Presentation is loading. Please wait.

Presentation is loading. Please wait.

Town of Dunn Sanitary District No. 3

Similar presentations


Presentation on theme: "Town of Dunn Sanitary District No. 3"— Presentation transcript:

1 Town of Dunn Sanitary District No. 3
Informational Meeting on Capital Improvement Plan June 2, 2016

2 Capital Improvement Plan
Manhole Inspection Review Sewer Video Recordings Lift Station Inspections Review Maintenance Records from Madison Metropolitan Sewerage District Identified Defects and Needed Restoration Established Three Phases for the Restoration Work and Estimated Costs

3 Gravity Sewer Mains and Manholes
Pipe Diameter (inches) Quantity (linear feet) 8 35,133 10 1,983 12 4,556 15 1,032 18 593 Total 43,297 180 Four Foot Diameter Manholes

4 Lift Stations No. 1 No. 2 No. 3 Design Capacity (GPM/TDH)
600 / 41 feet 500 / 63 feet 300 / 35 feet Pump Motor (HP) 15 20 7.5 Percentage of District Served 95% 78% 11%

5 Existing Flow Lift Station 1 Lift Station 2 Lift Station 3
Daily Average Flow (gpd) 63,000 50,700 10,300 Peak Daily Flow (gpd) 216,000 193,200 39,600 Peak Hourly Flow (gpm) 240 180 110 Peaking Factor (Peak Day/Average Day) 3.4 3.8

6 Current Peak Hourly Flow Percentage of Capacity Utilized
Lift Station 1 600 gpm 240 gpm 40% Lift Station 2 500 gpm 180 gpm 36% Lift Station 3 300 gpm 120 gpm 18” Gravity Sewer 1,540 gpm 612 gpm 39% 15” Gravity Sewer 1,120 gpm 55% 12” Gravity Sewer 730 gpm 33% 10” Gravity Sewer % 80% 8” Gravity Sewer % 22%

7 New System Map

8 Capital Improvement Plan
Phase One – Critical Infrastructure and Urgent Repairs Phase Two – Lift Stations Phase Three – Repairs to Remaining Collection System

9 Phase One Slip Line Critical Sections
Excavate and Relay Significant Sags Grout MH Walls Replace MH Lids with Open or No Pick Holes Estimated Cost with Construction in $1,365,000

10 Phase One Map One

11 Phase One Map Two

12 Phase One Map Three

13 Phase One Map Four

14 Phase Two Paint Lift Stations
Replace Screening Box in Lift Station No. 3 Replace Control Panels Estimated Cost with Construction in $138,000

15 Phase Three Slip Line Remaining Sewer Sections
Replace MH Lids with Open Pick Holes Estimated Cost with Construction in $354,000

16 CIP Financing Financing of these improvements could be accomplished by using funds in the District’s replacement account, loan(s) from the WDNR, and special assessments from the District. The District is currently plans to finance Phases Two and Three from the replacement account.

17 Phase One Financing Options
Option 1 - $400,000 from District Replacement Account and $965,000 Loan A 10-year loan of $965,000 at 2.275% (current WDNR loan rate) would result in an annual principal and interest payment of $108,000. This would require an approximate $221 increase in annual sewer service charge to a residential customer or a 42% increase in current sewer service charges for 10 years. Option 2 - $400,000 from District Replacement Account and $965,000 in Special Assessments Would require a special assessment of approximately $1,977 for a typical residential user. This would be a one-time 373% increase in sewer service charges.

18 Questions? Tim Astfalk, PE Project Manager 608-443-0482


Download ppt "Town of Dunn Sanitary District No. 3"

Similar presentations


Ads by Google