NERC LTRA Workshop August 16, 2007

Similar presentations


Presentation on theme: "NERC LTRA Workshop August 16, 2007"— Presentation transcript:

1 NERC LTRA Workshop August 16, 2007
Paul McGlynn Manager, Transmission Planning Department

2 Regional Transmission Expansion Planning Process
Ongoing and cyclical 15 year planning horizon Comprehensive and Holistic Collaborative

3 Regional Planning Process - Reliability
Apply sensitivity analyses to reliability criteria 5 year 10 year 15 year Include all required upgrades at all voltage levels in RTEP kV new construction included in RTEP Identify kV new construction requirements and continue to re-evaluate each year kV upgrades included in RTEP Pursue Right-of-way acquisition for kV projects

4 Uncertainty – What are the drivers?
Load Growth Local Historical Weather and Load Data Local Econometric Forecasts Generation Received over 1000 interconnection requests since 1997 Received requests to interconnect over 200,000 MW since 1997 “S” Queue - closed on 7/31/07 124 projects Approximately 18,000 MW generation Deactivations Merchant Transmission Interconnection

5 Current Transmission Expansion Drivers
Generation Retirements and Exports to NYC

6 500 kV Overloads

7 Allegheny Mountain Corridor
Build a new 765 kV transmission line from the John Amos substation to Bedington substation and extend a twin circuit 500 kV line to a new substation in Kemptown near the Doubs-Brighton and Brighton-Conastone 500 kV lines. 15 year analysis shows that this alternative has the greatest impact on the overloads shown on the previous page. Expected in service: 6/1/12 Approximate cost: $ 1.8 Billion Note: This map does not represent the actual transmission routes. Bedington

8 500 kV Backbone Overload Reduction

9 Generation Sensitivities

10 Backbone Overload Sensitivity

11 Alternative Backbone Solutions Under Consideration

12 How do you manage the uncertainty?
Incent development where you need it PJM Reliability Pricing Model Location specific Includes multiple resources Generation Merchant Transmission Demand Response Resources Situational Awareness – In the planning horizon Sensitivity Analysis – What if scenarios? Communicate with stakeholders