1 Cannon Falls Roundabout Modification Project
Jai Kalsy | Project Manager January 25th, 2017

2 Agenda 5 mins Staff Introductions Project Purpose/Needs 10 mins
Time Topic 5 mins Staff Introductions Project Purpose/Needs 10 mins Project Description 20 mins Construction Staging/Traffic Impacts Schedule & Next Steps 15 mins Questions & Answers 11/22/2018

3 Introductions Jai Kalsy – Project Manager/Plans Engineer
Paul Schauer – Construction Engineer Adam Wellner Assistant Traffic Engineer Greg Paulson – Assistant District Engineer Mike Dougherty – Public Affairs Coordinator 11/22/2018

4 Project Purpose/Need Trucks having trouble using east roundabout
Noticeable curb height at east ramp roundabout– issues with loads. Constructability issue. Trucks feeling pinched negotiating all roundabouts Purpose Replace east ramp roundabout inside curb with updated curb design. Alleviate roundabout pinch points by moving island curb and signing back Construct with minimal traffic impacts, advanced planning and notice. 11/22/2018

5 Staging Plan – Stage I 11/22/2018

6 Staging Plan – Stage II 11/22/2018

7 Staging Pan – Stage IIIa
11/22/2018

8 Staging Plan – Stage IIIb
11/22/2018 Optional Tagline Goes Here |  mndot.gov/

9 Staging Plan – Stage IV 11/22/2018

10 Schedule Begin Construction – Mid April to Early May (weather permitting) Contract Time: 30 working days (weekend work not anticipated) End Construction: Mid June 11/22/2018

11 Questions? Jai Kalsy 11/22/2018