1 Woodinville-Duvall Road Widening Project Update
Parks and Recreation Commission February 7, 2013

2 WOODINVILLE-DUVALL ROAD PROJECT LIMITS 156th Ave NE to 171st Pl NE
Approximate length: 1 mile

3 ROADWAY SECTION ALTERNATIVES
Alternative B2 – Shifted to Accommodate Utilities Council Selected Alternative (selected 4/13/10)

4 PROJECT COST / BUDGET / FUNDING
$ 10,219,000 FUNDING TIB (State) $ 4,500,000 FHWA (Federal) $ ,852 LOCAL $5,172,148 FUNDING AVAILABLE $ 10,219,000 UNFUNDED AMOUNT $

5 PROJECT SCHEDULE Utility relocation March – August 2013
Construction bid December 2013 Construction beginning Spring 2014

6 Any Questions?