Download presentation
Presentation is loading. Please wait.
1
Sellafield Ltd An Overview
2
Modern Catastrophes BP Deep Water Horizon
11 employees died in the initial explosion Cost to date £30 Billion and rising Fukushima Nuclear Power Plant Arising from Natural event Costs around £30 Billion and rising TEPCO Nationalised by Japanese Government
3
National Audit Office 2012 “Nuclear operations at Sellafield started in the 1940s, successive operators of the site did not give sufficient thought to decommissioning or retrieving and disposing of radioactive waste. The Authority inherited a legacy of poor planning, neglect and gaps in information” Predicted out turn costs £70 Billion
4
Safe Secure Stewardship Demonstrable Progress Return on Investment
Sellafield Strategy Safe Secure Stewardship Demonstrable Progress Return on Investment
5
11,000 employees at Sellafield
Sellafield Today £1.8bn| annual budget £300m| Local supply chain spend 11,000 employees at Sellafield
6
Sellafield Context 7 shutdown reactors 2 Reprocessing plants
Waste Management High hazard legacy facilities Product Storage Supporting Infrastructure Low temperature, low pressure processes Very large inventory of radioactive material Relatively low rates of change to loss of cooling Aging facilities and infrastructure
7
Sellafield Ltd COMAH status
SL is the largest Nuclear site in Europe One of only two COMAH (Seveso) Nuclear sites in the UK SL uses a number of hazardous substances (COMAH). Examples are as follows, with associated major accident hazards (MAH): Petroleum products Oxygen Sodium Nitrite 38% Hydroxylamine Nitrate 36% NOx Hydrogen COMAH assessment shows SL is currently a lower-tier site PROTECT - COMMERCIAL 15 November 2018
8
Site History – National Defence Programme
The Sellafield site has been operational since the 1940s, when it was used as a Royal Ordinance Factory supporting the war effort. In 1946 the US Congress passed an Atomic Energy Act prohibiting passing classified information to other countries In response to this, Sellafield became the UK’s first atomic energy site and construction of the Windscale Piles to produce military plutonium began in 1947.
9
Site History – Accelerating the clean up
From the 1990s construction began on a number of waste treatment and storage facilities to support reprocessing and decommissioning operations. In 2002 the Waste Vitrification Plant was opened to convert the Highly Active Waste from reprocessing into a solid form for long term storage.
10
Nuclear Safety Principles: Preventing a Catastrophe
Maintaining containment Maintaining cooling Maintaining control of reactivity Maintaining control of chemistry
11
Scope of Emergency Arrangements
Radiological/Nuclear Chemical Fire Transport Loss of Site Services External Events – Weather, Seismic, Malicious Acts/Security Environmental Impacts Severe Accident Considerations
12
Co-ordination of Emergency Response
Emergency Management 15/11/2018 4
13
Effective Management Control
Control of Contractors Security SQEP Nuclear Site Licence COMAH Training Accountability Assurance Regulators Review
14
Control of contractors
Approved contractor status Gated process Demonstrate SQEP Subject to intense scrutiny Performance subject to monthly review Scocio economic commitments Security vetting
15
Security considerations
Driven by specific legislation Classification anyone on site DV SC BC Visitors Info security Breach sanctions
16
SQEP Demonstrable and auditable experience Must be “Suitable”
Formally reviewed at least annually Applies to all site areas Subject to regulatory review
17
Nuclear Site Licence 36 Licence conditions
Each condition approved by the Regulator Covers all aspects of site Subject to formal review
18
Training Not SQEP Formal Site Induction linked to Security
Contract Induction Planned Approved
19
Accountability At all levels Reviewed as part of work package planning
Reviewed at Stakeholder meetings Subject to formal review by the Regulator Runs from SL Board to all areas
20
Assurance Internal Assurance Group Focussed on: Internal Regulation
Tiered audit process Full range of activities Reports directly to the SL Board Works alongside Regulators
21
Regulators: ONR HSE EA Euratom IAEA WANO INPO
22
Review Activities reviewed by SL Board through:
Safety, Security Assurance Group Project Assurance Group Safety Case Assurance Group RIM (Regulator Interface Meetings) Tier 1 Regulatory interface NMP Safety and Operations Review Group Performance Assurance Group
23
Conclusions Sellafield Limited and its specialist suppliers have developed an effective and systematic method of assessing resilience. Effective management control cornerstone Focussed on the plants within the greatest potential consequences Provided successful insights into many facilities beyond their Design Basis. Identified a range of considerations and actions which will make a genuine and sustainable improvement in resilience. Close engagement with Regulators and industry colleagues has been important to success Sellafield are committed to enhanced resilience Incorporated this approach into our long-term periodic review of safety cases
24
Arrangements for resilience
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.