Presentation is loading. Please wait.

Presentation is loading. Please wait.

Cryogenic cavern in Asian site

Similar presentations


Presentation on theme: "Cryogenic cavern in Asian site"— Presentation transcript:

1 Cryogenic cavern in Asian site
Conceptual design of the cryogenic system Layout of the cryogenic plant (old & new version) Storage of helium inventory Cooling water for cryogenic system Summary & Future Plan Oct.12,2011 KEK K. Hosoyama

2 Conceptual Design of Cryogenic System 1
He Gas Tank Cluster 200 m3 x 24 Liq. He Dewar He Gas Tank 50,000 L 200 m3 x 2 SC Cavities 2.5 km 2 K Ref. Cold Box 4 K Ref. Cold Box Helium Gas Compressor Cooling Tower CIB 2.5 km SC Cavities 2 K Ref. Cold Box 4 K Ref. Cold Box Helium Gas Compressor Cooling Tower Helium Gas Accept Station 2K Liq. He Dewar He Gas Tank 50,000 L 200 m3 x 2 He Gas Network 2K Multi-transfer Line 4K Multi-transfer Line Cooling Water Piping Helium Gas Piping Note CIB: Cryogenic Interconnection Box Cooling Tower He Gas Tank Cluster He Gas Tank Cooling Tower Small Shaft for Cooling & He gas storage Cryogenic Cavern Helium Gas Accept Station 2 K and 4 K Ref. Cold Box Access Tunnel Helium Gas Compressor L < 1km SC Cavities in Main Tunnel ~ 5 MW x 2 units

3 Conceptual Design of Cryogenic System 2
Cooling Tower Cooling Tower Access Tunnel Access Tunnel He Compressor x 2 units He Compressor x 2 units 2K He Ref. x 2 units ~ 5 MW x 2 ~ 5 MW x 2 4 K He Ref. 2K He Ref. x 2 units Cryomodule Cryomodule Cryomodule Cryomodule 2.5 km 2.5 km 5 km 5 km Multi-transfer Line 4K cold boxes will be installed in the large caverns at the end of access tunnel. Two 2K cold boxes must be installed in the caverns at 5 km intervals and each 2K cold box supports cooling of ~2.5 km long cryogenic unit. Long multi-transfer line must be installed in the main tunnel to connect 2K and 4K refrigerators. 2K cold box must install in the main tunnel.

4 Layout of Cryogenic Plants for Mountain Site-B
2K cold boxes and distribution boxes will be installed in the cavern in the main tunnel 4 K cold boxes & compressor units will be installed at the end of access tunnel   2.5 km 2.5 km 5 km 5 km 2.5 km 2.5 km 5 km 5 km 1.1 km 2.2 km 1.9 km 2.6 km 2 km 1.3 km 2K Ref.#6 2K Ref.#5 2K Ref.#4 2K Ref.#3 2K Ref.#2 2K Ref.#1 Zone 6 3.8 km Zone 5 4.8 km Zone 4 5.8 km Zone 3 5.1 km Zone 2 4.7 km Zone 1 5.4 km 2K Ref. cold box ( + cold compressor) 4 K Ref. cold box Comments : Long multi-transfer line must be installed in the main tunnel In the caverns build at the end of access tunnel so called cryogenic cavern, two 4.4 K cold boxes will be installed. Compressor unit will be installed far away from main tunnel in the cavern near by access tunnel. He Compressor Access Tunnel

5 Cryogenic Cavern The 4K ref. cold box will be installed in
cavern at the end of access tunnel, so called “cryogenic cavern.” The size of the cold box will be limited by transportation on road from factory to the site Sub tunnel 18kW Helium ref. cold box / CERN LHC Main tunnel Access tunnel 4 K ref. cold box Transportation of the cold box Cavern at the end of access tunnel will be used for installation of cryogenic plants.

6 Installation of Main Cryogenic Components
4K cold box will be carried through the access tunnel to the cavern at the end of access tunnel. -- Enough cross section for transportation of 4K cold box and compressor unit! Problems: 2K cold box must be carried in and out through the main tunnel. 2K caverns must be constructed for installation of 2K and distribution boxes. Multi-transfer line must be installed in the crowded main tunnel. Multi-transfer Line (between 4K and 2K cold boxes) Cryo-module Cold box for LHC 18 kW at 4.5K Ref. 7.2 m D 3.9 m 10.2 m D 4.1 m D 5.2 m Sub tunnel Main tunnel Access tunnel

7 New Layout of Cryogenic Plant
To solve following problems: a) 2K cold box must be installed through the main tunnel b) Need the 2K cryogenic cavern and the long multi-transfer line. Need new access tunnel plan: Cryogenic caverns will be constructed at the end of the access tunnels at every 5 km intervals in the tunnel. Main components of two cryogenic plants: compressor units, 4K refrigerator cold boxes, 2K cold boxes, distribution boxes, and multi-channel transfer line, will be installed in the cryogenic cavern.

8 Concept of New Cryogenic Cavern
Access tunnel 2K cold box Compressor 4K cold box Main tunnel Sub tunnel Access tunnel 30 m 8 m 56 m 20 m 20 m

9 Detailed Structure of Cryogenic Cavern
Temporary size of the cryogenic cavern is given here as for starting point. To decide the shape and size of cavern, we need the detailed design study of the main components and these layout in the cavern. In designing the cryogenic system we must care about the safety and maintenance. compressor unit x 2 4K cold box x 2 2K cold box x 2 2K distribution box 2 liquid helium Dewar(50,000 L)

10 Helium Compressor Unit
The helium compressor is installed in far end of the cryogenic cavern Location of the cavern is ~ 60 m away from the main tunnel to avoid the vibration 26 m Compressor + Motor 5 m x 1.9 m x 2 m H 6 m 12.5 m Helium compressor for18kW Helium Ref / CERN LHC

11 Helium Compressor Unit for LHC
The helium compressor unit consists of several main components. There are many option for layout of these components. We can optimize the lay out.

12 4K Ref. Cold Box for LHC Size of 4K cold box Linde 18kW@ 4.5K
D4m x L18 m

13 Storage of Helium Inventory
ILC Cryogenic Systems Reference Design T.J. Peterson et al. CEC Vol. 53 Required Total Liquid Helium ~ 650,000 L If all helium is stored as gas: 200 m3 x 10 x 2 x 6 cryo. stations units Storage as gas and liquid : Liquid helium 50,000 L x 2 x 6 cryo. stations units Gas helium (Near helium compressor unit) 200 m3 x 2 x 6 cryo. stations units Gas helium (He tank cluster: at He gas accept station) 200 m3 x units Helium gas network ( Gas pipe line connecting 6 cryo. plants) Comment: Gas helium tank D 4 m x 15 m x 20 bar Liq. Helium Dewar D3 m x 15 m Vaporization loss: 50,000 L x 0.5%/day = 250 L / day ~10 L/hr Small refrigerator can be used as “Baby-Sitter”

14 Conceptual Design of Water Cooling System
Option Cooling Tower A Cooling Tower Cluster Small shaft Cryogenic Cavern ~ 100 m Access Tunnel Compressor 4K cold box 1 ~ 2 km Cooling tower at the entrance of access tunnel can support cooling of underground 2 cryogenic plants. Cooling tower cluster can support cooling of ~ 8km long distributed heat load. The cooling water circulate in 900 mm in diameter pipe. By installation of the cooling tower in the tunnel, we can eliminate heat exchanger which need to cut the head pressure. But we need large bore shaft. By using the “thermo-siphon” of refrigerant we can reduce the pipe size.

15 Extraction of heat from the tunnel (1/2)
Plan A Plan A’ Circulation of cooling water 1) Use the specific heat Cp of water 2) Need large mass flow 3) Large in size and long piping 4) Heat exchanger to intercept pressure Underground Cooling Tower Eliminate the heat exchanger Need large dia. shaft Latent Heat of Water 37oC Cooling Tower Air out Air in Air in Supply Water ~ 8 m3 / hr Latent Heat of Water 32oC Access tunnel DH = 100 ~ 150 m DT Large Shaft DH = 100 ~150 m Pump Heat Exchanger Specific Heat Cp of Water 37oC 37oC Pump 37oC 37oC Helium compressor Latent Heat of Water 42oC 32oC 10 MW Cooling Tower Helium compressor 42oC 32oC Pump

16 Extraction of heat from the tunnel (1/2)
Plan B Plan C Circulation of refrigerant 1) Use the vaporization heat 2) Small amount of mass flow 3) Small size piping 4) Eliminate the intercept heat exchanger Compressor is cooled by refrigerant directly ! NH3, R410A, R32 Tc =32oC Cooling Tower Cooling Tower Latent Heat of Water Condenser Condenser h1 Small shaft Vapor Liquid Vapor Liquid Pump Pump Cooling water h3 h2 Te = 35oC Helium compressor Evaporator Helium compressor Evaporator Pump Latent heat of refrigerant

17 Cooling Power by Water vs. Refrigerant
Cooling by water DT = 5 oC Cooing power Pc [ kW ] Specific Heat Cp [kcal / kg] Mass flow rate mw [ kg/sec] Pc [kJ / sec] = 4.2 [kJ / kcal] x Cp [kcal / kg] x mw [kg/sec] Required water mass flow rate mw for cooling 1MW; mw = 1000 / 4.2 / 5 = 48 [L/s] [ m3 /min.] [ m3 / hr.] i.e. For cooling Pc = 10 MW Cooling water = 1710 m3 / hr. Cooling by refrigerant R134a Vaporization Heat Hv. [kcal/kg] kcal / kg Mass flow rate mR [ kg/sec] Pc [kJ / sec] = 4.2 [kJ / kcal] x Hv. [kcal / kg] x mR [kg/sec] mR = 1000 / 4.2 / 40 = 6 [L/s] [ m3 /min.] [ m3 / hr.] Cooling Refrigerant = 220 m3 / hr.

18 Heat transfer capacity of refrigerants
WATER AIR NH3 R410A R32 Liquid Gas Te 37 35 Pe --- 1350.8 2139.9 kPaA Tc 32 1238.2 1975.6 Density 1 0.0012 0.587 0.0105 1.008 0.0883 0.912 0.0652 t/m3 Specific Heat 0.24 Mcal/t・℃ DT 5 Latent Heat 268 40.5 59.0 Mcal/t Velocity m/s Cooling Power 0.0072 157.3 14.1 40.8 17.9 53.8 19.2 Mcal/m2・s Note: Cooling Power is defined by Heat Transfer Capacity [Mcal/s] of 1m2 cross-section pipe;

19 Motor power for circulation of water and refrigerants
30 MW Heat Load (including other heat load) WATER AIR NH3 R410A R32 Liquid Gas Mass Flow Rate 5160 21500 96.3 637.0 437.3 t/h Velocity 1.0 5.0 m/s Pipe Size 1.35 35.60 0.24 0.81 0.47 0.71 0.41 0.69 m 5 1.3 0.2 kPa 1.00 1.82 5.00 16.7 Pipe Length 4000 2000 100 500 ⊿P 666.1 ⊿H 0 * Water Head 587 10.5 1008 88.3 912 65.2 ⊿P at H.X. 50 Total ⊿P 766 588.3 61.8 1008.2 138.5 Pe-Pc 112.6 164.3 Pump Efficency 60% % Motor Power 1318 No Need kW Moter Power 4.4% 0.0% / Cooling Power Ideal case: larger pipe size for water Water pipe size: 1m in dia. Note: In the case of water , head of flow and return cancelled.

20 Summary & Future Plan Cryogenic caverns should be constructed at the end of the access tunnels at every 5 km intervals of the main tunnel. The 4K and 2K cold boxes and distribution boxes should be installed in cryogenic caverns. The compressors will be installed in the far end of cryogenic cavern. The helium inventory should be stored as liquid for long shutdown of the cryogenic system. Extraction of heat from the deep tunnel economically is key issue. We need more study including new idea. Detailed engineering design study for the cryogenic system is needed, including topography of the site.


Download ppt "Cryogenic cavern in Asian site"

Similar presentations


Ads by Google