Presentation is loading. Please wait.

Presentation is loading. Please wait.

Agreements & Cost Estimates

Similar presentations


Presentation on theme: "Agreements & Cost Estimates"— Presentation transcript:

1 Agreements & Cost Estimates
Gail Lee, P.E. Highway Utility Engineer INDOT June 14, 2017

2 Learning Objectives Reimbursement Agreements Cost Estimates
Grounds for Reimbursement & the Appropriate Agreements Partial Reimbursement Agreements Filling out an Agreement Reviewing an Agreement Extraordinary Cost Agreement Cost Estimates Parametric Estimates Developing Estimates Detailed Estimates Invoices & Invoicing Reviewing an Invoice Itemized Cumulative Invoice Sample Invoice References

3 Legal Basis for Reimbursement
The Legal basis for reimbursement derives from the Code of Federal Regulations 23 CFR 645 and Indiana Code I C

4 Reasons for Utilities to Be Reimbursed
1. The Utility has a property interest 2. Extraordinary Cost – sometimes referred to as hardship 3. Unnecessary which includes second time 4. Interstate 5. Some customer service lines

5 1. Property Interest Utility has a title to the property
Utility has a recorded easement Utility can provide the legal documentation that it has obtained an easement by adverse possession, other wise known as a prescriptive easement, by demonstrating that the easement has been in continuous use for at least 20 years. Best Proved by Quiet Title action in court A municipal utility exists on municipally owned property

6 2. Extraordinary Cost For INDOT projects IC states that the department may negotiate an agreement with a utility to reimburse the utility for extraordinary costs of facilities relocation caused by a highway or bridge construction or improvement project or a combination of highway or bridge construction or improvement projects. The utility’s cost to relocate exceeds 10% of the utility’s Gross Annual Revenue The utility’s cost to relocate exceeds 50 % of the INDOT project estimate cost – think about re-scoping

7 3. Unnecessary Relocations
The relocation did not take the utility out of conflict with the project The utility remains in conflict with the final project The utility would be out of conflict with the final project, but the project is not constructible in the relocated position The utility did not need to relocate A change of design or construction method took the utility’s original location out of conflict The project was not constructed within two years after the utility completed its relocation.

8 4. Interstate Highways Utilities are reimbursable for facility relocations on the interstate system except for the relocation of facilities installed on the interstate system after June 30, 1991 Utility facilities within the interstate system that were placed solely to cross the interstate system are reimbursable even if they were installed after June 30, 1991

9 5. Customer Service Lines – Who Relocates?
The utility is responsible for relocating its customer service lines IC states: “If a highway or bridge construction or improvement project requires the relocation of customer service facilities, the utility providing service to the customer is responsible for arranging the relocation of the utility’s customer service facilities required to be relocated.”

10 Customer Service Lines in New ROW – Who Pays?
If INDOT acquires new right of way that includes customer service lines: IC states: “If a highway or bridge construction or improvement project requires the acquisition of additional right of way and the relocation of customer service facilities that existed within the newly acquired right of way, the department is responsible for the cost of relocating those customer service lines.”

11 Customer Service lines in Existing ROW – Who Pays?
IC states: “If the utility does not own the customer service facilities, the department is responsible for the cost of the relocation of those facilities. “If the utility owns the customer service facilities, the cost of the relocation is the responsibility of the utility or the customer as determined by the operating rules of the utility or by a contract between the utility and the customer.”

12 Reimbursement & Agreements

13 Reimbursable Positions
Reimbursable Positions should be determined by Stage 1 A summary page should be drafted Include all utilities seeking reimbursement Grounds for reimbursement Further explanation of their situation Submitted to Project Manager & State Director of Utilities at Stage 1 Clarifies who has a qualified interest early in the project Any disputes can be cleared well in advance of letting

14 Partial Reimbursement
A utility may be partially reimbursable for a project Different options to split the cost Percentage of overall cost Precise breakdown Should be noted in the agreement Percentage is most appropriate for relatively uniform facilities Example: 700 LF of a 1000 LF line is in a private easement 70% reimbursable from the total cost of the relocation Includes overhead, equipment, etc. Precise Method works best for non-uniform facilities Example: Same as above except the last 500 LF is a larger pipe The first 700 LF are 100% reimbursable The last 300 LF are excluded The overhead, equipment, etc., can be split 70%-30%

15 Partial Reimbursement
Precise method works best for non-uniform facilities Example: Same as above except the last 500 LF is a larger pipe The first 700 LF are 100% reimbursable, less betterment The last 300 LF are excluded The overhead, equipment, etc. can be split 70%-30%

16 Types of Agreements INDOT employees can access all current agreements from the UTA Consultants may request a copy of the correct agreement from their Oversight Agent or request access to the UTA Work may be by Utility or by INDOT General Agreements Preliminary Engineering Standard Extraordinary Cost Unnecessary Cost Addenda to Agreements LPA Utility Agreements Utility-Specific Agreements

17 Example Agreement – Prep

18 Example Agreement – Prep

19 Agreements – Exhibits Agreements generally have two exhibits:
Exhibit A – Signed & Approved Work plan Prioritize reimbursable utilities when planning coordination Exhibit B – Itemized Cost Estimate All pages should be numbered, i.e. Exhibit A – 1 of 4 Very large reimbursements could impact our ability to fund a project!

20 Example Agreement – Review
Be sure these sections have the appropriate responses circled.

21 Example Agreement - Review

22 Example Agreement - Review

23 Extraordinary Cost Agreements
EC Agreements require additional approval before proceeding with development Extraordinary Cost Request Internal Memo prepared by Oversight Agent Exhibit A – Copy of the SPMS Schedule Exhibit B – Letter from utility requesting hardship Exhibit C – Revenues from the previous calendar year Exhibit D – Itemized Cost Estimate Exhibit E – Work plan Generally, include the work in the contract

24 Extraordinary Cost Agreements
Cost Split Utility is responsible for at least 10% of its gross annual revenue PE & CE costs may be deducted from its share INDOT is responsible for the remainder of the estimated cost

25 Example Agreement – Ex. Cost

26 Reimbursement & Agreements
There must be a clear conflict between the INDOT Project and the utility’s facilities Betterment of utility facilities is not reimbursable Original signed hardcopy must be sent to CO for approval & execution Ensure the address on the front page is the Utility's remit to address Ensure all exhibits are correctly labeled and numbered Flag the signature pages before sending to CO Affix a Memo & Routing Slip to the front of the packet LPA stands in for the State Transportation Department (STD) in regards to all FHWA Requirements

27 Cost Estimates

28 Cost Estimates Parametric Estimate
Used to populate a basic amount of money when a project is initially developed Does not take any site/utility conditions into consideration The project manager can decline these recommendations Non-Interstate Interstate Rural 5% 10% Urban 15% Example: State Road 256 in Austin Estimated Project Cost: $315,000 Utility Estimate: $31,500

29 Cost Estimates Ballpark Estimate:
Submitted by the utility with its initial notice response Educated Guess Specific to the project Based on initial anticipated accommodation Can be as simple as a cost per foot x length Refined as the project develops As more is known about the relocations Develops towards a detailed estimate

30 Cost Estimates Detailed Estimate: Submitted by Reimbursable Utilities
May be refined multiple times Preferably formatted similarly to an invoice Contingencies are not accepted by FHWA Labor Surcharge Materials Salvage Transportation Equipment Overhead Preliminary Engineering Construction Engineering Inspections Legal Fees Betterment

31 Cost Estimates Credits: Salvage
Materials that can be returned to stock at current market value Proceeds from sale of materials can be credited to the project Betterment Definition: Wholly at the election and for the benefit of the utility Methods of calculation: Determined to be a percentage of the total cost Precise itemization Exceptions: Required by the project Equivalent standards Next highest grade/size for obsolete materials Required by government law or regulatory commission code Current utility design practices & there is a direct benefit to the highway project

32 Cost Estimates Non-Participating Items:
The following items are not reimbursable with federal money External Relations Marketing Lobbying Research Programs Returns on Investments AFUDC (Allowance for Funds Used During Construction) Interest Financing Costs Float (Considered to be interest) Capital Stock Tax Contingencies In the event of conflicting policies, we follow FHWA guidelines

33 Cost Estimates – Sample

34 Invoices & Invoicing

35 Reviewing an Invoice A good invoice should include three components
The Bill Single Page Letter Utility Name Remit to Address Invoice Number Date of Invoice Start & End Dates Project & Permit Information Purchase Order Number Utility Representative Contact Information Summary of Charges The Ledger Cost Item ID Cost Item Category Date cost was incurred Name of Contractor Type of goods or services Rate for each unit of goods or services Number of units of the goods or services Total Cost of the goods or services The Supporting Documentation Work Logs Contractor Invoices Receipts

36 Itemized Cumulative Invoice
The Final Bill Summary listing of the charges for the entire project Should use the same categories as the ledgers Include a total amount due Can be compared directly to estimate Facilitate an explanation of cost overruns Must be submitted within 90 days of utility work complete per the agreement

37 Example Invoice

38 Example Ledger

39 References For More Information IC 8-23-2-6 FHWA 23 CFR 645, Subpart A
FHWA 23 CFR 645, Subpart A Commentary Appendix A – Legal Code INDOT Utility Coordination Website Indiana Design Manual: Chapter 104

40 Questions?


Download ppt "Agreements & Cost Estimates"

Similar presentations


Ads by Google