Presentation is loading. Please wait.

Presentation is loading. Please wait.

SR 400 Express Lanes: Market Sounding

Similar presentations


Presentation on theme: "SR 400 Express Lanes: Market Sounding"— Presentation transcript:

1 SR 400 Express Lanes: Market Sounding
February 27, 2018 K. Joe Carpenter, Jr., P.E. Director of P3 Georgia Department of Transportation Photo: SR 400 N at Abernathy Hello and brief introduction. Today I would like to share information on the SR 400 Express Lanes Project which is a part of GDOT’s Major Mobility Investment Program (MMIP).

2 MMIP Projects 11 major mobility projects under contract in 10 years (by 2026) $11 billion program Improve passenger and freight movement Use innovative delivery and public-private partnerships to accelerate projects The state Transportation Funding Act of 2015, or TFA, added approximately $1B a year to address our state’s transportation needs. A major part of the promise to Georgia taxpayers was to commit $11 billion dollars to get 11 new major projects into construction by 2026. One of those project is SR 400 Express Lanes.

3 SR 400 Express Lanes Two Express Lanes in each direction along SR 400 between I-285 and McGinnis Ferry Rd One Express Lane in each direction from McGinnis Ferry Road to McFarland Road Anticipate DBFOM – availability payments Est. Cost: $1.8 Billion Suggested highlights… 2 Express Lanes in each direction. Very northern section will be 1 Express Lane in each direction. The corridor is approximately 18 miles long. Fund source is a mix of State and Federal. DBFOM with availability payments. No concession. Other things to highlight… An adjacent project just to the south is I-285 Top End Express Lanes which too will be DBFOM using Availability Payments for the payback. GDOT is administering Transform 285/400 which is scheduled to be complete in 2020. We are currently working Logical Termini between SR 400 and I-285 Top End which we believe will be Spalding Drive. A GEC team (AECOM) is developing concept, NEPA document and costing plans. HNTB is serving as Program Manager. EY has been providing financial advisor services.

4 Typical Cross Section SR 400
Shoulder Shoulder Existing Shoulder ETL ETL ETL ETL Shoulder The existing SR 400 cross section is shown at the top. The proposed SR 400 cross section… widening existing to the outside with the new Express Lanes on existing concrete pavement in the median separated from the GP lanes by delineators. The original concrete pavement constructed in early 1970s and widened in stages starting in 1989 from its original four lane configuration to its current configuration of 8 lanes. Proposed

5 SR 400 Express Lanes Schedule
High level overview of the schedule. Environmental document is the critical path to meeting Dec 2020 letting. Department is working to acquire ROW early. Schedule subject to change

6 SR 400 Express Lanes Schedule Highlights
Public Notice Advertisement/Industry Forum – Spring 2019 Issue Draft RFP – Jan/Feb 2020 Project Letting – December 2020 Open to Tolling – Fall 2024 To highlight a few schedule milestones.

7 SR 400 Express Lanes Activities
Current Activities Operational study to define express lane access points Traffic analysis Local/agency stakeholder coordination Environmental field work Next Steps Environmental phase Early ROW acquisition Existing asset condition surveys Traffic Report Costing Plans Procurement Documents The SR 400 Express Lanes is now in early activities with the GEC for pre-let support.

8 SR 400 Express Lane Miles Existing New Total Express Lane 48 15 62 General Purpose Lane 69 44 113 Ramp 17 9 26 Cross Street 8 142 67 209 Majority of completed express lanes and general purpose lanes will be supported on existing (old) concrete pavement Asphalt Concrete Structure Total Express Lane 61 1 62 General Purpose Lane 110 2 113 Ramp 5 21 26 Cross Street 4 8 9 192 209 I show this slide to highlight the existing SR 400 assets within this corridor. The Department understands the risk associated with including these existing assets into a DBFOM contract.

9 Initiate Procurement/Develop DBFOM RFP Documents
Industry and Owner Outreach Develop O&M Estimates Define Operational Constraints Evaluate Existing Assets Extent of Operational Services by Developer Responsibility for Non-Toll ITS Maintenance Performance versus prescriptive Specifications Fence to Fence versus restricted O&M Limits Life-Cycle Risk for Existing Assets DB Technical Requirements and OVT for DBFOM Develop O&M Risk Register Alignment with Goals Preserve Asset Value Value for Money Reliability Customer Service Seamless User Experience Traveler Safety Worker Safety Accurate Reporting Contracts Enforced Optimized Technology Key Decisions Core Activities Consultees Office of Traffic Operations Office of Maintenance District Offices SRTA Office of Materials and Testing IT / Network Group Bridges Construction Optimize programmatic / Project-specific Outcomes Initiate Procurement/Develop DBFOM RFP Documents FHWA There is a lot in this slide. I show it to highlight that the Division of P3 is actively engaged with key GDOT offices (Traffic Ops, Maintenance, District Maintenance), State Road and Tollway Authority (SRTA), EY, and others to evaluate the various risks and opportunities associated with delivering this corridor using DBFOM. In addition, we met with a small group of AMOTIA members last year, I have been on the road communicating the program to gather feedback. And with that I turn it over to questions.

10 Questions?

11 MMIP Program Information
@GeorgiaDOT @GADeptofTrans @gadeptoftrans


Download ppt "SR 400 Express Lanes: Market Sounding"

Similar presentations


Ads by Google