1 Heelan Construction Project
Tom Kleen Tom Kleen

2 Project Overview New classroom wing on Heelan Hall
Add 6,000 sq. ft. of classroom space. This Photo by Unknown Author is licensed under CC BY-SA-NC

3 Timeline July 2011 August 2011 January 2012 August 2012
Demolish Heelan auditorium August 2011 Exterior structure January 2012 Finish classrooms August 2012 Move in

4 Timeline August 2012 January 2012 August 2011 July 2011 Move in
Demolish Heelan auditorium August 2011 Exterior structure January 2012 Finish classrooms August 2012 Move in

5 Demolish Heelan Auditorium
Budget Table Demolish Heelan Auditorium Exterior Structure Finish Classrooms 1 4 3

6 Budget Chart