1 Professor S K Dubey,VSM Amity School of Business
OPERATIONS RESEARCH Professor S K Dubey,VSM Amity School of Business

2 Simulation

3 Contents Introduction Reasons for using simulation.
Steps in simulation process. Advantages, Disadvantages & Limitations of Simulation. Mont-Carlo simulation process Role of Computers in Simulation. Summary. 11/15/2018

4 Case1 A bombing mission is sent to bomb a military target, which is rectangular in shape and has dimensions 75 meter by 150 meter. The bombers will drop 10 bombs altogether, all aimed at the geometric centre of the target. It is assumed that the bombing run is made parallel to the longest dimension of the target. The deviation of the impact point from the aiming point is normal with mean zero & SD 50 meter in each dimensions. The deviations are independent random variable. Estimate the expected No. of bombs to be used. 11/15/2018

5 Case2 A bakery keeps stock of a popular brand of cake. Previous experience shows the daily demand pattern is as given below:- Daily Demand Probability Simulate the daily demand pattern 11/15/2018

6 Introduction Simulation is a quantitative procedure which describes a process by developing a mathematical model of that process and then conducting a series of organized experiments to forecast the behavior of the process. 11/15/2018

7 Reasons for using Simulation
Simulation may be the only method available. ( Space flight programme) It may not be possible to develop a mathematical solution. Actual observation may be too expensive. There may not be sufficient time to allow the system to operate extensively. Actual operation & observations may be too expensive. 11/15/2018

8 Steps of Simulation Process
Step 1:- Identify the problem. Step2:- Identify the decision variables. Step3:- Decide the performance criterion. Step4:- Construct a numerical model. Step5:- Validate the model. Step6:- Design the experiment. Step7:- Run the simulation model. Step8:- Examine the results. 11/15/2018

9 Advantages of Simulation
Approach is suitable to analyze large & complex real life problems which can’t be solved by use of quantitative methods. It allows the decision maker to study the interactive system variables & the effect of changes in these variables on the system. Simulation experiments are done on the model, not on the system itself. Simulation can be used as a pre service test to try out new policies & decision rules for operating a system before running the risk of experimentation in the real system. 11/15/2018

10 Disadvantages of Simulation
Sometimes simulation models are expensive & take a long time to develop. Ex: A corporate planning model. The simulation model does not produce answers by itself. The user has to provide all the constraints for the solutions which he wants to examine. It is trial & error approach. 11/15/2018

11 Limitations of Simulation
Simulation is not precise. It does not yield an answer but merely provides a set of the system’s responses to different operating conditions. Managers have still to generate the solutions. A good simulation model may be very expensive. It takes years to develop a suitable corporate model. All situations can't be evaluated using simulation. 11/15/2018

12 Monte Carlo Simulation
The Monte-Carlo technique uses random number. It is generally used to solve problems requiring decision-making under uncertainty & where mathematical formulation is impossible. 11/15/2018

13 Principle behind Monte Carlo Simulation technique
The principle behind the Monte Carlo simulation technique is to represent the given system by some known probability distribution. Then draw random samples from the probability distribution by means of random numbers. In case the system can’t be described by a known probability distribution function such as Normal, Poisson, Exponential etc, then an empirical probability distribution can be constructed. 11/15/2018

14 Monte Carlo Simulation
Step1:- Set up probability distribution for variables to be analyzed. Step2:- Build a cumulative probability distribution for each random variable. Step3:- Generate random numbers. Step4:- Assign an appropriate set of random numbers value for each random variables. Step5:- Conduct the simulation experiment by means of random sampling. Step6:- Repeat Step5 until the required number of simulation runs has been generated. Step7:- Design & implement a course of action and maintain control. 11/15/2018

15 Example (Case1) A bombing mission is sent to bomb a military target, which is rectangular in shape and has dimensions 75 meter by 150 meter. The bombers will drop 10 bombs altogether, all aimed at the geometric centre of the target. It is assumed that the bombing run is made parallel to the longest dimension of the target. The deviation of the impact point from the aiming point is normal with mean zero & SD 50 meter in each dimensions. The deviations are independent random variable. Estimate the expected No. of bombs to be used 11/15/2018

16 Discussion on Case1 (Target Parameters)
Impact Point Flight Line Y -----X---- 75 meters Aiming Point (0,0) 150 meters 11/15/2018

17 Discussion on Case1 Y : Line Error u : Range error deviate = (X-0)/50
X : Range Error Y : Line Error u : Range error deviate = (X-0)/50 -1.5/2 < u < 1.5/2 v : Line error deviate = (Y-0)/50 - 0.75/2 < v < 0.75/2 11/15/2018

18 Random Normal Table in Units of Standard Deviates (Z)
0.8 1.95 -2.92 0.34 -0.67 -0.7 -0.54 1.87 1.72 0.88 0.61 0.36 0.42 0.63 -0.9 -1.07 1.15 0.05 -0.48 -1.48 -0.24 0.47 -0.19 0.56 0.16 -0.49 0.24 1.46 1.28 -1.18 -0.32 -0.69 1.57 1.53 0.06 -0.66 2.22 -0.21 1.41 -0.08 0.14 -0.68 0.02 1.67 1.17 -1.75 0.54 2.47 -0.55 -1.13 0.46 1.16 -0.25 1.76 2.62 -0.61 -0.27 11/15/2018

19 Simulation Trial1 Bomb u v Result 1 0.8 -0.54 Hit 2 0.42 -0.48 3 0.16
1.95 Miss 4 1.87 0.63 5 -1.48 -0.49 6 -2.92 1.72 7 -90 -0.24 8 0.24 0.34 9 0.88 -1.07 10 0.47 1.46 5 Hits 11/15/2018

20 Simulation Trial 2 Bomb u v Result 1 -0.67 0.61 Hit 2 1.15 -0.19 3 0.9
-0.7 4 0.36 0.05 5 0.56 1.28 6 -1.18 -0.66 Miss 7 0.68 1.76 8 2.47 -0.32 9 2.22 0.02 10 -0.55 2.62 5 Hits 11/15/2018

21 Simulation Trial 3 Bomb u v Result 1 -0.69 -0.21 Hit 2 1.67 -1.13 Miss
-0.61 1.57 4 1.41 1.17 5 0.46 -0.27 6 1.53 -0.08 7 -1.75 1.16 8 0.16 0.06 9 0.14 0.54 10 -0.25 4 Hits 11/15/2018

22 Role of Computers in Simulation
It is difficult to perform simulations without computer. Computer aided simulation also does the sensitivity of the model. Simulation Languages :- GPSS (General Purpose Sys Simulation), SIMSCRIPT, Fortran, C, PASCAL, PL/1, LISP 11/15/2018

23 Procedure of Computer Simulation
Define the problem- nature, scope & importance. Build mathematical model. Write computer program of the model. Process the program on the computer. Evaluate the results of the computer simulation. Recommend a course of management action on the problem. 11/15/2018