P09712 Commercial Roll Line Shrink Reduction

Similar presentations


Presentation on theme: "P09712 Commercial Roll Line Shrink Reduction"— Presentation transcript:

1 P09712 Commercial Roll Line Shrink Reduction
Levi Stuck Evan DeCotis Cinthia Sanchez Joseph Fitzery Ryan Dennison P09712 Commercial Roll Line Shrink Reduction

2 Technical Review Agenda
Meeting Purpose Address any issues that feel soft or unsure in our project so we can proceed with confidence Materials to be Reviewed Risks and Concerns, Current State Value Stream Map, Ranked Areas of Analysis and Defects (Data Collection) and Defect Sources Meeting Date January 16th, 2009 Meeting Location RIT Campus, Kate Gleason College of Engineering Building 09, Room 4435 Time: 3:30pm to 5pm Team Expectations for Design Review 3 minutes Project Background 15 minutes Project Risks and Concerns 20 minutes Design Implementation Defects and Sources of Defects Impact of Possible Changes

3 Our Expectations from this Design Review are to talk about…
Risks Address and resolve Implementation Probability On-going Acceptable for Senior Design Defects and Sources How can we improve our data collection Impact Other rolls New buildings New ideas

4 Background Information
Project will resolve issues in producing hotdog and hamburger rolls Brooks Ave bakery supports all Wegmans stores Maximum throughput of around 4,500 packages per hour 5% to 10% defect ratio Many different reasons why

5 Objective Statement The objective of the Commercial Roll Line Shrink Reduction project is to identify wastes associated with transportation, inventory, motion, over production, over processing and defects and reduce them. Other objectives include implementing flow, transforming current operations to lean processes, developing metrics, and researching and updating outdated bottleneck equipment.

6 Customer Needs

7 Engineering Specifications

8 Data Collection

9 Data Collection

10 Risks Implementation Project Constraints/General Delay Time
Sustainability Changes have negative impact on other rolls Extra work/resistance Project Customer needs vs. Senior Design Scope Constraints/General Not easily making a connection with the defect and the source Budget Tweaking machines Food grade regulations

11

12 Example: Proof Box Measure Temperature and Humidity
Dough at the top of rack can be exposed to different conditions than the bottom of rack Eliminate Variability Weather-stripping, vents, fans, timers Material Handling Handles on racks, rack bumpers, proper training Visual Aids Need to know when to take out dough

13 Good Product, Bad Product

14 4+4 Defect, Not Aligned, Size

15 Dough Touched or Unsettled

16 Uneven Baking, Dough Bubble

17 Dough Offset, Brown/Overcooked