hydroelectric Project Location: Western Honduras Project type: Hydroelectric Installed Capacity: MW CO2e per year: ,552 tons CER buyer: EcoSecurities through Austrian Facility Current Status: st Registered Unilateral Project Lessons learned: Engage with DNA early in the process Unilateral Project Sunday, February 17, 2019

9 Lessons Learned Bundles of SSc projects an attractive option for buyers to secure a number of projects Under CDM rules it was possible to develop a large pipeline of projects for the Facilities Uncertain what problems may be encountered during moniotirng, certification, and issuance stages Other problems unrelated to CDM Executive Board price expectations and forecast for CERs host country approval can take a long time Sunday, February 17, 2019

10 Conclusions Make system for SSc projects as simple as possible to reduce transaction costs associated with carbon related aspects of project development Any charges for by JISC must be kept low Specify as much of JI cycle in detail ASAP. Clarity is important in building confidence that JI is workable Do not re-invent the wheel Utilise CDM baseline meths & additionality tools of SSc Are any specific meths needed for JI SSc in addition to CDM meths (I do not know). If so develop them – SSc developers will not and cannot (they are by default relatively poor) Sunday, February 17, 2019