Presentation is loading. Please wait.

Presentation is loading. Please wait.

SC1R Cold Box PDR Overview

Similar presentations


Presentation on theme: "SC1R Cold Box PDR Overview"— Presentation transcript:

1 SC1R Cold Box PDR Overview
SC1R Cold Box Preliminary Design Review K Dixon Monday, November 12, 2018

2 Review Committee Charge
Does the process design meet the stated Accelerator requirements? Is the cold compressor design requirements documentation ready for procurement? Is the heat exchanger design requirements doc ready for procurement? Are the planned modifications to the infrastructure suitable for cold compressor operations? Does the commissioning strategy presented have a favorable chance of success? Is the plan for removing the existing cold box sound? Is the plan for installing the new cold box reasonable? Does the vessel look like it can be easily fabricated at a reasonable cost and structurally sound? Does the internal piping allow room for access to the critical components? Are the technical risks accounted for and suitably addressed for a preliminary design? SC1R PDR Overview

3 SC1 History Delivered by CVI using 4 LN-cooled Cold Compressors (CC’s) in 1990 Commissioned in 1994 Isolated from system in 1999 Reconfigured to include 5 CC’s, increased HX NTU’s, thermosiphon cooling, volumetric and flow stability, etc. Re-commissioned in fall of 2013 CC4 failure in spring of 2015 Recovered in fall of 2015 CC5 failure in spring of 2017 Cold Compressor Advisory Team (Rode, Oren, Arenius, Howell, Freyberger, Ganni, Klebaner) unanimously recommended replacing SC1 during June ‘17 meeting. Presently supporting 2K operations. SC1R PDR Overview

4 CHL1 SC1 Cold Compressor 4 Failure
Compressor 4 failed Magnetic bearing cabinet control problem resulted in hard rotor landing at high speed that damaged back up ball bearings, rotor, etc. Spare compressor borrowed from SNS and modifications performed to be ready to install it for fall FY15 run Failed compressor sent to France Manufacturer repairing using spare parts Unit returned after two years Finishing a test program to verify health Readiness uncertain SC1R PDR Overview

5 CHL1 SC1 Cold Compressor 5 Problem
Problem traced to internal broken wire for bottom rotor radial position sensor Least operating hours Wire repaired and others checked Compressor tested warm Bearings energized Properly levitated Rotor spun at high speed Compressor installed and running successfully SC1R PDR Overview

6 Overview of SC1R DOE Science Lab Infrastructure (SLI) Funded Schedule
$8M Includes design, cold box and spare cold compressors Installation, interfacing piping and electrical wiring/panels not presently included Schedule Conceptual Design Complete 9/30/17 CB Design Completion 6/29/18 Cold Compressor Delivery 12/21/18 CB Assembly Complete 12/20/19 Critical Path Project Complete?? 12/23/20 Conceptual Design Use present location Use 5 external water-cooled CC motors with VFD’s and long-life bearings Could use similar/same size as MSU & LCLS2 Maintain Bayoneted Connections incl 2K Return Header Keep large 2K/4K HX inside cold box Vacuum break at LP Return header considered but eliminated Platform for upper shell access SC1R PDR Overview

7 Overview of SC1 (cont.) Cold Box Structural Shell Internals
Contracted build to print ASME BPVC design requirements Painted carbon steel, SA-517, Gr 70 Inverted st. steel nozzles & flat plates with domed heads Allows room for discharge nozzles Avoids large flat head Internals Contracted build to print along with shell ASME B31.3 design requirements Use similar HX specification as SC2 Bellow-sealed control valves Partial LN2 shielding for 2K piping Overall Dimensions 17’ tall x 10.5’ dia <28 T weight SC1R PDR Overview

8 SC1R P&I Diagram SC1R PDR Overview

9 Cold Compressor Requirements
General 5 CC’s in series Mass flow controlled by adjusting fixed- ratio speeds in CC’s 1-4 during steady state operations CC5 speed controlled using its suction pressure Casings Design per ASME BPVC and API 617 K design pressure Motors VFD controlled Externally accessible Design conforming to NEC Bearings Long-life, 5 yr 5-axis support Fully instrumented SC1R PDR Overview

10 Cold Compressor Requirements (cont.)
Operating Conditions Maximum 250 g/s flow ≤ K, inlet conditions 1.2 < 30 K discharge Nominal 200 g/s flow K, inlet conditions SC1R PDR Overview

11 ‘2K/4K’ Heat Exchanger Requirements
General 1.5 kW duty, 3 NTU Brazed aluminum plate-fin constr. Includes Al/SStl transition joints Design conforming to API Std 662 Constructed to ASME BPVC— ‘U’ stamped Parameter Supply Stream Return Stream Flow 250 g/s Inlet Temperature 4.5 K 2.2 K Outlet Temperature 2.5 K 3.3 K Max Dif Pres 1.7 mbar 2 mbar Design Temp 340 K 2 K Design Pressure 350 psi 100 psi Inlet/Outlet Nozzle ≤ 3 NPS ≤ 10 NPS SC1R PDR Overview

12 Safety Considerations
Removal and Installation will be performed in close coordination with ESH&Q personnel Most equipment will be designed/procured using national consensus codes Safety related analyses will be included in the Final Design Review The Installation and Removal, including safety aspects, will be included in the Final Design Review OR Installation Design Review SC1R PDR Overview

13 Cold Compressor Reqmts Heat Exchanger Reqmts Safety
Charge History Failures Overview Cold Compressor Reqmts Heat Exchanger Reqmts Safety Monday, November 12, 2018


Download ppt "SC1R Cold Box PDR Overview"

Similar presentations


Ads by Google