1 ND Downstream Watersheds Comprehensive Detention Planning
February 15, 2013 2nd Street / Downtown Flood Control Project Option 1F City Commission Meeting December 9, 2013 Kick-off Meeting

2 Option 1F Minimal Disturbance Zone (MDZ)
Limited Disturbance Zone (LDZ)

3 Existing Conditions

4 Proposed with Project

5 Existing Conditions

6 Proposed with Project

7 Existing Conditions

8 Proposed with Project

9 Existing Conditions

10 Proposed with Project

11 Existing Conditions

12 Proposed with Project

13 Visualization with Project

14 Base Plan

15 Future Consideration - Reduced Closure Length?

16 Future Consideration - Reduced Height?

17 Base Plan

18 Future Consideration - Reduced Height?

19 Future Consideration - Reduced Height?

20 Recommended Motion Concur with the recommendations of PWPEC and approve the Option 1F as the preferred alignment for the floodwall and 2nd Street, as well as approving the removal of 3rd Avenue North between 2nd and 3rd Street N.