1 Efficiency and Excellence through Innovation
A1 Leeming to Barton Efficiency and Excellence through Innovation

2 COLLABORATIVE CULTURE
Key behaviours were identified and agreed between Aggregate Industries and Carillion/Morgan Sindall during mobilisation Successful A1L2B Project Solution Focused “One L2B Delivery Team” “Can Do, Will Do” Relationships Safety First Transparency & Trust Performance Driven Customer Focused *

3 INNOVATIVE VALUE ENGINEERING
Pavement Overview Original Scope : Permanent Works Asphalt 594,000t Temporary Works Asphalt 52,000t Total Asphalt Volume 646,000t Final Scope (after Value Engineering) Permanent Works Asphalt 459,000t Permanent Works CBGM 112,000t Total Asphalt Volume 511,000t SAVINGS IN EXCESS OF £3.5m *

4 COLLABORATION & INNOVATION AT WORK
Safety 2.75M Safe Hours Worked Zero LTI’s Quality 99.9% Right First Time – Material & Workmanship 94% in tolerance across all layers Performance 712,500 tonnes of Pavement in 75 Weeks c2,000t Asphalt and c2,300t CBGM laid every day Customer 15% Saving on Carriageway cost Quality digital record The CBGM has since been extended to include many of the overlay areas where, by the use of a flexible composite pavement alongside the existing and by cold planing the existing to either the underside of the pavement or the underside of the bituminous surfacing, we have been able to provide a cost effective, easily constructed pavement that gives the best option for good productivity, quality and ease of working. *

5 COLLABORATION BRINGS SUCCESS…
*

6 INNOVATION BRINGS REWARDS… 39 and Counting!
BCI Award Winner Application of Technology *