Team Kenneth Aramaki Kevin Atebara Petra Carlson Kevin Vitayaudom Advisor Dr. Albright Industry Representative Mr. Howard Voorheis Fluke Instruments, Ret. 28 February, 2006 University of Portland School of Engineering

2 Overview Introduction Scorecard Additional Accomplishments Plans
Issues/Concerns Conclusions 28 February, 2006 University of Portland School of Engineering

3 Introduction What it does? How it works? 28 February, 2006
University of Portland School of Engineering

4 Ssssssscorecard Jake the Snake Plummer January’s Plans Completed
TOP Complete Transfer Function Test/Build Mech. Prototype Integrate Sub-circuits Build Amplifiers Completed Shortcomings Jake the Snake Plummer 28 February, 2006 University of Portland School of Engineering

5 Additional Accomplishments
Received “Upgraded” Parts Built Enable Circuit Built 4th Order LPF Concluded Simulations 28 February, 2006 University of Portland School of Engineering

6 Plans Move Parts to Vector Board Test/Build Mech. Prototype
Integrate Entire System Test/Measure System 28 February, 2006 University of Portland School of Engineering

7 Milestones 1 Product Pre-Approval 9/15/05 9/20/05 2
Number Description Original 9/29/05 Previous 1/31/06 Present 2/28/06 1 Product Pre-Approval 9/15/05 9/20/05 2 Functional Spec 1.0 10/7/05 10/12/05 3 Finalize Parts Needed 10/3/05 11/25/05 4 Project Approval 10/14/05 5 Order Parts 10/24/05 12/16/06 6 Plans 1.0 11/17/05 7 Design Release 12/9/05 1/30/06 2/27/06 8 Receive Parts 1/18/06 2/1/06 2/24/06 9 TOP Approval 10 System Integration 3/9/06 11 System Testing Complete 4/3/06 12 Prototype Release 4/7/06 13 Founders Day 4/11/06 14 Final Written Report 4/28/06 28 February, 2006 University of Portland School of Engineering

8 Concerns/Issues Concerns/Issues: Voltage Supplies Lab Test Results
Additional Testing 28 February, 2006 University of Portland School of Engineering

9 Conclusions Project Approach Status On Schedule
Additional Accomplishments Milestones Update Concerns/Issues Questions? 28 February, 2006 University of Portland School of Engineering