Project Management Principles and Practices

Similar presentations


Presentation on theme: "Project Management Principles and Practices"— Presentation transcript:

1 Project Management Principles and Practices
University of Alberta Technology Training Center Developed by Priscilla Bahrey, PMP

2 Overview The purpose of this course is to provide an overview of Project Management – the principles and practices to help you to manage a project or to participate more effectively as part of a project team. This training guide covers related Project Management principles related to planning and executing a project, managing people and resources, connecting with stakeholders, maintaining and managing scope, budget and timelines.

3 Training Objectives: By the end of this Project Management Practices and Principles course, you will have an understanding of how to: plan and execute a project manage people and resources connect with stakeholders maintain and manage scope, budget and timelines What we will cover today…. Learn what project management is and the qualities of an effective project manager. Understand the nine knowledge areas of project management and how they can be applied to your project. Discover the phases of a project and what deliverables are expected when. Identify a project’s key stakeholders. Understand the different types of business cases and how to create a Statement of Work. Learn to be prepared for the unexpected by utilizing risk management and change control. Learn how to organize project activities by creating a Work Breakdown Structure. Create a network diagram to track your project’s progress. Learn budgeting and estimating techniques.

4 Section 1: Introduction Section 2: Initiating (Definition)
Agenda for 3 Days Section 1: Introduction Section 2: Initiating (Definition) Section 3: Planning Section 4: Executing Section 5: Monitoring & Controlling Section 6: Closing Introduction to Project Management Reasons projects fail Successful project features What is Project Management? Key functional areas Project Definition Stakeholder Identification Business Case Feasibility Study Cost/benefit analysis Business Goals and Objectives Statement of Work Risk Constraints Day 2 Project Planning Work Breakdown Structure Network Diagrams Scheduling Budgeting

5 Introductions What is your Project Management Experience?
What types of projects will you be involved in? What would you like to get out of the course?

6 Reference Material Project Management
Idiot’s Guides As easy as it Gets! Sixth Edition Page 5

7 Unit 1: Introduction This unit will cover: Project Successes/Failures
What is Project Management? Project Management Knowledge Areas Project Life Cycle

8 What is a Project? Project
A temporary endeavor undertaken to create a unique product, service, or result —PMBOK® A Project is something that has a specific start date and a specific end date. This start and end date must be understood, and accepted, by the people in charge of the project. May be similar to other project but the process to create your project is unique, and therefore, the product of the project (the thing the project creates) is subsequently unique. This is distinct from a program, which often uses an existing process and duplicates it over and over to produce a replicated product. An assembly line is an example of a program, while building a skyscraper is an example of a project. A project is the result of a multi-task job that performs something specific (i.e. a goal). This means that between the start and end dates of your project, the unique thing that your project does involves a series of interconnected processes that performs in a progressively elaborative way to achieve a specific goal. Progressive elaboration means that you keep creating, modifying, and building upon the raw ingredients of your project, in an organized way, in order to achieve the project's specific goal (also referred to as the product of the project). “PMBOK” is a trademark of the Project Management Institute, Inc.

9 Activity Why do projects fail?
(Discuss what you have seen in your assigned teams) Have you been on a project that failed? Identify some of the reasons

10 Reasons for Project Failure
Poor project and program management discipline Lack of executive-level support No linkage to the business strategy Wrong team members No measures for evaluating the success of the project No risk management Inability to manage change Develop a well-defined project plan, use proven methodology and use project management tools to track and control your project Enlist executive leadership (talk more later). Provide regular executive level communication and keep reinforcing the need for their involvement Provide a clear business direction that can be understood by everyone impacted by the project. Everyone needs to know WHY the project is important and WHAT it will mean when it is done and HOW you are going to do it Should select people just because they have the time, they should be on the team because they have the right knowledge and experience – perhaps even contract out if you need to Success should be spelled out at the beginning so that a) you can meet it and b) you know when you’ve gotten there Be proactive in managing risk – have a risk plan – identify risk and strategies for dealing with them Change in both the project (project change management) and change within the organization in addressing the change that the project will bring (organizational change management). Chapter 3 Page 26

11 Project Management Project management
The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements —PMBOK® Project management Institute definition PM BOK – project management Body of Knowledge

12 PM Knowledge Areas Integration Management Scope Management
Time Management Cost Management Quality Management Human Resource Management Communication Management Risk Management Procurement Management Stakeholder Management PMI PMBOK Version Knowledge Areas Chapter 4 page 37

13 Project Success Criteria
On time Within budget Satisfied Stakeholders Develop a well-defined project plan, use proven methodology and use project management tools to track and control your project Enlist executive leadership (talk more later). Provide regular executive level communication and keep reinforcing the need for their involvement Provide a clear business direction that can be understood by everyone impacted by the project. Everyone needs to know WHY the project is important and WHAT it will mean when it is done and HOW you are going to do it Should select people just because they have the time, they should be on the team because they have the right knowledge and experience – perhaps even contract out if you need to Success should be spelled out at the beginning so that a) you can meet it and b) you know when you’ve gotten there Be proactive in managing risk – have a risk plan – identify risk and strategies for dealing with them Change in both the project (project change management) and change within the organization in addressing the change that the project will bring (organizational change management). Chapter 3 Page 26

14 Project Priorities

15 Project Constraints: Time Cost Scope Resources (People) Quality
Risk (Real world) (Facilities and equipment, Computer Infrastructure, Physical Location etc.) Scope (what must be built) Schedule (when it must be built by) Resources (how much it must cost) A good PM needs to know the priorities of the above – then can work at keeping the other sides in balance Must have agreement (team and stakeholders) to the scope and the goals of the project Have appropriate resources supplied – management support Third dimension that a PM needs to balance in customer satisfaction – just because it is done on time, on budget and with the features, still have to be sure that the customers are satisfied with the results. – communication! Effective, appropriate and ongoing.

16 The Triple Constraint Cost (Budget) Time (Schedule)
Good + Fast = Expensive A first rate project, delivered quickly will cost a lot Good + Cheap = Slow want a quality job done for a discounted price? It will be delivered very slow – fit into others scheudle Fast + Cheap = Inferior expect an inferior job delivered on time – you get what you pay for Scope (Work to be done)

17 Project Life Cycle 5 process groups (things you do)
4 phases (Executing, Monitoring and Controlling happen at the same time) Page 49

18 Initiating Phase Initiate the Project Identify the Project Manager
Develop the Project Charter Identify the Stakeholders Define Planning Phase Sign off on the Project Charter

19 Planning Phase Develop a Project Plan (work plan)
Organize and staff the project Sign off on the Project Plan Project plan finalize scope definition (project objective, requirements and specifications, objectives) develop organizational Breakdown Structure – match project work activities and performing organization project scheduling and cost estimating – dependencies, sequencing, project schedule, costs, budgeting, start dates, milestones, other plans – risk, change control, issues resolution, quality assurance, hr plan, procurement plan, monitoring and reporting plan organization transition plan – communication, change leadership plan

20 Executing, Monitoring and Controlling Phase
Execute the Project Plan Manage the Project Plan Implement the project’s results Sign off on project’s completion Execute manage project scope monitor and report project status Manage execute and refine management plans – risk, quality assurance, change control, issue resolution, organization and HR, procurement activate project controls – scope, cost, schedule, quality Implement verify scope complete execute organizational Transition plan transition to operation

21 Closing Phase Document the Lessons Learned during the project
Post-implementation review Provide performance feedback Close-out contracts Complete administrative close-out Final project report

22 Discussion Discuss the rationale for the Phases of a Project and the consequence of rushing into the Planning phase too soon Start well with approval to proceed

23 Unit 1 Review What is Project Management? Key Functional Areas
Project life cycle

24 Unit 2: Initiating (Definition)
This unit will cover: How Projects are selected How Projects are defined and approved How to identify and manage Stakeholders

25 How Projects are selected

26 Business Case: Feasibility Study:
Reasons why the project is undertaken Options that were considered Benefits that are hoped to be realized High-level risks High-level costs & schedule Cost/benefit analysis Feasibility Study: A general estimate used to determine whether a particular project should be pursued Align project with Business Many templates – include one??? Should be more than one benefit – what happens if don’t realize that benefit? Project a bust – should have more than one benefit so that if one falls through other benefits make it worth while Everything at a high level Page 70

27 Business Goals & Objectives
The Project Manager must understand: Goals (the need for the project and the measurable benefits) Scope Time to complete Estimates of timeline, resource requirements and costs This must be done up front Projects must provide some benefit for someone – else why do it? Spell out how the project will benefit each stakeholder Goals should include measurable success criteria – time, costs and resources Get consensus with team before moving on Page 70

28 SMART objectives S – Specific M – Measurable A – Agreed upon
R – Realistic T – Time-bound Chapter 7 page 69

29 Activity Using the Case Study: Define a Service that you will showcase
Create a SMART Project Objective for the project S – Specific M – Measurable A – Agreed upon R – Realistic T – Time-bound Create a project objective for Case Study in one or two sentences (Have other team do the SMART test)

30 Project Charter Purpose statement (Project Objectives)
Scope statement (In/Out) Project approval requirements Benefits and risks High-level cost and schedule estimates Sign-off (approval to move to planning) Project charter critical document between project manage and customer and/or sponsor. Authorizes the project to begin and set stage for all the planning that will follow. Page 79

31 Statement of Work (SOW)
Purpose statement Project scope Project deliverables Goals & objectives High-level cost and schedule estimates Stakeholders Benefits and risks Assumptions and constraints User acceptance criteria SOW lists and defines the goals, constraints, scope, communication guidelines and success criteria for a project. The initial SOW becomes a document subject to negotiation and modification by the stakeholders. When approved it becomes the “official rules” for the project Can be from 1-2 pages on a small project to 100 – page document of understands for a major technical undertaking Purpose – why are we doing this project? Scope – that the project will and won’t do. Project priorities Deliverables – what the project is supposed to produce. Include intermediate deliverables too – can include Project management deliverables like status reports, change requests and other reports. Goals & Objectives – criteria for success. Measurable Cost and schedule estimates – rough but researched Stakeholders – who are they and their interests or ‘stake’ in the project Chain of command – who report to whom on the project. Project org chart. Responsibility matrix outlining roles and responsibilities Benefits and risks – high level Assumptions & constraints – Communication plan – basic reports that will be produced, meetings – frequency, membership

32 Discussion What is the rationale for getting Approval or sign-off on the project and what are the consequences of not getting approval to proceed? Page 81

33 Estimating costs

34 Activity Create a Project Charter for the case study Scope (in/out)
Project Deliverables Success Criteria Assumptions and Constraints High-level Cost and Schedule and Risks Determine who would sign-off Charter using Project Charter template

35 Stakeholder Management
PMI defines Stakeholders as: “An individual, group or organization who may affect, be affected by, or perceive itself to be affected by a decision, activity or outcome of the project”. Who is a Stakeholder Stakeholder is someone who has a vested interest in the success of a project. The pmi defines stakeholder as individuals and organizations who are actively involved in the project or whose interests may be positively or negatively affected as a result of project execution or successful project completion Chapter 6 page 57

36 Stakeholder Management
Step 1) Identify Stakeholders Step 2) Determine Key Stakeholders Step 3) Determine how to Communicate (and manage conflicts) with Stakeholders How to manage Stakeholders Page 58

37 Project Sponsor Shares responsibility for project success
Has authority to make decisions and may provide funding Overcomes political and organizational obstacles Page 61 Holds the ultimate authority, responsibility and accountability for the success of the project Resolves cross-functional organizational issues Promotes innovation to achieve project goals Provides guidance, support and direction to the project Signs project charter and business case Signs project plan and statement of work Certifies quality of the implementation Contributes to and approves the responsibility matrix Assists in developing project policies and procedures Approves project deliverable Approves changes to project scope and provide additional funds for those changes as required Monitors the progress of te project, the project budget and schedule Works with the steering committee Makes business decisions for the project Provides user resources to the project as needed Shields the project from corporate politics Works to resolve conflicts Sponsor provide authority for the project to proceed; guides and monitors the project together with the project manager; key organizationla advocate for the project typically approves the project charter

38 The Customer/User Uses the product or services
May be internal or external Provides requirements May have multiple categories or roles Page 61 Customer may be internal or external individual or organization that will use the project created by the project. establishes the requirements provides funding review project milestones and deliverables ultimately accepts the product

39 Steering Committee Group of stakeholders who approve and agree on:
Project scope Schedule Budgets Plans Changes Page 63 Aka review and approval team or project governance board Usually comprised of key customer representatives and functional managers and executives from organization Limit size to those who really do need to approve project documents May need to have an approval process Advise on business architecture Monitors the project and maintains priority relative to other projects Settles priorities between related/competing projects Provides organizational support Provides timely decisions Resolves major issues of significant risk to the enterprise Deals with issues and change requests that impact the organization Executes changes in budget and/or schedule Provides feedback to the project sponsor and the project managers

40 Working Committee Line managers who are responsible for delivering business results once the project is completed Page 64 Business must “own” the project Representation from all areas of the business that is impacted

41 Functional Managers May manage or supply people that work on the team
Need to be communicated with Need their commitment to the project Page 64 AKA line managers Functional Managers establish company policy provide people sometime provide review and approval authority

42 Input from Stakeholders
Need input from Key Stakeholders throughout the project life cycle

43 Activity Identify Stakeholders from the Case Study
Determine who are the Key Stakeholders Define the Key Stakeholders’ responsibilities/goals/concerns/success criteria Identify as many Stakeholders as possible and then have participants identify the Key Stakeholder – ones with High Influence and will be directly Impacted by the Project

44 Discussion Discuss the importance of knowing who the Key Stakeholders are and the consequence of not communicating with them effectively Cannot achieve project success = Satisfied Stakeholders

45 What is the role of the Project Manager?
Ultimately responsible for project success Plans the project Maintains focus on the project’s objective Leads and manages the Project Team Plan & Act establish objectives breaking work into well-defined tasks charting sequence of tasks scheduling, budgeting coordinating a team reporting communicating Project’s end – success criteria, getting it done Leader honest, competent and inspirational. Motivate, delegate, mentor and coach Manager administrative skills Attitude is most important!!!

46 Discussion What characteristics/skills/competencies are required to be a good Project Manager? Skills/Competencies/characteristics?

47 Seven Traits of Good Project Managers
Trait 1: Enthusiasm for the project Trait 2: Ability to manage change effectively Trait 3: A tolerant attitude toward ambiguity Trait 4: Team building and negotiating skills Trait 5: A customer-first orientation Trait 6: Adherence to the priorities of business Trait 7: Knowledge of the industry or technology Ambiguity other bosses for team members varying levels of job levels customers on the team Chapter 2 page 15

48 Project Leadership Gain consensus on Project Outcomes
Build the best team you can Develop a plan and keep it up to date Remember that people count Gain the support of Management and Key Stakeholders Keep others informed of what you are doing

49 Discussion What can the Project Manager do to gain consensus and buy-in on project objectives? How can you build synergy on the project team? (What is your team is a virtual team?) Skills/Competencies/characteristics?

50 Establish Ground Rules for a Project Team
Activity Establish Ground Rules for a Project Team (Brainstorm Ground Rules that would be appropriate for this 3-Day Project Management Course) Have you been on a project that failed? Identify some of the reasons

51 Unit 2 Review Project definition Business case Project Charter Stakeholder identification Project Leadership

52 Unit 3: Planning This unit will cover planning: Scope (WBS)
Schedule (Network Diagram) Cost (Project Budget) Responsibility Allocation (RAM)

53 Project Planning Scope (Work Breakdown Structure)
Schedule (Network Diagram) Cost (Budget) 2 3 Time Cost Part 3 page 103 Planning involves defining the Scope/the Schedule and then the Budget Scope 1

54 Work Breakdown Structure (WBS)
The WBS is defined by PMI as, "a deliverable-oriented grouping of project elements that organizes and defines the total work scope of the project….” Chaper 9 Page 104- WBS – hierarchical chart Will use it to schedule and cost from Work package – lowest level of project activities – has time and cost associated with it. Have a unique deliverable associated with it

55 The Work Breakdown Structure (WBS)
Breaks the large project into manageable units Defines the total scope of the project Starts with the deliverables Shows work packages (tasks or activities) Allows you to organize work to then be scheduled Allows you to be able to assign work to team members and identify resources needed Communicates all the work that needs to be done What WBS does

56 To create a WBS Break work into independent work packages that can be sequenced, assigned, scheduled and monitored Define the work package at the appropriate level of detail Integrate the work packages into a total system Present in a format easily communicated to people Verify that the work packages will meet the goals and objectives of the project How to create a WBS

57 Work Packages Way of managing the project by breaking it down
Help determine skills required and amount of resources needed Communicate work that needs to be done Work sequences are identified and understood Page 110 How do you eat an elephant? One bite at a time 8/80 rule if less than one day (8 hours) should be combined with other task if more than 2 weeks (80 hours) should be broken down into smaller activities

58 Activity Create a WBS (Work Breakdown Structure)
List all work packages required for the Case Study on yellow sticky notes (Start with Deliverables) Use Yellow Sticky notes – Start with Deliverables

59 Discussion Discuss the importance of defining the “what” we will do in the WBS before moving to the “how” in building the schedule? Must define the What first or you will miss things if you jump to a PM tool (Microsoft Project) first

60 Dilbert’s Scheduling

61 WBS and Network Diagram
WBS: what needs to be done Network Diagram: how the work will be done (the workflow) Page 116 What then How

62 Scheduling Establish scheduling assumptions
Estimate the resources, effort and duration Effort – time that it takes to work on the activity Duration – the time to complete the activity Determine calendar dates for activities Adjust individual resource assignments Chart final schedule Chapter 10 Scheduling assumptions Fixed resources? What is a work day? What is the delivery date? Is it fixed? Are resources trained and available? Effort and duration – explain the difference Effort driven – the amount of work stays the same, adding more resources will shorten the duration Fixed duration – doesn’t matter how many people you add to the task, it will still take the same amount of time – ex how long it takes for paint to dry

63 Estimating Time Have the people who are doing the work provide the estimates Get an expert’s estimate Find a similar task Look for relationship between activity and time (parametric estimate) Educated guess Page 119 Just a guess but instead of a WAG (wild ass guess) use the following Parametric estimate – so much time per lines of code. How long to paint – how long to paint 100 sq ft? then extrapolate Who to ask: experienced team members outside vendors and service agencies other PM or experts management or other project staekholders

64 PERT Estimating PERT = [O + 4(ML) +P] / 6
PERT – Program Evaluation Review Technique (Uses 3 time estimates to determine most probable) Optimistic estimate (O) Most likely (ML) Pessimistic estimate (P) PERT = [O + 4(ML) +P] / 6 Compromise between best and worst case Statistical Logic – weighting most likely Can discuss Standard Deviation Levels and Confidence Levels

65 Contingency Padding Estimates = Poor Estimates
Add contingency as an activity (Contingency is typically 10-15% of the base budget) Typically 10% and then a 10% Management amount if we use up the 10% contingency PM – controls Contingency Mgmt – controls Mgmt

66 Activity List all Activities on Network Diagram Sticky Notes and determine their Duration (Start with Work Packages) List all Activates related to the Work Packages and guess duration but do one PERT calculation

67 Network Diagrams Logical representations of scheduled project activities Define the sequence of work in a project Drawn from left to right Reflect the chronological order of the activities Shows sequences and relationships between activities Vehicle for scheduling

68 Precedence Precedence defines the sequencing order
How work elements are related to one another in the plan Many activities can be done in parallel or at the same time (if resources are available) If one activity must be completed before the next activity can be started, the first one has precedence over the second

69 How to create a Network Diagram:
Create an Activity for each task Lines connect activities to one another Activities are laid out horizontal from left to right Parallel activities are in the same column Precedence is shown by drawing lines from activity to activity One activity may depend on the completion of multiple other activities How to

70 Sample Network Diagram
Shows sequences and relationships between activities Vehicle for scheduling

71 Lead and Lag Lead – amount of time that precedes the start of work on another activity Lag – amount of time after one activity is started or finished before the next activity can be started or finished Lead time – painting first coat and second coat. There must be 4 hours before the second coat can be started. Lag – the primer can be started before the final colors are finalized (just need to know the type of paint to use). However they both must be finished before the start of the first coat

72 Critical Path The longest path (the sequence of tasks that forms the longest duration) The shortest time that you can complete your project Float Amount of time that an activity may be delayed from its earliest possible start date without delaying the project finish date Latest possible finish date – earliest possible start – duration = total float Page 134 Critical path Least amount of flexibility – delaying an activity on the critical path delays the whole project Note: not most important path – just the one constrained by time Float aka slack If float = 0 it is on the critical path Walk through an example of determining float and critical path

73 Gantt Chart Page 125 Gantt Chart sample

74 Normalizing the Schedule
Assign people to the schedule Start with the critical path first Non-critical tasks second Page 139 Know availability of resources Assign best suited person to the task Use effectively as possible so smallest gap in working schedules Iterate until balanced

75 Loading and Leveling Resource Load – the amount of work that is assigned to a resource Resource Leveling – redistribution to even out the distribution of work across all resources Page 140 Some resources may be over allocated – given too much work than they can accomplish in a given period of time Leveling can move some of the work from over allocated resources to under utilized resources. Use a histogram to show usage of resources

76 Scheduling Tips Ensure that learning time is identified
Ensure that administration time is included Be aware that resources seldom work 100% of the time on one project Page 143 Sometimes a SCHMO is more expensive than a SME

77 Activity Create a Network Diagram for the Case Study
Order all Activities on Network Diagram (relationships and dependencies) Do a forward pass to determine the project length (Input + Duration = Output) Mark the Critical Path in red Create a Network Diagram - Google some samples to show

78 Discussion Discuss the importance of knowing the critical path and how that helps the project manager make decisions Page Why you need to know Critical Path To assign resources – take off non-critical activities at times If you need to shorten project – take out of CP

79 Budgeting Budget = People + Resources + Time

80 Classic Budgeting Mistakes
Giving a number too soon Before WBS Not considering risk Not evaluating experience and skill of resources Budgeting mistakes giving an off-the-cuff estimate that becomes the budget budgeting before WBS is done – don’t know the amount of work not including risks in budget Pressured into giving a number. Becomes gospel without any planning. Better response “I wouldn’t want to give you an inaccurate number, so I don’t want to offer a guess right now, But I’m currently working on it. How soon do you need it. Poorly defined project, may be overly optimistic in what you can accomplish. Contingency and mitigation activities not accounted for Training, time etc not accounted for.

81 Budgeting Levels Rough Order of Magnitude Definitive Estimate Page 149
Ballpark – used in project definition phase Rough order of magnitude – parametric estimates – like another project Detailed estimate – bottom-up estimate – take all the details and add them up

82 Direct & Indirect Costs
Direct costs (Directly attributed to the project) Labor Supplies & raw materials Equipment Travel Legal Fees Training Marketing/advertising Direct costs labor supply and materials equipment travel legal fees training marketing/advertising Indirect costs facilities management and administrative overhead

83 Indirect Costs Indirect costs (Shared amongst other projects)
Facilities Site-specific requirements Management & administrative overhead Direct costs labor supply and materials equipment travel legal fees training marketing/advertising Indirect costs facilities management and administrative overhead

84 Types of Budgeting Bottom-Up Top-Down Phased
Bottom-up – use the tasks and then roll them up Top-Down – general expectations of how much it will cost. Harder to do. Senior managers estimate how much at the summary level to budget from Phased – use bottom-up or Top-down to estimate each phase at a time

85 Don’t pad but manage the contingency
Contingency Reserve 10-15% of budget is normal Don’t pad but manage the contingency PMI Library article “Change Budget- One Key to Never Padding Estimates Again” by Neal S. Gray, Keane Inc. Can use PERT estimates to be better at estimating Sometimes easier to get money up front than to keep coming back because of bad estimates. Refer to PMI Library article “Change Budget- One Key to Never Padding Estimates Again” by Neal S. Gray, Keane Inc.

86 Activity Create a Budget for the Case Study
Direct and Indirect costs (Materials, Supplies, Labour costs, Marketing, Printing etc.) Start with Costs add resources (if contracted)

87 Getting the Project Plan Approved
Review the plan with key stakeholders Project Plan must be approved Must get Sign-off to get from Plan to Action Page 197

88 Risk Management Project risk is defined by PMI as, "an uncertain event or condition that, if it occurs, has a positive or negative effect on a project's objectives." Chapter 8 page 88 Risk can be positive (opportunity) or negative (threat)

89 Risk Management Step 1) Identify Risks
Step 2) Prioritize Risks (Qualitative Analysis) Step 3) Develop Risk Management Strategies Page 92 How to manage risk

90 Risk Categories Funding Time Staffing Customer relations
Project size and/or complexity Overall structure Organizational resistance External factors Page 91 Categories of risk – can be used to brainstorm risks

91 Risk Analysis Qualitative Analysis = Probability x Impact
Probability (Likelihood) Impact (Consequence) Qualitative Analysis PxI

92 Risk Response Plans (Strategies)
Threats: Avoid Mitigate Transfer Accept Opportunities: Exploit Share Enhance Accept When you have time, you have options – 4 potential Risk Strategies or Plans

93 Risk Track and Control Risk Register Review and update regularly
Assign ownership to risk Risk Register Template

94 Activity Identify 10 Risks for Case Study Project
7 threats/3 opportunities 2) Rank the Risks (PxI) 3) Develop Risk Response Strategies 3 threats and 3 opportunities (for highest ranked risks from PxI) Use Risk Register Template for 10 Risks

95 Discussion Discuss the value of Risk Management and the consequence of not identifying risks Exponentially more expensive to deal with Risk when they happen than to plan ahead

96 Project Team Need to let the team members know:
The reason they are on the team, and what they have to offer Their Roles and Responsibilities Standards that they will be held accountable to Chapter 13

97 Responsibility Assignment Matrix
Activity PS PM BA Tech Test User SOW A R S I Scope Doc C Design Doc Test Plan Training Plan RASIC Chart R – Responsible A – Approves S – Supports I – Inform C – Consult Page 234 Special type of Responsibility good for decision making or specific deliverables

98 Building a team What kinds of experience do you need?
What kind of competency do they have? What is their availability? Do they have a personal interest in the outcome of the project? Will they work well in a team environment? Choosing the core team could be the single most important decision you make as a project manager Match skills to WBS

99 Staffing Alternatives
Use your own staff & people from your department Staff from other departments Contract with consultants, outside agencies, or temporary agencies Hire and train new staff Own staff easiest already busy manage conflicts in priorities between project and other work Other department better access to expertise hard to get the resources manage conflicts Contractors expensive more flexibility no cultural experience (can be good and bad) Hiring if long project and need the people after for support this is a good alternative takes time to hire and then train

100 Dealing with Staffing Challenges
Do the best you can with the people you have, and document problems and results. If they do not have enough skills, and training takes too long, consider contracting. Compromise and negotiate for the team members you really need. Page 174

101 Activity Using the Case Study, create a RAM (Responsibility Assignment Matrix) using any legend you wish (e.g. RACI, RASCI, RASIC, PBRIS) Deliverable Person/Role Activity 1 R A C Activity 2 I Sample RASIC Page 163 Sample RACI chart page 341

102 Unit 3 Review WBS Network Diagrams Scheduling Budgeting Risk RAM
Sign off on Project Plan

103 Unit 4: Execution In this unit, you will learn: Operating Guidelines
Communication

104 Operating Guidelines Reporting Project Status Change Management
Decision making Managing the team Chapter 18

105 Plan-Do-Check-Act Cycle
Page 230 W. Edward Deming – total quality movement of 1980s Plan – Planning Do – executing Check & Act – controlling process

106 Discussion Discuss how the role of the Project Manager changes in the Execution phase? In Execution the PM is managing the team

107 Communication Chapter 19

108 Communication Plan Who? Right point of contact
What? Information to be communicated How? Method of communication (Format) How Often? Frequency of communication Timing too soon may not know all the answers – too late and it may seem like you are seemly railroading ahead without getting their approval. Feedback loops phone call water cooler chat rumors

109 Sample Communication Plan
Develop a communication plan from the case study Stakeholder Information Required From Whom (Sender) Schedule of Delivery Means of Delivery Format Start Date End Date Comments This person or group needs this information from this person or group on this schedule delivered by in this format starting this date and ending this date Enter additional information here Project Sponsor Status Report Project Manager Bi-weekly Report Jan. 15 June 31 Summary of accomplishments for this period, plans for next period, issues barriers, overall project status Page 243

110 Adapt your communication style based on:
Macro and Micro Barriers Geography, language, culture Attitudes Jargon and Acronyms Stakeholder preferences Page 244 Adapt or tailor your communication style

111 Effective Messages Draft the message and edit
Consider audience’s expectations, actions required, and your expectations after the message is delivered Justify the choice of delivery method Identify the issue, context or opportunity of interest first Make required actions clear and specific Be concise Page 253 How to communicate effectively

112 Activity Create a Communication Plan for the Case Study From To
Choose 4 Stakeholders (from Stakeholder Identification Activity) What do they need to know (Nature of Communication) How will you will communicate with them (Method) How often you will need to communicate with them (Frequency) Choose stakeholders with different impact and influence and decide how you will communicate with them From To Nature of Communication Method Frequency

113 Discussion What is the value of a Communication Plan and what are the consequences of not communicating effectively with Stakeholders? Exponentially more expensive to find out about a Stakeholder in the implementation phase

114 Unit 4 Review Operating Guidelines PDCA Communication

115 Unit 5: Monitoring and Controlling
In this unit, you will learn: What to Monitor and Control Earned Value Change Management Quality

116 Monitoring and Controlling

117 Discussion What does it mean to Monitor and Control the project?
Monitor is verifying things go according to plan and Controlling is taking action to correct things

118 What to Monitor? Completion of work packages compared to plan
Scope of work Quality of work Costs and expenditures Attitudes and cohesiveness of team Page 261 Project scorecard (green, yellow, red) cost schedule quality best practices functional issues communication risk

119 Purpose of Monitoring Communicate project status and changes to Project Team Manage expectations of Stakeholders Provide justification for project adjustments Document current project plans compared to original Page 264

120 Monitoring Project Performance
Time $ EV PV Actual cost BAC Page 265 Project review meeting with team – resolve issues, discuss status, etc Used to Report Status

121 Earned Value EV= Earned Value (Value of work completed)
PV= Planned Value (Value of work as planned) AC= Actual Costs (Costs billed to the project) Reporting on Variances: Schedule Variance (SV=EV-PV) Schedule Performance Index (SPI=EV/PV) Cost Variance (CV=EV-AC) Cost Performance Index (CPI=EV/AC) Page 265 Measures project progress Forecasting its completion date and final cost Providing schedule and budget variances along the way As project activities are completed they will “earn value” SV – compare amount of work performed to the work scheduled if negative – project is behind if positive – project is ahead CV – compare the budgeted cost of work performed with the actual cost if negative the project is over budget if positive the project is under budget

122 Reporting Cost and Time
Progress Status Forecast

123

124 Using a Gantt chart to report progress

125

126 Controlling Use the project plan as a guide
Monitor and update plan regularly Adapt project schedule, budget and work plan as needed Document progress and changes, communicate them to the team Communicate actions taken to Key Stakeholders Page 268 What controlling is

127 Techniques to compress the schedule: Crashing
How to Control? Techniques to compress the schedule: Crashing Focused on critical path Generate multiple alternatives Add additional resources to the project Fast tracking Overlap sequential activities Project scorecard (green, yellow, red) cost schedule quality best practices functional issues communication risk Indicate that you may need to take action 0 Fast Track or Crash the project

128 How will the Case Study project be monitored?
Activity How will the Case Study project be monitored? What will be reviewed and how often? Examples of what we would be Monitoring?

129 Change Management Plan
The only way to maintain and manage scope! Roles involved in managing change Change Authority (Sponsor, Change Control Board, PM) Process flow diagram for change management All changes are documented and communicated (both approved and rejected changes) Control documents Change Control Log Issues Log Chapter 22

130 Sample Change Control Process
No Impact plan or risk? Good idea? Define impact Yes Yes Change? No Prepare change order Page 286 Walk through example Change approved? To issues list No Yes Amend plan Make the change 3-20

131 Sample Change Control Log
Basic Change Control log example Sample Change Request on Page 289 3-21

132 How to respond to Approved Change
Update the original baseline for approved Project Scope changes to continue to report Project Status (Scope/Time/Cost) Update the original plan to reflect the approved change Communicate the change to all Stakeholders to manage stakeholder expectations (no surprises) Page 294 After Change is Approved 3-22

133 Activity A change is requested by the Project Sponsor. What is the impact of delivering the event 2 weeks sooner to coincide with another similar event? In your groups, perform a Change Impact Assessment in the Change Request Form (Tip: Consider the impact of making the change in terms of time/cost/scope and the impact of not making the change as well as any additional risks) Exercise to do an impact assessment on a Change Request How much will it cost to shorten schedule by 2 weeks? Will anything be taken out of scope or are you able to accomplish all the original scope with additional costs? What new risks are there?

134 Quality Management Project quality is defined by PMI as the “degree to which a set of inherent characteristics (of the finished product) fulfills requirements." Chapter 23 Page 300 Difference between Grade and Quality

135 Quality Quality Planning Development of criteria or metrics
Quality Control: Measuring results Quality Assurance: Assuring conformance to requirements Page 302 3 key parts of building quality into the project Google Duran Crosby Deming (gurus) 3-22

136 Discussion What activities would you do on the Case Study Project to verify and validate Quality? Perhaps testing inspecting verifying etc.

137 Unit 5 Review What to Monitor How to Control Earned Value Analysis
Change Management Managing Stakeholder Expectations Quality

138 Unit 6: Closing This unit will cover: Closing the project
Lessons learned Post-Implementation Review Final Report

139 Closing Chapter 24

140 Closing the Project Final approval from stakeholders
Finalize contractual commitments Transfer responsibilities to others Reassign people in the project Release non-human resources Complete final accounting Document results and recommendations for the future Page 313 Activities done in closing phase

141 Post-Implementation Review
Meeting with Project Team and Sponsor (After celebration but before forgotten) Did the Project accomplish the Objective as stated in the Charter? Page 319 After the project sometimes 3 months or 1 month post-project

142 Activity How would the Case Study project be closed out?
What type of post-implementation review would you do and when? Verifying Launching new service Measuring whether objective was achieved

143 Discussion Celebrate the success of the Project
Why is celebrating success and acknowledging people’s performance on the Project so important? Important to recognize the work – only successful because of team’s efforts Leave an imprint as a PM

144 Final Report Overview of project Major accomplishments
Achievements compared to Business Case objectives Final Financial accounting Analysis of Quality against expectations/requirements Evaluation of administration and management performance Team’s Performance/Special acknowledgments Changes (approved and impact of changes) Issues or tasks of further investigation Recommendations for future projects Post-implementation date Page 325 Final Report to Key Stakeholders

145 Lessons Learned Focus areas
Project Management, Communications, Schedule & Budget, Training, Quality, Issues, Human Resources, Administration What went well? What didn’t? What should be improved? How? Anything else? Page 315 Sample Lessons Learned

146 Discussion Why document Lessons Learned on the project?
Adds to the Intellectual Capital of the organization - don’t make the same mistakes

147 Activity In your teams, conduct a Lessons Learned based on your team performance over the past 3 days: What did you do well in your teams? What could you have done better? What advice would you give to a team about to embark on a similar project (planning an event)? Do a Lessons Learned in teams

148 Common Problems on Projects
Start date moves but end date doesn’t Not enough time Changes, changes, changes Key person quits or is unavailable Team has more enthusiasm than talent People are always 90% done Politics 7 things that often happen on projects

149 Activity Put Learning into Action:
Each team identifies Strategies (to address the reasons that projects fail) Assign one or two problems per team and let them come up with strategies that they have learned in this course

150 Unit 6 Review Final Report Administrative Details Lessons Learned
Celebrating Project Success

151 Review of 3 Days Section 1: Introduction
Section 2: Initiating (Definition) Section 3: Planning Section 4: Executing Section 5: Monitoring & Controlling Section 6: Closing

152 Activity Personal Action Plan
What 3 things do you commit to putting into practice back on the job? Their key takeaways from 3 days

153 Thank you for attending Project Management Principles and Practices…
Slides: Evaluations Would you please provide feedback as to the content of this course and any other suggestions you may have. Thank you again. Evaluations