1 Subsystem Mgrs F2F Meeting Calorimeter Subsystem
15 June 2005 J. Eric Grove Naval Research Lab J Eric Grove

2 CAL Status Completed final CPTs and calibrations on FM 111 – FM 118
Completed ATDPs and PreShip Reviews on FM 111 – FM 118. Shipped to SLAC FM 108 – FM 114 Post-ship testing in progress for FM 111 – FM 114 Preparing FM 115 – FM 118 for shipment on 23 June. Assembly and Test of Module 119 PEM assembled and tested AFEE boards installed and soldered TEM/TPS safe-to-mate in progress J Eric Grove

3 Assembly and Test Completion ] This month ] Previously  Started
J Eric Grove

4       CAL Module Milestones Deliveries or Ready to Ship
December ’04 FM 101 January ’05 FM 102 – 105 February ’05 FM 106 – 107 March ’05 - - - April ’05 FM 108 – 110 May ’05 FM 111 – 114 June ’05 FM 115 – 118 Shipped 6/6/05 Shipped 6/13/05 Ship 6/23/05 J Eric Grove