1 Federal Aid Process for Local Agency Federal Aid Projects
The purpose of this presentation is to provide important information to you about the DCP. With this document we hope to provide you with suggestions/considerations in the development of your project. There are many steps involved in the DCP process and not every one may apply to your project. We STRONGLY encourage you to always navigate to the DCP Checklist online. Do NOT save it or any of the many forms on your computer. Refer to the State Aid Manual for more information and explanations of the requirements for a federal aid project.

2 Acronym/abbreviation list
ATP = Area Transportation Partnership Army COE/Corps = Army Corps of Engineers COE = Corps of Engineers (US Army) DBE = Disadvantaged Business Enterprise DCP = Delegated Contract Process DNR = Department of Natural Resources DSAE = District State Aid Engineer FA = Federal Aid FAHP = Federal Aid Highway Program FHWA = Federal Highway Administration FTA = Federal Transit Administration GM (greater MN) = Counties outside the Metro district LPA = you, the Local Public Agency (county or city) MnDOT = Minnesota Department of Transportation MPCA = Minnesota Pollution Control Agency NPDES = National Pollutant Discharge Elimination System OJT = On the Job Training PDR = Project Development Report SALT = State Aid for Local Transportation STIP = State Transportation Improvement Program TIP = Transportation Improvement Program

3 Overview of content Presentation content
This is a general “101” overview of the basics This is not intended to cover every detail of the federal process There are different requirements for metro and outstate Every project is unique but similar

4 DCP – what in the heck is that?
Delegated Contract Process What’s been delegated? Who is it delegated to? How is it delegated? What does that mean to and for me exactly? First we’ll look at what has been delegated – which is, Oversight of the Federal Program.

5 Presentation topics The law and how it’s delegated Funding
Project development and design Letting and awarding Construction administration Resources

6 The law and how it’s delegated

7 The law and how it’s delegated How is it delegated?
U.S. Department of Transportation Responsible for ensuring the U.S. has a fast, safe, efficient, accessible and convenient transportation system that meets vital national interests and enhances the quality of life of the American people, today and into the future. Federal Aid Highway Program Supports state highway systems by providing financial assistance for the construction, maintenance and operations of the Nations 3.9 million-mile network. Federal Highway Administration The agency within the U.S. Department of Transportation (DOT) and charged with implementing the Federal Aid Highway Program (FAHP) in cooperation with states and local governments. The Contract, the Federal Aid Highway Program – Federal Government (through the US DOT) with the American people. US DOT: Congress and the President agree on a Program of spending for new construction, reconstruction, preservation & improvement on roads, bridges. Funds appropriated for the Federal Aid Highway Program, which is administered through the Federal Highway Administration, an agency within the US DOT.

8 The law and how it’s delegated Hierarchy of the law
Title 23 U.S.Code REGULATIONS 23 Code of Federal Regulations The law is passed by Congress and supported through Regulations, Policy and Directives. FHWA Policy & Directives: Created by FHWA Headquarters (applied nationwide) or locally (applied statewide)

9 THE LAW I mean, really, Virtually no flexibility from the law

10 The law and how it’s delegated Regulations and policy
Regulations implement the law and have the force and effect of law, with some flexibility on what constitutes compliance with a particular regulation. Regulations are how the Federal Highway Association (FHWA) has interpreted and how they will implement the law. Regulations - slight flexibility from the law Policy and directives give additional guidance to those who administer the program. Policy - substantial flexibility from the law

11 The law and how it’s delegated Other laws applicable to the DCP
Other federal laws apply as part of receiving federal funds National Environmental Policy Act Clean Air Act Limit FHWA funding unless the project has been developed within their guidelines Occupational Safety and Health Act Americans with Disabilities Act Must be followed based on their applicability Civil Rights – applies if agency receives any federal funding. State laws and regulations must also be followed if applicable (23 CFR 1.9(a))

12 Through the Stewardship and Oversight Agreement
The law and how it’s delegated FHWA delegates to the state – the who and the how Through the Stewardship and Oversight Agreement Extent to which FHWA delegates responsibility of FAHP to state Governs partnership between FHWA and state DOTs Establishes DOTs administration of the FAHP, through approval and oversight responsibilities, on local federal aid projects. State DOT is expected to exercise judgements similar to the FHWA based on federal laws, regulations and policies in the areas of transportation planning activities, assessing environmental impacts, project design requirements, civil rights protections, purchase of rights of way, administering construction projects and maintenance activities. Every State has a Stewardship and Oversight Agreement which is uniform among all the states and defines how the FAHP will be handled by the states. Required to receive federal funds.

13 The law and how it’s delegated More delegation through a Memorandum of Understanding
Memorandum of Understanding is a unique document between the FHWA and each state DOT Outlines state specific directives for how the FHWA and the state shall operate So, Stewardship is Efficient and effective management of public funds Activities to deliver the FAHP consistent with laws, regulations and policies Between FHWA and each state DOT – required to receive funding Extent to which FHWA delegates responsibility of FAHP to state And Oversight is The compliance or verification component of Stewardship activities

14 The law and how it’s delegated What did you just tell me?
Changes to any of the following can affect the DCP The law Regulations Policy Stewardship and Oversight Agreement And Memorandum of Understanding

15 The law and how it’s delegated Delegation from DOT to locals
FHWA is tasked with upholding ALL federal laws. FHWA delegates the authority for delivering the FAHP to MnDOT through Stewardship and Oversight Agreement. MnDOT State Aid meets with FHWA regularly to assure that State Aid delivers projects that fulfill the federal law. Minnesota delegates authority for delivering the FAHP to locals through DCP Agreement for Federal Participation in Construction (Minnesota Statutes ). Locals – By following the DCP and State Aid Manual, remain in compliance with federal laws. DCP Agreement for Federal Participation in Construction -

16 The law and how it’s delegated State Aid’s role?
State Aid is like the filling between the FHWA and local governments, ensuring compliance and providing oversight on federal aid projects. State agencies MnDOT PCA DNR and federal agencies FHWA FTA Army Corp of Engineers Administrator Manager Liaison Negotiator Facilitator Advocate Resource Partner Mentor State Aid’s reputation and focus on customer service with our external partners is a product of our past leadership. As we begin to look forward, we will continue to have high expectations for external customer service and relationships, but we will also start to focus on building the internal culture within MnDOT. State Aid Local Agencies Counties Cities Townships

17

18 The law and how it’s delegated How are roadways funded with federal funds?
Congress appropriates money from the Highway Transportation Fund to fund the program (law), becoming federal aid funds. Federal aid funds distributed by formulas specified in the law. Distributed to each state within funding categories (ex: Highway Safety Improvement Program) State DOTs are the designated recipients or “grantees” for the funds Local Public Agency’s (LPA) are sub-recipients or “sub-grantees”, meaning LPAs receive funds via the state DOT. State DOTs oversee selection of projects and ensure that federal requirements are met, including eligibility. FHWA federal aid essentials for LPAs FHWA federal aid essentials for LPAs -

19 So, you think this stretch of road might be ready for some work?

20 Or it might be time to finally build that bridge?

21 Don’t worry – the DCP is here to guide you through your federal project!

22 Funding

23 Funding Federal aid funding program
This is a REIMBURSABLE program The work must be completed before the federal dollars are reimbursed This is NOT a grant!

24 Funding Funding overview
General Overview Project funding development State Transportation Improvement Program (STIP) Funding deadlines Program year extensions Amendments – STIP and Transportation Improvement Program (TIP)

25 Funding Project funding development
Funding source Identify project, get a sponsor and submit an application Project selected by Area Transportation Partnership for funding Project added to Area Transportation Improvement Program or TIP Project added to STIP STIP submitted to FHWA/Federal Transit Administration (FTA) –> FHWA/FTA approves STIP

26 Funding Project sponsor
In order to be a recipient of a federal aid project, the recipient must either be a public agency or the project must be sponsored by a public agency on behalf of the recipient. The project recipient/sponsor must be qualified to administer a federal aid construction contract. The DSAE will determine if a project sponsor is qualified. Qualification is determined on a project-by-project basis. If a project sponsor elects to use consultants for engineering services, the LPA shall provide a full-time employee of the agency, qualified to be in responsible charge of the project. To be qualified, the local public agency must be adequately staffed & suitably equipped to undertake & satisfactorily complete the work. Projects must receive adequate supervision & inspection to insure that projects are completed in conformance with approved plans & specifications

27 Funding Sponsoring projects for non State Aid partners (ex: Safe Routes to School)
Agencies which are non State Aid (not identified as State Aid city or county) may undertake a federal aid project but must be sponsored by the county they reside in and need approval by the District State Aid Engineer (DSAE). The sponsor will assist in the preparation of and sign the environmental docs required for the project to meet any state and federal requirements. The sponsor will also aid in the preparation of and sign the construction plans as a registered Professional Engineer as appropriate. The sponsor will act as the fiscal agent, fronting any necessary funds and passing through the federal funds from the FHWA and the DOT. A separate agreement between the project proposer and the sponsor is required to outline roles and responsibilities specific to the individual project. Ultimately the sponsor (not the project proposer) is responsible for adherence to the DC Process. It is advisable to have a kick off meeting with a non State Aid project proposer (and their consultant if applicable) to discuss the DC process and set up terms through an agreement between the two agencies.

28 Funding Project funding
Review the project funding sources Funding sources will determine the plan preparation and review requirements. An SP number denotes federal funds, an SAP number does not have federal funding. You may have multiple project numbers for one plan with multiple partners and/or multiple state aid routes. See Finance Section on how payments are made. See slide on eligibility for hints and help on Par (Fed funds eligible) and NonPar (not federally eligible). Possible combinations: Federal Aid (FA) plus State Aid (SA) and/or State and/or multiple local jurisdictions Other State Aid Program funds, i.e. Bridge Bonds, Disaster Funds, Local Road Improvement Program, etc. Each combination of funding requires a unique column in the SEQ and EE. Each SP# requires a unique column in the SEQ and EE. State Aid project numbers can be requested through an on line form or on a fill in .pdf that can be ed to your DSAE or other assigned District Staff. Does your project have multiple partners? Will you or your partners be using State Aid, Federal Aid or State funds? Is your project on more than one State Aid route?

29 Project initiation

30 All state and local transportation projects with:
Funding STIP funding All state and local transportation projects with: Federal highway funding Federal transit funding Special federal funding packages 100 percent state funding

31 Funding STIP funding (continued)
Federal Funding Sources Transportation Alternatives Program Surface Transportation Program Congestion Mitigation and Air Quality Highway Safety Improvement Program Others (may vary from metro to outstate) Approximately $80 million available in the metro annually Approximately $82 million available in greater Minnesota

32 Funding STIP funding (continued)
STIP is developed and updated on an annual basis STIP is approved by the FHWA and Federal Transit Authority STIP has a four year outlook (2018 – 2021)

33 STIP

34 STIP

35 STIP

36 Funding Funding deadlines
STIP/TIP follows state fiscal year (July 1 to June 30) FY 2018 starts July 1, 2017 and ends June 30, 2018 For most types of federal funds, authorization must be requested by June 1 of the fiscal year in which it appears in the STIP Calendar Math State FY-Begins July 1 of the year proceeding Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Federal FY - Begins October 1 of the year proceeding Calendar Year - Begins January 1 of current year

37 Funding Funding deadlines (continued)
Learn requirements for your district Contact district State Aid office or engineer Do not need project to learn more about deadlines Establish a project schedule June 1 deadline determines project delivery schedule Several project milestones needed before June 1 Missing June 1 deadline can jeopardize funding Need to meet original program year/fiscal year in which your project appears in the STIP

38 Funding Funding deadlines (continued)
Program Year Extensions (outstate) Contact district State Aid office or engineer Program Year Extensions (metro) Maximum of one year extension Need approval for extensions Approval is not automatic Extension request deadlines (metro – December 31st) Funding in next program year is not guaranteed 11/14/2018

39 Metro – program year extension financial implications
Federal Funding becomes available for reimbursement Program Year 2018 2017 2019 2020 2021 Program Year Extension (Project must be delivered) Local Agency needs to finance Metro – program year extension financial implications

40 Funding STIP/TIP amendments
Funding is limited to the original scope Different levels of amendments Formal and administrative Amendments can extend process Formal/metro: 3 months Administrative: 2+ weeks Authorization cannot be requested until STIP amendment is approved (June 1) Contact district State Aid office or engineer

41 Funding Formal STIP/TIP amendment examples
Adding or removing significant elements of the project Major change in project limits A phase of work is added and increases the cost Increase in total cost of project exceeds guidelines Project not listed in the STIP See STIP Amendment Guidance for more information STIP Amendment Guidance -

42 Project development and design

43 Project development and design Overview
Funding received, now what? Federal DCP Checklist Federal process requirements Agreements Project development reports Right of way process Submittal milestones DCP Checklist -

44 Project development and design Overview (continued)
Plan preparation (State Aid Manual and State Aid Rules) Federal design regulations Common plan errors Proposal Pre-letting process LPA prepares and submits Project Memo and Plans, including right of way and utility documentation. Follow SA Manual and SA Rules for design Plan Errors: Not following Not following federal eligibility guidance. Not matching the federal funds correctly (eg CSAH match vs CR match). Proposal: Make sure to follow the State Aid Electronic Proposal Documents, not MnDOTs State Aid Manual - State Aid Rules - Proposal -

45 Project development and design Funding received, now what?
Kick-off meeting Get stakeholders, design team, and State Aid involved Contact DSAE Identify documents needed Develop a preliminary project delivery schedule Determine if your agency is adequately staffed to complete the work Verify if design fees are eligible for federal funding Special process for using and selecting consultants Review and follow the State Aid Manual and federal DCP checklist Schedule Very Important Dates: Environmental Documents submitted to DSAE by December 1. Plan submitted to DSAE by April 1. State Aid Manual – DCP Checklist -

46 Project development and design Federal DCP Checklist
The DCP Checklist outlines major steps in the Delegated Contract Process It is an extremely valuable resource that walks you through the federal process and all of the documents that are needed to maintain funding Print off new checklist with each new project Follow all steps in the checklist and do not move ahead until each step is completed Submit all forms and submit in a timely manner Forms contain information needed to comply with federal regulations Failure to provide info could jeopardize federal funds This list covers plan development and contracting processes only For information on the environmental review process, refer to the Chapter 5.1 Environmental and Design Studies in the State Aid Manual As you go through the checklist, you’ll notice it has tasks in two columns. Local Public Agency MnDOT This column shows what And this column shows you need to do. what State Aid does in response. DCP Checklist - State Aid Manual –

47 DCP Checklist links

48 Project development and design Full oversight process
Used on FHWA Projects of Division Interest (PODI) Projects on the National Highway System Projects funded by other FHWA Divisions - Federal Lands Access Program In addition to regular plans process: Plans, specifications, estimate and ad must be reviewed and approved by FHWA prior to advertising and bid. FHWA must concur in award of PODI’s FHWA must concur in contract changes on PODI’s Full Oversight Process refers to projects where the FHWA “takes back” some of the delegated authority. These projects are few and far between, but require more coordination between the FHWA, MnDOT and the Local Partner.

49 Project development and design Federal process requirements - agreements
MnDOT must follow state and federal regulations Regulations govern how MnDOT must act as an agent in receiving and disbursing federal funds to local agencies Agreements may vary by funding source Follow DCP Checklist and coordinate with the district State Aid office or engineer

50 Project Development Report
Project development and design Federal process requirements – Project Development Report Project Development Report National Environmental Policy Act mandated Consider project impacts Evaluate possibility of avoiding impacts Public involvement Document analysis Project Memo Environmental Assessment Most local federal aid projects utilize a Project Memo.

51 Project development and design Federal process requirements – Right of Way process
All city and county acquisitions must conform with applicable federal policies and regulations, regardless of funding source (State Aid Manual, Chapter 5.2 Right of Way) If condemnation required, process can take 6-8 months Typically drives project schedule Right of Way Certificate 1 or 1A required before authorization State Aid Manual -

52 Project development and design Submittal milestones
December 1 deadlines Project Development Report submitted February 28 deadlines Condemnation proceedings formally initiated (if needed) April 1 deadlines Project in an approved STIP Project Development Report approved Plan submitted for review by State Aid for standards, eligibility, funding, and structural design Right of Way Certificate 1 or 1A approved or condemnation initiated (Condemnation proceedings formally initiated by February 28)

53 Project development and design Submittal milestones (continued)
June 1 deadlines Authorization request deadline for federal funding Approved construction plan (all signatures) Engineers Estimate Special provisions (metro) Utility Relocation Certificate (if impacts to utilities) Required permits: COE, DNR, NPDES, watershed, etc. Fee and title possession for condemned properties

54 Project development and design Submittal milestones (continued)
Deadlines should be adjusted to meet desired construction schedule Plan routing timeline impacted by number of functional groups reviewing the plan Bridges, signals, work on trunk highway Add 6-10 weeks for plan routing if MnDOT funds are part of the project

55 Project development and design Plan requirements
Plan must agree with Project Development Report and STIP Follow guidelines outlined in Chapter 5.4 Plans and Proposals of the State Aid Manual Use correct federal aid signature block with required functional group signatures State Aid Manual -

56 Project development and design Federal design regulations
Proprietary items Need at least three acceptable alternates with “or approved equal” statement Public Interest Findings if using proprietary items Buy America Buy America restrictions apply to entire project, including non-federal items Max of $1,500 non-U.S. steel without prior approval MnDOT qualified products list DOES NOT meet Buy America.

57 Project development and design Federal design regulations (continued)
ADA compliance and implementation FHWA is responsible for enforcement of ADA requirements on projects utilizing federal funds Provide pedestrian curb ramps where they are required Provide detectable warnings (truncated domes) on all new and existing ramps within the project limits To receive funding in 2021, a Local Agency must have, or be developing, an ADA Transition Plan.

58 Project development and design Common plan errors
Funding columns All federal eligible items in one column labeled “Participating” Non federal items (state aid eligible) in separate column labeled “Non Participating” Non federal/state aid items in separate column labeled “Local Funds” Federal aid section of state aid checklist not filled out/submitted Proprietary items In Federal Aid Plans, PAR always refers to federal participation. Non PAR are those items not federally eligible.

59 Disadvantaged Business Enterprise (DBE) goals
Project development and design A note about phased projects and DBE goals Phased projects When a SAP project precedes a fed project (even HSIP) a Project Memo must be processed in advance of the non-federal project to cover all the phases of work on that road. Disadvantaged Business Enterprise (DBE) goals DBE goals are established by type of work, location of work, when work will occur and timeframe to accomplish work.

60 Project development and design Proposal
Required sections (download for each project) State and federal wage rates Current materials control testing Equal Employment Opportunity sheets DBE sheets, whether the project has a goal or not A project funded with some other kind of funding (DNR) may have a few additional sections in their proposal. SALT can help you out.

61 State aid proposal sequence online (all/federal/state)
This table can be found on the Electronic Proposals webpage. Electronic Proposals webpage - State aid proposal sequence online (all/federal/state)

62 Project development and design Pre-letting process
Complete all items needed for authorization See “Submittal milestones” Authorization must be requested by June 1 FHWA authorization required prior to advertising

63 Project development progression

64 Letting and awarding

65 Letting and awarding Letting an awarding overview
General overview Letting and awarding milestones Advertising Bid opening Awarding Post-award submittals

66 Letting and awarding Letting and awarding milestones
Authorization received from FHWA Approved advertising language Advertise for bids Bid opening Office of Civil Rights approval Award (after Office of Civil Rights approval) Notice to proceed with construction SALT (Greater MN) or Project Manager (Metro) requests authorization once the approved plan, RW Certs, approved PM are submitted.

67 Letting and awarding Advertising
Federal aid project manager provides required ad language to LPA LPA submits a copy of the completed ad as it will be published for review/approval Do not place ad until approved by federal aid project manager

68 Letting and awarding Advertising timelines
LPA discusses letting date with federal aid project manager Counties: follow minimum county advertising requirements (Minnesota Statute ) Cities: follow minimum city advertising requirements (Minnesota Statutes ) Federal requirement – one ad per week for three weeks, with at least 10 days between the last ad date and bid opening

69 Letting and awarding Letting
Bid opening Bid opening procedure is found in the construction chapter of the State Aid Manual Verify all documents have been submitted Post-bid procedures Follow DCP Checklist for post letting instructions Submittals to the Office of Civil Rights State Aid Manual - DCP Checklist -

70 Post bid with DBE goal

71 Letting and awarding Awarding
Do not award until clearance from the Office of Civil Rights has been received Typical the Office of Civil Rights approval takes two weeks DBE clearance could add more time if goal was not met Board or council meetings may add more time DBE Clearance. If your project has a goal and it’s been more than three weeks since the contractor submitted the required documentation, and you’ve heard nothing. Contact SALT.

72 Letting and awarding Post award submittals
Follow the DCP checklist Need to complete in a timeline manner Requests for payment cannot be made until project setup is completed Check the funding summary when it is ed to you. Notify Mark Channer (SALT) or your Project Manager IMMEDIATELY if it is in error. Corrections can be made for the first week or two, but not later than that.

73 Project bid and award progression

74 Construction administration

75 Construction administration Overview
State aid vs. federal aid Labor compliance Civil rights compliance Contract change process Project closeout and final payment Audits Federal inactive list

76 Construction administration State aid vs. federal aid
Federal aid construction administration follows the same process and requirements as state aid projects. MnDOT Spec Book State Aid Manual Schedule of Materials Control (MnDOT or State Aid) Field, plant and lab testing Equal Employment Opportunity provisions Labor compliance

77 Construction administration State aid vs. federal aid (continued)
DBE goal On-the-Job Training requirements Buy America Proprietary items Independent assurance testing Independent cost estimate required

78 Construction administration State aid vs. federal aid (continued)
Submit payment requests (monthly) DCP payment request form and funding split documentation Project closeout and final payment submittals Follow DCP checklist and forms

79 Construction administration Primary labor compliance items
Labor monitoring Certified payrolls submitted weekly Field interviews completed by field representative Payroll rates checked against State and Federal wage rates Payroll also checked against field interviews and site records Labor monitoring is a main item checked during audits

80 Construction administration Primary labor compliance items (continued)
Trucking Certified trucking reports submitted monthly Field interviews completed by field representatives Trucking rates checked against state trucking rates Truck reports checked against field interviews and site records

81 Construction administration Contract change process
Contact State Aid for discussion on eligibility Request price from contractor Independent cost estimate from MnDOT estimating MnDOT can review legal language if desired Contractor and agency sign document Execute change State aid signature for funding eligibility

82 Construction administration Contract language, the good and bad for eligibility
The Engineer has Determined Engineering Judgment Safety Restocking Fees Change Condition Unforeseen Condition Differing Site Conditions The BAD Damages Higher Standard Preference/Desired Upgrades Aesthetic Upgrades Surplus Materials City/County Requested Resident Requested Incentives Not in Original Contract Acceleration Plan Error Rework, Rebuild, Regrade, Re-Anything Outside Project Limits

83 Construction administration Project closeout/final payment
DCP final submittal Final DCP payment request Overrun form (If additional federal funds needed) Copy of final voucher Copies of all change orders, work orders and supplemental agreements Overrun/underrun report for contract quantities

84 Construction administration Project closeout/final payment (continued)
Materials exception summary List of certified testers MnDOT Bituminous Office list of exceptions* MnDOT Concrete Office list of exceptions* Copy of documents for deducts/penalties Independent Assurance documentation* *If services not provided by MnDOT, provide supporting documentation from organization providing the services

85 Construction administration Project closeout/final payment (continued)
Final inspection report (signed by State Aid) Cost distribution spreadsheet State Aid Payment Request Backsheet item costs

86 Project construction progression

87 Construction administration Audits
All federal projects are subject to auditing for review of compliance Main items Labor/civil rights compliance Testing and certificates Documentation of payment/quantities Contract changes Compliance with plans and specifications

88 Construction administration Federal Inactive List
No expenditures for 12 months Ensure timely closeout of federal aid projects Need explanation and plan to get finalized Funding could be jeopardized if acceptable reasoning not supplied

89 Resources

90 Resources State Aid website Metro State Aid website State Aid Manual
DCP Checklist Contract Administration Forms MnDOT Construction Tools webpage MnDOT ADA website State Aid website - Metro State Aid website - State Aid Manual - DCP Checklist - Contract Administration Forms - MnDOT Construction Tools webpage - MnDOT ADA website -

91 Questions? Contact your DSAE.