Download presentation
Presentation is loading. Please wait.
1
The Mountain Ridge Team
Mountain Ridge Team Final Presentation The Ridge University Engineering Building May 15, 1998 Architect: Humberto Cavallin Engineer: Alec Zimmer Construction Manager: David Miller Owner Representative: Luciana Barroso The Mountain Ridge Team
2
The Mountain Ridge Team
Presentation Outline The Project Statement Early Proposed Concepts The Idea: Product, Evolution, and Process The Final Product Summary: The Team Process The Mountain Ridge Team
3
The Mountain Ridge Team
Project Definition Facility: A new 30,000sf academic building for The Ridge University School of Engineering with classrooms, labs, offices and auditorium Year: 2010 Location: Tahoe City, California The Mountain Ridge Team
4
Project Definition: Physical Constraints
Must use one of 2 existing footprints The Mountain Ridge Team
5
Project Definition: Physical Constraints
Must use one of 2 existing footprints 35’ height restriction Very heavy snow loads Moderate to high seismicity (Zone 3) Remote site with limited access The Mountain Ridge Team
6
Proposed Concept - Lshape1
The Mountain Ridge Team
7
Proposed Concept - Square1
The Mountain Ridge Team
8
Proposed Concept - Lshape2
The Mountain Ridge Team
9
Proposed Concept - Square2
The Mountain Ridge Team
10
Proposed Concept - Square2
The Mountain Ridge Team
11
The Mountain Ridge Team
The Iterative Process Square2 E C Lshape2 A O Square1 Lshape1 First Quarter Second Quarter The Mountain Ridge Team
12
The Mountain Ridge Team
Site Plan The Mountain Ridge Team
13
The Mountain Ridge Team
The Building 1 2 3 The Mountain Ridge Team
14
The Mountain Ridge Team
Activities Administrative Students Educational The Mountain Ridge Team
15
Architectural Evaluations - Floor 1
The Mountain Ridge Team
16
Architectural Evaluations - Floor 2
The Mountain Ridge Team
17
Architectural Evaluations - Floor 3
The Mountain Ridge Team
18
Architectural Evaluations - Section
The Mountain Ridge Team
19
Architectural Evaluations - Section
The Mountain Ridge Team
20
Engineering Loads- Gravity Loads
Dead Loads Including 25 psf floor & partitions 10 psf MEP equipment 83.5 psf for 6.5” slab and metal deck 109.6 psf total (205 psf is seismically effective) Live Loads Including 100 psf in halls & library 50 psf in offices 40 psf in classrooms The Mountain Ridge Team
21
Engineering Loads- Seismic and Snow Loads
223 psf Ground Snow 1.0 Importance Factor 0.6 Exposure D Factor Nominally Flat Roof 133 psf roof snow load (75% is seismically effective) Seismic Loads from 1994 UBC Z = 0.3 Seismic Zone 3 T = by Method A C = 2.75 for firm soil Rw = 8 compromise for this dual system Vbase = 608 kip Mot = 9426 k-ft The Mountain Ridge Team
22
Engineering Evaluations - Floor Details and Load Path
Composite steel deck - concrete slab Shallow beam sections Typical Sections: Beams sizes from W10x12 to W12x30, unshored construction All columns W12x40 to facilitate connections Shear connections only Cross Beam: W10x19, Typ. Ext. Girder: W10x22, Typ. Typ. Vertical Gravity Load Transfer Column: W12x40, Typ. 12” Shearwalls Resist All Lateral Loads Second Floor Beams - Plan View The Mountain Ridge Team
23
Engineering Evaluations - ETABS model
Verify period with modal analysis Evaluate deflections and interstory drift Verify load path assumptions Problems in model The Mountain Ridge Team
24
Engineering Evaluations - Cross Sections at Lines 1 and 3
Note typical sections and detail references The Mountain Ridge Team
25
Engineering Evaluations - Critical Connection Details
Third Floor Moment Frame Connection Detail The Mountain Ridge Team
26
Engineering Evaluations - Shear Wall-Beam Connection Details
The Mountain Ridge Team
27
Engineering Evaluations - Shear Wall Design
Resist all lateral loads, both seismic and wind Mot = k-ft per wall Vbase = 484 k No boundary zones No additional moment reinforcement Torsional effects are negligible The Mountain Ridge Team
28
Engineering Evaluations - MEP Assumptions
Steam heat and chilled water from central facility 15’ x15’ room provided on ground floor for equipment Circular ducts standard throughout with rectangular ducts in congested areas, 18” max. Small equipment rooms provided on all floors for advanced communications equipment Air requirements in auditorium are 20 CF/person/minute, given an approximate capacity of 250 people The Mountain Ridge Team
29
Engineering Evaluations - Three-Dimensional Model
The Mountain Ridge Team
30
The Mountain Ridge Team
Contractor - Site Plan The Mountain Ridge Team
31
Contractor - Fall 2011 Schedule
The Mountain Ridge Team
32
The Mountain Ridge Team
Contractor - Spring 2012 Schedule The Mountain Ridge Team
33
Contractor - Winter Respite Analysis
Impractical to weatherproof before winter weather hits Either shut job down during winter or rent tent for $42,000 per month Project can still be completed comfortably if dormant for <4 months Respite allows for coordination and planning The Mountain Ridge Team
34
Contractor - Estimate Details
Location adjustment factor of 1.15 $160/s.f dollars ($210/s.f dollars) 6% Contractor fee 10% Architecture and Engineering fee The Mountain Ridge Team
35
Contractor - Critical Phases of Work
Heaviest lift complete The Mountain Ridge Team
36
Contractor - Critical Phases of Work
Floors and roof complete The Mountain Ridge Team
37
Contractor - Equipment
Crane selection for steel erection 50T hydraulic rough terrain crane with 65’ boom Critical lift: 4 ton beam at 60’ radius Gradall material handlers The Mountain Ridge Team
38
Contractor - Estimate Progression
The Mountain Ridge Team
39
Contractor - Schedule Loading
2011 2012 The Mountain Ridge Team
40
Contractor - Budget Breakdown
The Mountain Ridge Team
41
Contractor - Inflation Analysis
The Mountain Ridge Team
42
Contractor - Construction Cost Index
The Mountain Ridge Team
43
Product, Evolution, and Process
A/E/C/O Height variance Ramp in rear of building 2 plane vs. 4 plane roof system C/E Beam spacing Floor system A/E/O Window wall Balcony in rear 3rd floor Shearwall Entrance façade column locations A/C/O Cladding Excavation costs The Mountain Ridge Team
44
Floor and Structural Systems - E/C Trade-off Analysis
Concrete for floor decks: Lightweight concrete? Normal weight concrete? Steel Framing: Moment resistant frames - shop welded? Eccentrically braced frames? Simple gravity frames? The Mountain Ridge Team
45
Beam Spacing - E/C Trade-off Analysis
20’ column grid Beams can be spaced at 10’ or 20’ on center? Larger beam spacing means fewer pieces, fewer connections and thus faster construction. But, also requires deeper slabs Cost basically unaffected Long-term usability chosen over short-term construction schedule benefits The Mountain Ridge Team
46
Basement Layout vs. Excavation - A/E/C/O Trade-Off Analysis
Building Functioning Space allocation slope floor, owner requirement Costs Activities and program requirements O/A Evaluation The Mountain Ridge Team
47
Ramp in Rear of Building - A/E/C/O Trade-Off Analysis
Relationship with the excavation Development of the option Rejection of the ramp alternative The Mountain Ridge Team
48
East Balcony and Column Locations - A/E Trade-Off Analysis
Owner requirements for a balcony Architectural solution - cantilever Engineer’s response with additional columns - spares moment connections Added Columns Plan of East Balcony The Mountain Ridge Team
49
Window Wall and West Balcony - A/E/O Issues
The Requirements of O/A/E The communications breakdowns The positioning of walkway supports The Mountain Ridge Team
50
Exterior Cladding - A/C/O Cost vs. Appearance Concerns
Plaster or stone Stone more has institutional, timeless appearance Stone $1 million than plaster Stone/plaster combination chosen The Mountain Ridge Team
51
Product, Evolution, and Process
The building solution is the PRODUCT The A/E/C team interaction is the PROCESS The iterations along the way are EVOLUTION Process is the Cause Evolution is the Effect Product is Summation of those effects The Mountain Ridge Team
52
Evaluation of Communication Media and Resources
Hardware vs. Software Progress in the Future The Mountain Ridge Team
53
At the Core of Our Process...
Complementing skills Sharing points of view Mutual concern for cross disciplinary problems Mentor Interaction The Mountain Ridge Team
54
Summary of Team Process
Importance of information flow transfer Team dynamic The role of the owner O C A E The Mountain Ridge Team
55
Creating a Better Solution
Dave’s Axiom 2 times better process = 8 times better product! The Mountain Ridge Team
56
The Mountain Ridge Team
We acknowledge the support of Luciana Barroso and the Course Mentors! The Mountain Ridge Team
Similar presentations
© 2025 SlidePlayer.com Inc.
All rights reserved.